Latest 10 changes, newest first
Correction
QTS Data Centers — New Albany 1 campus · New Albany, OH · RecordEvidence review note
Gilroy Data Center · Gilroy, CA · Evidence reviewEvidence review note
Project Mitten · Saline Township, MI · Evidence reviewCorrection
Microsoft — New Albany campus · New Albany, OH · RecordCorrection
QTS Data Centers — New Albany 1 DC2 · New Albany, OH · Record evidenceEvidence review note
Project Jupiter · NM · Evidence reviewCorrection
QTS Data Centers — New Albany 2 DC2 · New Albany, OH · Record evidenceCorrection
QTS Data Centers — New Albany 2 campus · New Albany, OH · RecordCorrection
QTS Data Centers — New Albany 2 DC1 · New Albany, OH · Record evidenceEvidence review note
Project Sail · GA · Evidence review
Every change, grouped by kind, follows: verdict changes, field corrections, evidence review notes, records added and lifecycle events.
Verdict changes
21 September 20262 entries
Correction · 21 September 2026 · Editorial classification update
Sabey — Decatur Technology Park → Power / cost allocation
Field Power / cost allocation
From Partially supported
To Unknown
Why A developer-authored, site-specific commitment does not establish statewide customer protection. The question now separates what the petitioner promised from what remains unknown.
Evidence re-reading of the sources already cited on this claim; no new source.
Correction · 21 September 2026 · Editorial classification update
Meta — Lebanon → City impact payment
Field City impact payment
From Supported
To Not independently verified
Why The economic-development announcement establishes that the term was announced, but the controlling agreement and any payment records remain unavailable.
Evidence re-reading of the sources already cited on this claim; no new source.
16 September 20261 entry
Correction · 16 September 2026 · Editorial classification update
Meta — Jeffersonville → Cooling + water
Field Cooling + water
From Company claim
To Unknown
Why The page tests a common inference about what the announcement establishes; Meta did not make the cooling-and-water statement shown.
Evidence re-reading of the sources already cited on this claim; no new source.
14 September 202611 entries
Correction · 14 September 2026 · Editorial classification update
Record → Power / rates
Field Power / rates
From Not independently verified
To Partially supported
Why The tariff supports part of the risk-allocation claim, but it does not prove that generation, transmission or wholesale-market costs can never affect household bills.
Evidence re-reading of the sources already cited on this claim; no new source.
Correction · 14 September 2026 · Editorial classification update
Meta — Lebanon → City impact payment
Field City impact payment
From Not independently verified
To Supported
Why The government announcement supports the stated term. It does not establish an executed agreement, a due date or any payment received.
Evidence re-reading of the sources already cited on this claim; no new source.
Correction · 14 September 2026 · Editorial classification update
Meta — Lebanon → Permanent jobs
Field Permanent jobs
From Not independently verified
To Company claim
Why The figure is a company projection; neither cited announcement is an observed payroll or employment record.
Evidence re-reading of the sources already cited on this claim; no new source.
Correction · 14 September 2026 · Editorial classification update
Sabey — Decatur Technology Park → Power / cost allocation
Field Power / cost allocation
From Not independently verified
To Partially supported
Why The cited commitment supports cost allocation for one site, but it cannot establish the statewide generalization shown.
Evidence re-reading of the sources already cited on this claim; no new source.
Correction · 14 September 2026 · Editorial classification update
AWS — New Carlisle → State incentives
Field State incentives
From Not independently verified
To Supported
Why The government announcement, portal fields and agreement support the carefully limited description of authorized terms. They do not prove delivery, jobs or completed investment.
Evidence re-reading of the sources already cited on this claim; no new source.
Correction · 14 September 2026 · Editorial classification update
AWS — New Carlisle → Project status
Field Project status
From Not independently verified
To Unknown
Why This card tests a common inference, not an attributed outside statement. The operating milestone still does not establish completion of every planned building or the full campus.
Evidence re-reading of the sources already cited on this claim; no new source.
Correction · 14 September 2026 · Editorial classification update
Field Investment
From Not independently verified
To Company claim
Why The exact investment figure is a Meta projection. The government announcement repeats it but does not establish completed or placed-in-service capital.
Evidence re-reading of the sources already cited on this claim; no new source.
Correction · 14 September 2026 · Editorial classification update
Meta — Lebanon → State sales-tax exemption
Field State sales-tax exemption
From Not independently verified
To Supported
Why The government announcement supports the stated term. It does not establish the controlling agreement or exemptions actually claimed.
Evidence re-reading of the sources already cited on this claim; no new source.
Correction · 14 September 2026 · Editorial classification update
Microsoft — La Porte → Jobs / timing
Field Jobs / timing
From Not independently verified
To Contradicted
Why The claim says the projected jobs already exist, while the cited company source still describes a forecast and the government source describes a different job scope.
Evidence re-reading of the sources already cited on this claim; no new source.
Correction · 14 September 2026 · Editorial classification update
Meta — Lebanon → Construction jobs
Field Construction jobs
From Not independently verified
To Company claim
Why The peak construction-jobs figure is a company projection, not an observed workforce count or job-years measure.
Evidence re-reading of the sources already cited on this claim; no new source.
Correction · 14 September 2026 · Editorial classification update
Meta — Lebanon → Water / cooling
Field Water / cooling
From Not independently verified
To Unknown
Why The prior label is defined for an unverified statement by a non-company party. This card tests a common inference instead; the reviewed company source does not establish annual or total campus water use.
Evidence re-reading of the sources already cited on this claim; no new source.
12 September 20267 entries
Correction · 12 September 2026 · Software-assisted second check
AWS — New Carlisle → Project status
Field Project status
From Partially supported
To Not independently verified
Why The operating Project Rainier milestone does not establish completion of every planned New Carlisle building or the full campus.
Evidence re-reading of the sources already cited on this claim; no new source.
Correction · 12 September 2026 · Software-assisted second check
Record → Taxes / incentives
Field Taxes / incentives
From Partially supported
To Contradicted
Why The reviewed statute remains in force, and the reported pause concerns new requests rather than repeal or cancellation of existing agreements.
Evidence re-reading of the sources already cited on this claim; no new source.
Correction · 12 September 2026 · Software-assisted second check
Record → Taxes / incentives
Field Taxes / incentives
From Partially supported
To Contradicted
Why The statute authorizes a complete or partial equipment sales-and-use-tax exemption; it does not establish that a qualifying project pays no taxes.
Evidence re-reading of the sources already cited on this claim; no new source.
Correction · 12 September 2026 · Software-assisted second check
Meta — Lebanon → Water / cooling
Field Water / cooling
From Partially supported; unknowns not recorded
To Not independently verified; operating water unknowns and the future design scope are explicit
Why The second review found that a literal zero-water conclusion is not established by Meta's narrower future design statement.
Evidence re-reading of the sources already cited on this claim; no new source.
Correction · 12 September 2026 · Software-assisted second check
Sabey — Decatur Technology Park → Power / cost allocation
Field Power / cost allocation
From Partially supported
To Not independently verified
Why One site's cost commitment cannot establish the statewide claim shown.
Evidence re-reading of the sources already cited on this claim; no new source.
Correction · 12 September 2026 · Software-assisted second check
Microsoft — La Porte → Jobs / timing
Field Jobs / timing
From Not yet due
To Not independently verified
Why The 600-plus first-phase forecast has no retrieved due date; the 2032 date belongs to a different 200-job scope.
Evidence re-reading of the sources already cited on this claim; no new source.
Correction · 12 September 2026 · Software-assisted second check
Record → Power / rates
Field Power / rates
From Partially supported; framed as stranded distribution investment
To Not independently verified; scope narrowed to AEP Ohio and infrastructure/transmission risk
Why The second review found that the tariff supports risk allocation but not the absolute household-bill conclusion, and PUCO's own description is not limited to distribution.
Evidence re-reading of the sources already cited on this claim; no new source.
Field corrections
3 November 20267 entries
Correction · 3 November 2026 · DataCenterData review
QTS Data Centers — New Albany 1 campus → Record
Field Record
To Status wording now rests on QTS's U.S. locations page because the campus page no longer carries the In Development label. Lifecycle status unchanged; no opening or energization date is established.
Evidence No additional evidence link; see the linked record or claim.
Correction · 3 November 2026 · DataCenterData review
Microsoft — New Albany campus → Record
Field Record
To Updated from Microsoft's October 2026 construction update, which reports early construction works complete. Lifecycle status unchanged; the update does not establish operation.
Evidence No additional evidence link; see the linked record or claim.
Correction · 3 November 2026 · DataCenterData review
QTS Data Centers — New Albany 1 DC2 → Record evidence
Field Record evidence
To Status wording now rests on QTS's U.S. locations page because the campus page no longer carries the In Development label. Lifecycle status unchanged; no operating milestone inferred.
Evidence No additional evidence link; see the linked record or claim.
Correction · 3 November 2026 · DataCenterData review
QTS Data Centers — New Albany 2 DC2 → Record evidence
Field Record evidence
To Status wording now rests on QTS's U.S. locations page because the campus page no longer carries the In Development label. Lifecycle status unchanged; no operating milestone inferred.
Evidence No additional evidence link; see the linked record or claim.
Correction · 3 November 2026 · DataCenterData review
QTS Data Centers — New Albany 2 campus → Record
Field Record
To Status wording now rests on QTS's U.S. locations page because the campus page no longer carries the In Development label. Lifecycle status unchanged; no opening or energization date is established.
Evidence No additional evidence link; see the linked record or claim.
Correction · 3 November 2026 · DataCenterData review
QTS Data Centers — New Albany 2 DC1 → Record evidence
Field Record evidence
To Status wording now rests on QTS's U.S. locations page because the campus page no longer carries the In Development label. Lifecycle status unchanged; no operating milestone inferred.
Evidence No additional evidence link; see the linked record or claim.
Correction · 3 November 2026 · DataCenterData review
QTS Data Centers — New Albany 1 DC1 → Record evidence
Field Record evidence
To Status wording now rests on QTS's U.S. locations page because the campus page no longer carries the In Development label. Lifecycle status unchanged; no operating milestone inferred.
Evidence No additional evidence link; see the linked record or claim.
27 October 20261 entry
Correction · 27 October 2026 · DataCenterData review
Gilroy Data Center → Physical scale
Field Physical scale
To Restored the City's approximate qualifier for the planned Phase I building area: approximately 218,000 square feet. This corrects DCD's wording; it does not report a change to the project or an operating measurement.
Evidence No additional evidence link; see the linked record or claim.
18 October 20262 entries
Correction · 18 October 2026 · DataCenterData review
Field Policy record: City of Oakland, California: interim data-center moratorium effective 6 October 2026 (27-0050)
From Recorded as adopted with effective status unverified; the effective date, duration and expiration remained unverified.
To The City Clerk Notice and Digest posted with file 27-0050 states adoption on 6 October 2026 with immediate effect. Recorded as in effect from 6 October 2026. The final ordinance text, scope and exceptions have not been independently read, and no expiration date is recorded for the 45-day term the digest describes.
Why Log the 18 October 2026 status update, which was published without a change-log row; this row was added on 30 October 2026.
Evidence Oakland City Clerk Notice and Digest for file 27-0050 →
Correction · 18 October 2026 · DataCenterData review
Field Policy record: City of Milwaukee, Wisconsin: temporary data-center pause effective 17 October 2026 (File 251924)
From Milwaukee File 251924 (temporary data-center pause) described as proposed.
To Milwaukee's official matter record shows passage on 13 October 2026, signing on 14 October, publication on 16 October and effect on 17 October 2026. Recorded as in effect. The enacted Substitute 2 text and its final scope and exceptions have not been reviewed, and no expiration date is recorded.
Why Log the 18 October 2026 status update, which was published without a change-log row; this row was added on 30 October 2026.
13 October 20261 entry
Correction · 13 October 2026 · DataCenterData review
Field Policy record: City of Oakland, California: interim data-center moratorium effective 6 October 2026 (27-0050)
From Oakland file 27-0050 described as proposed and not adopted.
To The Council’s official record reports passage on 6 October 2026. Recorded as adopted with effective status unverified; the effective date, duration and expiration remain unverified.
Why Correct the outdated proposed status using the official matter page while preserving unknown legal effect and final terms.
Evidence Oakland City Council file 27-0050: recorded passage on 6 October 2026 →
12 October 20262 entries
Correction · 12 October 2026 · Editorial classification update
Vantage Data Centers — OH2 Millersport campus → Power / developer claim
Field Power / developer claim
From The evidentiary hearing is noticed for 17 September 2026.
To The previously reviewed notice scheduled the hearing for 17 September 2026; outcome and certificate remain unverified, with follow-up overdue.
Why Clarified historical notice and unresolved follow-up. No factual outcome, source date, substantive check date or company verdict changed.
Evidence https://fairfieldenergycenter.com/home/utility-facility →
Correction · 12 October 2026 · Editorial classification update
Vantage Data Centers — OH2 Millersport campus → OPSB / generation status
Field OPSB / generation status
From Application pending; hearing noticed for 2026-09-17. The evidentiary hearing is noticed for 17 September 2026.
To Proposal in evidence checked 17 September 2026; subsequent outcome unverified. The previously reviewed notice scheduled the hearing for September 17.
Why Replaced apparently upcoming hearing wording with historical context. No certificate, hearing outcome or factual review-date refresh established.
Evidence https://fairfieldenergycenter.com/home/utility-facility →
9 October 20261 entry
Correction · 9 October 2026 · DataCenterData review
Vantage Data Centers — OH1 campus → Location.address
Field Location.address
To Added the campus address printed on the independently reviewed Vantage OH1 page; preserved the competing Johnstown discovery label.
Evidence No additional evidence link; see the linked record or claim.
3 October 20261 entry
Correction · 3 October 2026 · DataCenterData review
Record → Power / rates
Field Power / rates
From The PUCO-approved AEP Ohio tariff allocates substantial underuse and cancellation risk to new loads over 25 MW. PUCO describes the concern as cost shifting from significant transmission infrastructure and other underused investment serving data centers. These protections are real, but the reviewed sources do not prove that residents can never be affected by generation, transmission, wholesale-market or pre-tariff costs. Under AEP's published contract-capacity formula, DataCenterData calculates a minimum of about 72.5% at 50 MW and 82.5% at 100 MW; a separate historical-demand ratchet can produce a higher billed demand. AEP reports that 12,219 of 17,861 MW of contracted data-center projects were signed before the tariff took effect; contracted projects are not current measured load.
To The PUCO-approved AEP Ohio tariff allocates substantial underuse and cancellation risk to new loads over 25 MW. PUCO describes the concern as cost shifting from significant transmission infrastructure and other underused investment serving data centers. These protections are real, but the reviewed sources do not prove that residents can never be affected by generation, transmission, capacity-market, wholesale-market or pre-tariff costs. The current Schedule DCT sheets (Ohio Power Company tariff P.U.C.O. No. 22, 1st Revised Sheets 223-1 to 223-8, issued and effective 28 August 2026 under the Commission's 1 April 2026 rate-case order and its 5 August 2026 order in Case No. 26-113-EL-ATA) set the minimum demand for new load after the ramp period at 15,000 kW plus 85% of the amount over 25,000 kW (25,001 to 75,000 kW) and 57,500 kW plus 100% of the amount over 75,000 kW, capped at 85% of total contract capacity; from that table DataCenterData calculates a minimum of about 72.5% at 50 MW and 82.5% at 100 MW, and a separate ratchet on the highest billing demand of the past 11 months can produce a higher billed demand. New-load contracts run for the load ramp period plus 8 years. Sheet 223-5 carries the interim standard-service-offer procedures the Commission granted on 5 August 2026: a Schedule DCT customer returning to the standard service offer must give 180 days' notice, AEP Ohio runs a separate procurement for that load at the customer's full cost, and if notice is not given AEP Ohio assigns the full cost of PJM spot-market purchases solely to that customer. The PUCO docket lists a 30 September 2026 entry denying the applications for rehearing of that order. AEP reports that 12,219 of 17,861 MW of contracted data-center projects were signed before the tariff took effect; contracted projects are not current measured load.
Why Cited the current Schedule DCT sheets (1st Revised Sheets 223-1 to 223-8, issued and effective 28 August 2026) for the minimum-demand table, the 85% cap and the Load Ramp Period plus 8 years term, and Sheet 223-5 for the interim standard-service-offer procedures; cited the PUCO docket listing for the 5 August 2026 order and the 30 September 2026 rehearing denial. Verdict unchanged. Household-bill, generation, transmission, capacity-market and pre-tariff-contract effects stay open; the missing documents are a PUCO or OCC household-bill analysis and the order texts.
Evidence https://www.aepohio.com/lib/docs/ratesandtariffs/Ohio/October_2026_Ohio_Power_Tariff_Book.pdf →
1 October 20261 entry
Correction · 1 October 2026 · DataCenterData review
Record → Policy record: Chicago, Illinois: adopted data center benchmarking ordinance; effect unverified
Field Policy record: Chicago, Illinois: adopted data center benchmarking ordinance; effect unverified
From Chicago Substitute Ordinance SO2026-0027165 (data center benchmarking and disclosure) described as proposed.
To The City Clerk's final matter record reports passage on 23 September 2026 as substituted and amended. Recorded as adopted with effect unverified; the final amended text and its effective clause have not been read.
Why Log the 1 October 2026 status update, which was published without a change-log row; this row was added on 30 October 2026.
21 September 20266 entries
Correction · 21 September 2026 · DataCenterData review
CoreWeave / Digital Crossroads expansion → Additional payment
Field Additional payment
From Minutes say it was not yet in the agreement.
To Discussed, not contracted, then the agreement lapsed. The 22 December 2025 minutes record the $25 million as announced but 'Right now it's not part of it'. The City announced on 1 July 2026 that the development agreement had expired after two extensions. No payment is shown as due or received in the saved record.
Why City of Hammond notice of 1 July 2026: the development agreement expired after two extensions because milestones were not satisfied by 30 June 2026. The authorized terms (Resolution 25R-16, 8–0, 9 June 2025) are now recorded as lapsed; no payment, incentive or NIPSCO agreement is shown in the saved record. Verdict unchanged.
Evidence https://www.gohammond.com/hammond-announces-expiration-of-data-center-development-agreement/ →
Correction · 21 September 2026 · DataCenterData review
CoreWeave / Digital Crossroads expansion → Incentives
Field Incentives
From Claimed or received amounts not established.
To Authorized terms, then lapsed. The 9 June 2025 minutes describe the contemplated 10-year construction abatement and 20-year 100% technology deduction alongside the development agreement adopted by Resolution 25R-16 (8–0, one member absent); the scope and terms of the CoreWeave equipment deduction and the Decennial construction abatement requested at the same meeting were not part of that resolution's vote and are not reviewed. The City announced on 1 July 2026 that the agreement had expired after two extensions. No abatement or deduction is shown as adopted, claimed or received in the saved record.
Why City of Hammond notice of 1 July 2026: the development agreement expired after two extensions because milestones were not satisfied by 30 June 2026. The authorized terms (Resolution 25R-16, 8–0, 9 June 2025) are now recorded as lapsed; no payment, incentive or NIPSCO agreement is shown in the saved record. Verdict unchanged.
Evidence https://www.gohammond.com/hammond-announces-expiration-of-data-center-development-agreement/ →
Correction · 21 September 2026 · DataCenterData review
CoreWeave / Digital Crossroads expansion → Community impact payments
Field Community impact payments
From Not shown due or paid.
To Authorized, then lapsed. The Common Council adopted Resolution 25R-16 approving the development agreement on 9 June 2025 by an 8–0 roll-call vote (one member absent); the 22 December 2025 minutes record an extension. The City announced on 1 July 2026 that the agreement for 301 Digital Crossroads had expired after two extensions because milestones were not satisfied by the 30 June 2026 deadline. No community impact payment is shown as due or received in the saved record, and the notice does not concern the operating DX-1 facility, which is a separate record.
Why City of Hammond notice of 1 July 2026: the development agreement expired after two extensions because milestones were not satisfied by 30 June 2026. The authorized terms (Resolution 25R-16, 8–0, 9 June 2025) are now recorded as lapsed; no payment, incentive or NIPSCO agreement is shown in the saved record. Verdict unchanged.
Evidence https://www.gohammond.com/hammond-announces-expiration-of-data-center-development-agreement/ →
Correction · 21 September 2026 · Editorial classification update
Meta — Lebanon → City impact payment
Field City impact payment
From $1.5 million annually per completed phase, up to six phases
To Meta will make a $1.5 million annual city payment for each completed phase, up to six phases.
Why The revised wording tests the future payment described in IEDC's announcement while distinguishing it from an executed agreement or delivered payment.
Evidence No additional evidence link; see the linked record or claim.
Correction · 21 September 2026 · DataCenterData review
CoreWeave / Digital Crossroads expansion → Power agreement
Field Power agreement
From No executed agreement located; exact failed milestones undisclosed.
To The 9 June 2025 minutes describe a final NIPSCO agreement as gating the expansion. No executed NIPSCO agreement is in the saved record, and the City's 1 July 2026 notice says the development agreement expired after two extensions because milestones were not satisfied by 30 June 2026, without naming which. The NIPSCO agreement remains unknown. The notice does not concern the operating DX-1 facility, which is a separate record.
Why City of Hammond notice of 1 July 2026: the development agreement expired after two extensions because milestones were not satisfied by 30 June 2026. The authorized terms (Resolution 25R-16, 8–0, 9 June 2025) are now recorded as lapsed; no payment, incentive or NIPSCO agreement is shown in the saved record. Verdict unchanged.
Evidence https://www.gohammond.com/hammond-announces-expiration-of-data-center-development-agreement/ →
Correction · 21 September 2026 · Editorial classification update
Sabey — Decatur Technology Park → Power / cost allocation
Field Power / cost allocation
From One Indianapolis developer cost commitment proves no Indiana data center can affect other customers' electricity costs.
To What electricity-system costs has the Sabey Indianapolis petitioner committed to cover, and does that establish statewide customer protection?
Why The prior wording framed a universal inference without citing anyone who made it. The replacement is an answerable research question.
Evidence No additional evidence link; see the linked record or claim.
17 September 20262 entries
Correction · 17 September 2026 · Editorial classification update
Vantage Data Centers — OH2 Millersport campus → OPSB / generation status
Field OPSB / generation status
From The source link used an OPSB case-summary URL that now returns 404.
To The working source link now opens Fairfield Energy's live project page, which identifies OPSB case 26-0160-EL-BGN.
Why The historical OPSB summary is described as preserved evidence rather than presented as a working page; the official case-summary URL returns 404 and the Docketing Information System rejected a direct case request during this check.
Evidence https://fairfieldenergycenter.com/home/utility-facility →
Correction · 17 September 2026 · Editorial classification update
Vantage Data Centers — OH2 Millersport campus → Power / developer claim
Field Power / developer claim
From The source link used an OPSB case-summary URL that now returns 404.
To The working source link now opens Fairfield Energy's live project page, which identifies OPSB case 26-0160-EL-BGN.
Why The historical OPSB summary is described as preserved evidence rather than presented as a working page; the official case-summary URL returns 404 and the Docketing Information System rejected a direct case request during this check.
Evidence https://fairfieldenergycenter.com/home/utility-facility →
16 September 20264 entries
Correction · 16 September 2026 · Editorial classification update
Google The Dalles → Cooling + water
Field Cooling + water
From Google The Dalles: Mixed evidence
To Google says The Dalles aquifer project added more than 100 million gallons a year of stored-water capacity for the community.
Why A source re-read replaced a generated status label with the exact company claim and separated community storage capacity from data-center water use.
Evidence No additional evidence link; see the linked record or claim.
Correction · 16 September 2026 · Editorial classification update
Meta — Jeffersonville → Cooling + water
Field Cooling + water
From Meta Jeffersonville: Not verifiable
To Meta's Jeffersonville announcement establishes the campus's cooling design and water use.
Why A source re-read converted a generated status label into the exact inference being tested and restored a concise unit boundary.
Evidence No additional evidence link; see the linked record or claim.
Correction · 16 September 2026 · Editorial classification update
Microsoft Mount Pleasant → Cooling + water
Field Cooling + water
From Microsoft Mount Pleasant: Announced
To Microsoft says its Mount Pleasant pilot will use closed-loop chip-level cooling without evaporating water for cooling.
Why A source re-read replaced a generated status label with the exact company claim and restored a concise unit boundary.
Evidence No additional evidence link; see the linked record or claim.
Correction · 16 September 2026 · Editorial classification update
Google — Fort Wayne → Cooling + water
Field Cooling + water
From Google Fort Wayne: Not verifiable
To The reviewed utility order establishes Google Fort Wayne's cooling design and water use.
Why A source re-read converted a generated status label into the exact inference being tested and restored a concise unit boundary.
Evidence No additional evidence link; see the linked record or claim.
12 September 202613 entries
Correction · 12 September 2026 · Software-assisted second check
Vantage Data Centers — OH2 Millersport campus → Power / developer claim
Field Power / developer claim
From Only company descriptions of the proposed adjacent power facility were cited.
To The preserved official OPSB case summary is cited separately from the developer's differing generation and storage figures.
Why Primary-record follow-up confirmed the proposal and hearing date while preserving the unresolved MW discrepancy and outcome hold.
Evidence https://fairfieldenergycenter.com/home/utility-facility →
Correction · 12 September 2026 · Software-assisted second check
Record → Water / permits
Field Water / permits
From The direct Ohio EPA decision notice had not been retrieved.
To The preserved official Ohio EPA Community Notice is cited with its dated heading and exact page location.
Why Primary-record follow-up recovered the agency's own notice, and the second review re-read it; a later live recheck was unavailable and is not treated as a retraction.
Evidence https://epa.ohio.gov/divisions-and-offices/surface-water/permitting/npdes-general-permits →
Correction · 12 September 2026 · Software-assisted second check
Record → Water
Field Water
From The evidence link opened the report landing page and described the unit as million US gallons.
To The evidence link opens the report PDF, cites the exact p. 97 table, and uses its printed unit, million gallons.
Why Independent re-extraction confirmed the three Google-reported Ohio rows without turning company reporting into municipal measurement.
Evidence https://sustainability.google/files/google-2026-environmental-report.pdf →
Correction · 12 September 2026 · Software-assisted second check
AWS — New Carlisle → State incentives
Field State incentives
From The contract split was held because no independent retrieval was recorded.
To Five Project 424567 portal instruments and the DATA agreement are cited with exact fields and contract locators.
Why The second review reproduced the portal records while preserving the difference between authorized terms, portal fields, and observed outcomes.
Evidence https://transparencyportal.iedc.in.gov/viewtaxgrantloancontract/8c0f68149feaee11904d001dd8306d4e →
Correction · 12 September 2026 · DataCenterData review
AWS — New Carlisle → Incentives commitments
Field Incentives commitments
To IEDC Project 424567 portal instruments and the DATA agreement were independently retrieved and separated by program, status, field name and contractual condition.
Evidence No additional evidence link; see the linked record or claim.
Correction · 12 September 2026 · DataCenterData review
STACK Infrastructure — NAL01B → Lifecycle status
Field Lifecycle status
To Changed from construction to approved. The city record establishes final development-plan approval, while the reviewed sources do not establish a construction start.
Evidence No additional evidence link; see the linked record or claim.
Correction · 12 September 2026 · Software-assisted second check
Microsoft Quincy → Cooling + water
Field Cooling + water
From Microsoft Quincy: Supported as delivered; combined measures and a 2021-2022 observation window
To EPA documents an operating reuse system; distinct estimates and dated observations are separated
Why The second review separated estimated savings, canal makeup and potable makeup share and removed an unsupported original-publication year.
Evidence No additional evidence link; see the linked record or claim.
Correction · 12 September 2026 · Software-assisted second check
Vantage Data Centers — OH1 campus → Opening status
Field Opening status
From The tested opening proposition was attributed directly to Vantage Data Centers.
To The proposition is labeled as a common reading; Vantage is cited only for its December 2025 opening target.
Why The operator page states a forecast and does not claim that the first building opened or is operating.
Evidence https://vantage-dc.com/data-center-locations/north-america/new-albany-ohio →
Correction · 12 September 2026 · DataCenterData review
EdgeConneX — New Albany location → Lifecycle status
Field Lifecycle status
To Corrected operating to construction. The prior basis itself said operation was not established; city records support an active building project and groundbreaking, not operation.
Evidence No additional evidence link; see the linked record or claim.
Correction · 12 September 2026 · Software-assisted second check
Record → Taxes / jobs
Field Taxes / jobs
From Statewide tax/jobs scope; underlying operator not specified
To One unnamed New Albany hyperscaler, tax year 2024 payable 2025; city-reported comparison
Why The second review narrowed the place, taxpayer and time scope and made the missing underlying records explicit.
Evidence No additional evidence link; see the linked record or claim.
Correction · 12 September 2026 · DataCenterData review
Sabey — Decatur Technology Park → Lifecycle status
Field Lifecycle status
To Changed from construction to approved. The commission record establishes approval subject to commitments, but no reviewed primary source establishes that construction began.
Evidence No additional evidence link; see the linked record or claim.
Correction · 12 September 2026 · Software-assisted second check
Record → Statewide count
Field Statewide count
From The directory denominator can include buildings, suites and campuses; March 2026 PDF
To The directory unit and deduplication are unreconciled; retained March-path PDF differs from the live page's current May-path target
Why The second review removed an unsupported description of the directory denominator and distinguished URL-path timing from publication date.
Evidence No additional evidence link; see the linked record or claim.
Correction · 12 September 2026 · Software-assisted second check
Vantage Data Centers — OH2 Millersport campus → OPSB / generation status
Field OPSB / generation status
From The claim cited only Fairfield Energy's application description.
To The claim now separates the preserved OPSB summary's 1,300/1,000 MW figures from Fairfield Energy's 1,350/1,040 MW figures.
Why The official and company summaries disagree; neither is converted to data-center IT capacity and the underlying filing remains unavailable.
Evidence https://fairfieldenergycenter.com/home/utility-facility →
11 September 202635 entries
Correction · 11 September 2026 · DataCenterData review
Record → Power / rates
Field Power / rates
From The PUCO-approved AEP Ohio tariff allocates substantial underuse and cancellation risk to new loads over 25 MW. That is real protection against stranded distribution investment; it is not proof that generation, transmission or wholesale-market costs can never affect household bills.
To Added how the 85% minimum-demand term works by contract size and AEP's count of pre-tariff contracted load. Verdict unchanged. The 72.5% and 82.5% shares are DataCenterData arithmetic from AEP's published formula (15,000 kW plus 85% above 25,000 kW up to 75,000 kW; 57,500 kW plus 100% above 75,000 kW; capped at 85% of contract capacity).
Evidence https://www.aepohio.com/company/about/rates/data-center-tariff/ →
Correction · 11 September 2026 · DataCenterData review
CyrusOne — CIN2 → Record evidence
Field Record evidence
To address was null ('address unresolved'). The current CyrusOne CIN2 page gives no street address; CyrusOne's archived CIN2 page (Internet Archive capture 2023-11-29, https://web.archive.org/web/20231129155948/https://www.cyrusone.com/data-centers/north-america/ohio/cin2-cincinnati) gives '229 West 7th St., Cincinnati'. A directory lead lists a 209-229 W 7th St range; the building extent is not resolved.
Why address was null ('address unresolved'). The current CyrusOne CIN2 page gives no street address; CyrusOne's archived CIN2 page (Internet Archive capture 2023-11-29, the cited source gives '229 West 7th St., Cincinnati'. A directory lead lists a 209-229 W 7th St range; the building extent is not resolved.
Evidence No additional evidence link; see the linked record or claim.
Correction · 11 September 2026 · DataCenterData review
AWS — New Carlisle → Permanent jobs
Field Permanent jobs
From At least 1,000 baseline; AWS's own July 2026 account says nearly 1,000 operations staff hired; an undated Chamber project page says 1,056 full-time AWS employees
To 2026-09-11: status was 'supported-as-delivered' with value 'At least 1,000 baseline; 1,056 full-time AWS employees later reported'. The company-linked counts sit on either side of the baseline (AWS op-ed: 'We have also hired nearly 1,000 operations staff so far'; Chamber page: '1,056 full-time AWS employees', undated), so the reviewed record does not support a delivery conclusion. Evidence level unchanged.
Correction · 11 September 2026 · DataCenterData review
Google — New Albany campus → County
Field County
To County resolved from Licking County parcel records. County is a typed field and may not hold a sentence.
Evidence No additional evidence link; see the linked record or claim.
Correction · 11 September 2026 · DataCenterData review
QTS Data Centers — New Albany 1 DC1 → Record evidence
Field Record evidence
To locality resolved from the current Licking County parcel record; no operating milestone inferred.
Evidence No additional evidence link; see the linked record or claim.
Correction · 11 September 2026 · DataCenterData review
Record → Water / permits
Field Water / permits
From Draft Ohio data-center general NPDES permit treated as if it were a final, measured water authorization.
To Ohio EPA said on July 21, 2026 that it would not finalize draft OHD000001 and would continue with individual NPDES permits. A permit is not measured discharge.
Why Correction chronology uses the recorded date, not the 21 July agency-event date.
Correction · 11 September 2026 · DataCenterData review
Microsoft — La Porte → Incentives
Field Incentives
From 35-year state sales-tax exemption for at least $1B eligible capital, with possible extensions; local and NIPSCO incentives referenced but not yet reconciled.
To Minutes record unanimous adoption of R-3-2026 under a title describing rescission of the 2024 taxpayer agreement and termination of its tax abatement; adopted resolution text not obtained; IEDC DATA exemption pending.
Why Correction chronology uses the recorded date 2026-09-11; the source event date remains 2026-03-02.
Evidence https://www.cityoflaporte.com/uploads/minutes/m_1932_Council-Mar.2-2026-Minutes.docx →
Correction · 11 September 2026 · DataCenterData review
Meta — New Albany campus / Prometheus expansion → County
Field County
To County resolved from Licking County parcel records. County is a typed field and may not hold a sentence.
Evidence No additional evidence link; see the linked record or claim.
Correction · 11 September 2026 · DataCenterData review
CoreWeave / Digital Crossroads expansion → Additional payment
Field Additional payment
From Previous locator
To pp. 1–4 ($80 million community-payment total p. 1; $25 million announced p. 2; 'Right now it's not part of it' p. 4); extension resolution at p. 10
Why 2026-09-11: previously 'pp. 1–2; extension resolution at p. 10'.
Correction · 11 September 2026 · DataCenterData review
Field Record
To previously '35-year state sales-tax exemption for at least $800M eligible capital, with extensions tied to additional eligible investment up to 50 years.' The $800M figure is the announcement's wording; the executed agreement (Exhibit A, section 2.A, page 13 of 18) says $845,000,000. The IEDC portal's separate 'expected qualified investment' field ($830M) is a different field and is not used here.
Evidence No additional evidence link; see the linked record or claim.
Correction · 11 September 2026 · DataCenterData review
Lumen Indianapolis 1 → Record evidence
Field Record evidence
To evidence_tier was 'municipal-list-only' and status 'Listed in municipal appendix; current service scope not verified'. The only source is a petitioner's exhibit whose list cites DataCenterMap; no Lumen first-party or government record for this site was found.
Evidence No additional evidence link; see the linked record or claim.
Correction · 11 September 2026 · DataCenterData review
STACK Infrastructure — NAL01A → Record evidence
Field Record evidence
To address resolved from the current Franklin County parcel record.
Evidence No additional evidence link; see the linked record or claim.
Correction · 11 September 2026 · DataCenterData review
DataBank — CLE1 → Facility location
Field Facility location
To 2026-09-11: suite and ZIP added from the cited DataBank page ('1255 Euclid Ave Suite #200 - Cleveland, OH 44115'); CLE1 is a suite in a multi-tenant building, so the building should be counted once if other providers there are added.
Evidence No additional evidence link; see the linked record or claim.
Correction · 11 September 2026 · DataCenterData review
Field Record
To The Common Council minutes record 'Motion/Vote – Adopt Resolution R-3-2026' and say the motion was unanimously carried. The LEAP director states that the resolution refers to the taxpayer agreement approved in 2024 with Microsoft.
Evidence No additional evidence link; see the linked record or claim.
Correction · 11 September 2026 · DataCenterData review
STACK Infrastructure — NAL01B → Record evidence
Field Record evidence
To address and approval status resolved from the city planning record and current county parcel record; no construction milestone inferred.
Evidence No additional evidence link; see the linked record or claim.
Correction · 11 September 2026 · DataCenterData review
Record → Indianapolis appendix
Field Indianapolis appendix
To 2026-09-11: publisher was 'Indianapolis Metropolitan Development Commission filing' and kind 'municipal case record containing an existing Indianapolis facility list'.
Evidence No additional evidence link; see the linked record or claim.
Correction · 11 September 2026 · DataCenterData review
CoreWeave / Digital Crossroads expansion → Incentives
Field Incentives
From Previous locator
To pp. 3–11 (resolution 25R-16 introduced p. 3; lease, jobs, tax terms and community impact payment p. 4; NIPSCO contingency p. 6)
Why 2026-09-11: previously 'pp. 3–4'.
Correction · 11 September 2026 · DataCenterData review
QTS Data Centers — Van Wert campus → Jobs
Field Jobs
To 2026-09-11: previously 'Thousands of construction jobs and hundreds of full-time positions; company projection'. Quantified figures are from the FAQ answer 'How many jobs will this project create?' on https://q.com/data-centers/van-wert/.
Why 2026-09-11: previously 'Thousands of construction jobs and hundreds of full-time positions; company projection'. Quantified figures are from the FAQ answer 'How many jobs will this project create?' on the cited source
Evidence No additional evidence link; see the linked record or claim.
Correction · 11 September 2026 · DataCenterData review
Record → Statewide count
Field Statewide count
From Ohio's consumer advocate repeats a commercial directory count. It is useful as a market signal, but the underlying unit can include buildings, suites and campuses and is not a state census. DataCenterData does not adopt 200+ as its own count.
To Added the wording difference between OCC's web fact sheet and its PDF fact sheet. Verdict unchanged.
Evidence https://occ.ohio.gov/factsheet/quick-facts-data-centers-ohio →
Correction · 11 September 2026 · DataCenterData review
CoreWeave / Digital Crossroads expansion → Power agreement
Field Power agreement
From Previous locator
To pp. 1–4 ($80 million community-payment total p. 1; $25 million announced p. 2; 'Right now it's not part of it' p. 4); extension resolution at p. 10
Why 2026-09-11: previously 'pp. 1–2; extension resolution at p. 10'.
Correction · 11 September 2026 · DataCenterData review
Vantage Data Centers — OH1 campus → County
Field County
To County resolved from Licking County parcel records. County is a typed field and may not hold a sentence.
Evidence No additional evidence link; see the linked record or claim.
Correction · 11 September 2026 · DataCenterData review
CoreWeave / Digital Crossroads expansion → Incentives
Field Incentives
From Previous locator
To pp. 1–4 ($80 million community-payment total p. 1; $25 million announced p. 2; 'Right now it's not part of it' p. 4); extension resolution at p. 10
Why 2026-09-11: previously 'pp. 1–2; extension resolution at p. 10'.
Correction · 11 September 2026 · DataCenterData review
CoreWeave / Digital Crossroads expansion → Power agreement
Field Power agreement
From Previous locator
To pp. 3–11 (resolution 25R-16 introduced p. 3; lease, jobs, tax terms and community impact payment p. 4; NIPSCO contingency p. 6)
Why 2026-09-11: previously 'pp. 3–4'.
Correction · 11 September 2026 · DataCenterData review
AWS — New Carlisle → Permanent jobs
Field Permanent jobs
To status was 'supported-as-delivered' with value 'At least 1,000 baseline; 1,056 full-time AWS employees later reported'. The company-linked counts sit on either side of the baseline, so the reviewed record does not support a delivery conclusion.
Evidence No additional evidence link; see the linked record or claim.
Correction · 11 September 2026 · DataCenterData review
CoreWeave / Digital Crossroads expansion → Expansion design
Field Expansion design
From Previous locator
To pp. 3–11 (resolution 25R-16 introduced p. 3; lease, jobs, tax terms and community impact payment p. 4; NIPSCO contingency p. 6)
Why 2026-09-11: previously 'pp. 3–4'.
Correction · 11 September 2026 · DataCenterData review
Lumen Indianapolis 2 → Record evidence
Field Record evidence
To evidence_tier was 'municipal-list-only' and status 'Listed in municipal appendix; current service scope not verified'. The only source is a petitioner's exhibit whose list cites DataCenterMap; no Lumen first-party or government record for this site was found.
Evidence No additional evidence link; see the linked record or claim.
Correction · 11 September 2026 · DataCenterData review
CoreWeave / Digital Crossroads expansion → Community impact payments
Field Community impact payments
From Previous locator
To pp. 3–11 (resolution 25R-16 introduced p. 3; lease, jobs, tax terms and community impact payment p. 4; NIPSCO contingency p. 6)
Why 2026-09-11: previously 'pp. 3–4'.
Correction · 11 September 2026 · DataCenterData review
CoreWeave / Digital Crossroads expansion → Community impact payments
Field Community impact payments
From Previous locator
To pp. 1–4 ($80 million community-payment total p. 1; $25 million announced p. 2; 'Right now it's not part of it' p. 4); extension resolution at p. 10
Why 2026-09-11: previously 'pp. 1–2; extension resolution at p. 10'.
Correction · 11 September 2026 · DataCenterData review
Sabey — Decatur Technology Park → Record
Field Record
To status was 'Approved; construction not verified' while the only linked source was the petitioner's appendix, which shows a request rather than a decision. The verification source is now the commission's hearing results. Prior verification source: https://indianapolis-in.municodemeetings.com/sites/indianapolis-in.municodemeetings.com/files/fileattachments/mdc_hearing_examiner/meeting/5368/2025-cap-856_2025-cvr-856_petitioner_appendix_mdc_3-18-26_final.pdf; prior fields with recorded verification: local filing, cooling claim, cost commitment.
Why status was 'Approved; construction not verified' while the only linked source was the petitioner's appendix, which shows a request rather than a decision. The verification source is now the commission's hearing results. Prior verification source: the cited source prior fields with recorded verification: local filing, cooling claim, cost commitment.
Evidence No additional evidence link; see the linked record or claim.
Correction · 11 September 2026 · DataCenterData review
Flexential — Cincinnati → Record evidence
Field Record evidence
To address was null ('address unresolved'). Flexential's Cincinnati page (Internet Archive capture 2025-03-28, https://web.archive.org/web/20250328101315/https://www.flexential.com/data-centers/oh/cincinnati/data-center) gives '5307 Muhlhauser Rd, West Chester, OH 45011' and a 43,551 sq ft data-center footprint; the live page refuses automated requests and was not retrieved again. Whether one or two buildings stand at the address is unresolved.
Why address was null ('address unresolved'). Flexential's Cincinnati page (Internet Archive capture 2025-03-28, the cited source gives '5307 Muhlhauser Rd, West Chester, OH 45011' and a 43,551 sq ft data-center footprint; the live page refuses automated requests and was not retrieved again. Whether one or two buildings stand at the address is unresolved.
Evidence No additional evidence link; see the linked record or claim.
Correction · 11 September 2026 · DataCenterData review
CoreWeave / Digital Crossroads expansion → Permanent jobs
Field Permanent jobs
From Previous locator
To pp. 3–11 (resolution 25R-16 introduced p. 3; lease, jobs, tax terms and community impact payment p. 4; NIPSCO contingency p. 6)
Why 2026-09-11: previously 'pp. 3–4'.
Correction · 11 September 2026 · DataCenterData review
Microsoft — La Porte → Incentives commitments
Field Incentives commitments
From 35-year state sales-tax exemption for at least $1B eligible capital, with possible extensions; local and NIPSCO incentives referenced but not yet reconciled.
To The 2 March 2026 council minutes record unanimous adoption of Resolution R-3-2026, whose agenda title describes rescission of the 2024 Microsoft taxpayer agreement, including termination of the tax abatement. DataCenterData has not obtained the adopted resolution text and therefore does not independently state its full legal effect. IEDC showed the state DATA exemption as a pending accepted offer when checked.
Why Primary municipal minutes record introduction and unanimous adoption of R-3-2026.
Correction · 11 September 2026 · DataCenterData review
Microsoft — La Porte → Stable id
Field Stable id
From Two Indiana project registers with different IDs for the same projects (microsoft-la-porte-1 vs microsoft-la-porte; digital-crossroads-hammond vs coreweave-hammond counted as parallel eights).
To One Indiana project file. microsoft-la-porte is canonical (alias microsoft-la-porte-1). Digital Crossroads Hammond is the campus; CoreWeave Hammond is the child expansion project; DX-1 remains the operating facility.
Why Remove the duplicate Indiana project authority before any further state expansion.
Correction · 11 September 2026 · DataCenterData review
Record → Ohio-claim-checks.json:ohio-water-permit
Field Ohio-claim-checks.json:ohio-water-permit
From Draft Ohio data-center general NPDES permit treated as if it were a final, measured water authorization.
To Ohio EPA said on July 21 it would not finalize draft OHD000001 and would continue with individual NPDES permits. A draft permit is not measured discharge.
Why Stable public citation for the agency's July 21 notice.
Correction · 11 September 2026 · DataCenterData review
Google — New Albany campus → County
Field County
From Unknown pending parcel resolution
To Licking
Why County GIS parcels resolve the three campus counties. County is a typed field and may not hold a sentence.
Evidence Licking County parcel records for Google, Meta and Vantage OH1 New Albany campuses →
Evidence review notes
These dates record source reviews, not project milestones or new observations.
3 November 20265 entries
Record history · 3 November 2026 · DataCenterData review
Gilroy Data Center → Evidence review
Field Evidence review
To Rechecked the City's project page. Its water and revenue answers moved to the City's Data Center General Q&A page; the permit dates and status stated here remain on the project page. This is a review date, not a construction date.
Evidence No additional evidence link; see the linked record or claim.
Record history · 3 November 2026 · DataCenterData review
Project Mitten → Evidence review
Field Evidence review
To Rechecked the township pages. Construction entries moved from its update page to its Advisory Committee Meetings page, and the status basis now cites that page. This is a review date, not a construction date; lifecycle status is unchanged.
Evidence No additional evidence link; see the linked record or claim.
Record history · 3 November 2026 · DataCenterData review
Project Jupiter → Evidence review
Field Evidence review
To State docket read through its 30 October filing; the permit stays pending. The environment department says state law requires a decision by 23 November unless the applicant waives that deadline, and the documents read do not settle how that fits a hearing on 7 December.
Evidence No additional evidence link; see the linked record or claim.
Record history · 3 November 2026 · DataCenterData review
Project Sail → Evidence review
Field Evidence review
To Rechecked against county minutes. An applicant representative told the Board that Prologis and Atlas Development were requesting support for Project Sail; the minutes state no legal relationship or operator. The DRI forms could not be re-read because the state site does not permit automated access.
Evidence No additional evidence link; see the linked record or claim.
Record history · 3 November 2026 · DataCenterData review
Project Cannoli → Evidence review
Field Evidence review
To County journals read. Township and Michigan Public Service Commission pages do not permit automated access, so final site-plan approval and the utility case were not re-read.
Evidence No additional evidence link; see the linked record or claim.
14 September 20261 entry
Record history · 14 September 2026 · DataCenterData review
VELCO New Haven Operations Facility → Evidence review
Field Evidence review
To Independent source review reopened VELCO's report for 2024, which describes the building as nearing completion. This is a retrieval/review date, not a construction, observation, publication or operating date.
Evidence No additional evidence link; see the linked record or claim.
Records added
Record publications are DataCenterData's own publishing activity, not facility events. Recent ones also appear as evidence updates.
13 October 20264 entries
DataCenterData record added · 13 October 2026 · Software-assisted second check
To Added the county-confirmed building identity and address. Operating status, legal roles and building capacity remain unknown.
DataCenterData record added · 13 October 2026 · Software-assisted second check
To Added the county-confirmed building identity and address. Operating status, legal roles and building capacity remain unknown.
DataCenterData record added · 13 October 2026 · Software-assisted second check
Pacific Corporate Park (PowerHouse Pacific) → Publication
To Added one campus with three county building addresses. The PowerHouse marketing name is linked to the site; legal roles and operating status remain unknown.
DataCenterData record added · 13 October 2026 · Software-assisted second check
PowerHouse Arcola → Publication
To Added the county-named project with county-level location. Street, building details and operating status remain unknown.
26 September 20262 entries
DataCenterData record added · 26 September 2026 · Software-assisted second check
To Added as one partly operating campus with continuing construction; the operator-reported 175 MW live capacity is kept separate from the 400 MW contracted full build-out.
Evidence https://www.sec.gov/Archives/edgar/data/1144879/000114487926000048/apld-20260531.htm →
DataCenterData record added · 26 September 2026 · Software-assisted second check
Google data center, Prince William County → Publication
To Added as an unresolved operator-confirmed facility in Prince William County (opened 2023 per Google). It is not counted as a verified facility until its identity and location are established.
18 September 202615 entries
DataCenterData record added · 18 September 2026 · Software-assisted second check
Vantage Data Centers — Quincy Campus → Publication
To Added after independent re-reading of the state index and site-specific order, with backup generation kept separate from IT capacity.
Evidence https://ecology.wa.gov/air-climate/air-quality/data-centers →
DataCenterData record added · 18 September 2026 · Software-assisted second check
Gregory Road Data Center → Publication
To Added from the opened Georgia DRI filing and Newton County objection. Covington is not assigned as the host city.
DataCenterData record added · 18 September 2026 · Software-assisted second check
To Added from the opened Georgia DRI filing after operator-null review; Prologis is not named in the cited records.
DataCenterData record added · 18 September 2026 · Software-assisted second check
H5 Data Centers — Quincy → Publication
To Added after independent re-reading of the state index and site-specific order, with equipment ratings excluded from IT-capacity fields.
Evidence https://ecology.wa.gov/air-climate/air-quality/data-centers →
DataCenterData record added · 18 September 2026 · Software-assisted second check
Northtown Data Center (NTDC) → Publication
To Added from the opened CEQAnet and CEC records. Backup-generation capacity is recorded as proposed onsite generation, not IT load.
DataCenterData record added · 18 September 2026 · Software-assisted second check
Project Camellia → Publication
To Added from the opened Georgia DRI filing after operator-null review. The cited DRI does not name an end user or tenant and does not support the OpenAI attribution.
DataCenterData record added · 18 September 2026 · Software-assisted second check
To Added from the opened city ordinances and Georgia DRI filing. Adopted rezoning is recorded as zoning approval only.
DataCenterData record added · 18 September 2026 · Software-assisted second check
Microsoft Corp-Chicago Data Center → Publication
To Added from the opened Illinois EPA notice. The DCEO Northlake Microsoft incentive award is not treated as the same facility.
DataCenterData record added · 18 September 2026 · Software-assisted second check
McLaren Data Center → Publication
To Added from the opened CEQAnet notice after operator-null review; generator authority is not converted to IT capacity or current operation.
DataCenterData record added · 18 September 2026 · Software-assisted second check
Colovore LLC Aurora data center → Publication
To Added from the opened Illinois EPA notice after operator-null review; the applicant is not treated as a verified operator and the West Chicago address is not merged.
DataCenterData record added · 18 September 2026 · Software-assisted second check
Goodman Energy Park (GEP) data center → Publication
To Added from the opened CEQAnet and CEC records. Backup-generation capacity is recorded as proposed onsite generation, not IT load.
DataCenterData record added · 18 September 2026 · Software-assisted second check
To Added from the opened Georgia DRI filing. A neighbouring Stonewall Tell filing sits on the opposite side of the road and is not merged.
DataCenterData record added · 18 September 2026 · Software-assisted second check
CyrusOne — Quincy Data Center → Publication
To Added after independent re-reading of the state index and site-specific order.
Evidence https://ecology.wa.gov/air-climate/air-quality/data-centers →
DataCenterData record added · 18 September 2026 · Software-assisted second check
To Added from the opened Georgia DRI filing after operator-null review; QTS branding is not treated as a verified operator role.
DataCenterData record added · 18 September 2026 · Software-assisted second check
Kingston Technology Hub → Publication
To Added from the opened Georgia DRI filing after operator-null review; Thor Equities is not stated as a parent in the cited records.
14 September 202611 entries
DataCenterData record added · 14 September 2026 · Software-assisted second check
JP Morgan Chase CDC 1 → Publication
To Added as one permit-defined existing facility; current IT use, roles, scale and capacity remain unknown.
Evidence https://dnrec.delaware.gov/public-notices/title-v-synthetic-minor-permit-applications-jp-morgan/ →
DataCenterData record added · 14 September 2026 · Software-assisted second check
Google Papillion Data Center → Publication
To Qualified as one operating campus with at least one operating data-center building; complete campus scale, roles, and capacity remain unknown.
Evidence https://www.sarpy.gov/m/newsflash/home/detail/113 →
DataCenterData record added · 14 September 2026 · Software-assisted second check
Eternal Mind Loring Data Center Building → Publication
To Qualified as one proposed building from dated lease and tenant records; current tenancy, occupancy and operation remain unknown.
DataCenterData record added · 14 September 2026 · Software-assisted second check
Sabey Montana Connections Data Center Project → Publication
To Qualified as one proposed land-sale and due-diligence project; no later lifecycle milestone is inferred.
Evidence https://www.co.silverbow.mt.us/AgendaCenter/ViewFile/Agenda/_04162025-4618 →
DataCenterData record added · 14 September 2026 · Software-assisted second check
Meta Rosemount Data Center → Publication
To Qualified as one construction-stage campus; roles, capacity, exact parcel, completion, and operation remain unknown.
DataCenterData record added · 14 September 2026 · Software-assisted second check
STAK Energy Campus → Publication
To Qualified as one proposed campus; final lease action, construction, operation, roles and IT capacity remain unknown.
Evidence https://notice.alaska.gov/223817 →
DataCenterData record added · 14 September 2026 · Software-assisted second check
Massachusetts Green High Performance Computing Center → Publication
To Added as one assessed building with dated operating evidence; current utilization and capacity remain unknown.
DataCenterData record added · 14 September 2026 · Software-assisted second check
To Qualified from current ETS use and procurement pages as one operating facility; roles, capacity, and scale remain unknown.
Evidence https://ets.hawaii.gov/services-oriented-infrastructure/ →
DataCenterData record added · 14 September 2026 · Software-assisted second check
Gotspace Groton Data Center Project → Publication
To Qualified as one agreement-backed project with current lifecycle unknown; all later milestones remain unverified.
DataCenterData record added · 14 September 2026 · Software-assisted second check
To Added as one rezoning and preliminary-plan-approved project; construction, end user, roles and capacity remain unknown.
DataCenterData record added · 14 September 2026 · Software-assisted second check
DataOne Vineland AI Data Center → Publication
To Qualified at approval only; current construction and applicant corporate-role crosswalk remain unresolved.
13 September 202634 entries
DataCenterData record added · 13 September 2026 · Software-assisted second check
Thornburg Industrial Park 2 → Publication
To Added as a bounded under-review project after independent review of Spotsylvania County case records.
DataCenterData record added · 13 September 2026 · Software-assisted second check
Gilroy Data Center → Publication
To Added as a bounded construction-stage project after independent review of the City of Gilroy source.
Evidence https://www.cityofgilroy.org/1019/Gilroy-Data-Center-by-AWS →
DataCenterData record added · 13 September 2026 · Software-assisted second check
Microsoft Tyrone Data Center Project → Publication
To Added as a zoning-approved project after a fresh review of the Town of Tyrone source; unverified Project Rita, building and capacity details were excluded.
DataCenterData record added · 13 September 2026 · Software-assisted second check
Meta Gallatin Data Center → Publication
To Added as one campus record; operating status remains visibly operator-attributed and regional renewable-generation figures were excluded from campus capacity.
DataCenterData record added · 13 September 2026 · Software-assisted second check
Nexus Data Center Hubbard → Publication
To Added as a permit-defined proposed project after independent review of current TCEQ records.
DataCenterData record added · 13 September 2026 · Software-assisted second check
Rifle Range Road Data Center Project → Publication
To Added as one dated construction-stage project; party identities, current progress, capacity and physical scale remain unknown.
Evidence https://webstercountymo.gov/commission-data-center-update-may-21/ →
DataCenterData record added · 13 September 2026 · Software-assisted second check
QTS York County Data Center Campus → Publication
To Added as one construction-stage campus after a fresh review of county and state records; planned/developing buildings were not counted as operating facilities.
DataCenterData record added · 13 September 2026 · Software-assisted second check
To Added as a bounded operating-facility record after independent review of current TCEQ records.
DataCenterData record added · 13 September 2026 · Software-assisted second check
To Added as one construction-stage campus; the lease-backed 200 MW was scoped to the initial two-building phase and developer, operator, owner and tenant identities remain unresolved.
Evidence https://www.sec.gov/Archives/edgar/data/1144879/000114487926000030/apld-20260228.htm →
DataCenterData record added · 13 September 2026 · Software-assisted second check
Pairmont Data Center Campus → Publication
To Added as a bounded under-review project after independent review of Spotsylvania County case records.
DataCenterData record added · 13 September 2026 · Software-assisted second check
Amazon Data Services BWI-150–BWI-153 Campus → Publication
To Added as one permit-approved campus after a fresh review of the issued permit and MDE pages; generator ratings and broader-site relationships were not promoted.
DataCenterData record added · 13 September 2026 · Software-assisted second check
Osmium Data Center → Publication
To Added as one permit-defined existing facility; party roles, physical scale and data-center capacity remain unknown.
Evidence https://www.iowadnr.gov/media/6245/download?inline →
DataCenterData record added · 13 September 2026 · Software-assisted second check
AL Bessemer Land Data Center Project → Publication
To Added as one zoning-approved project; company identity, construction, acreage and capacity claims remain excluded.
DataCenterData record added · 13 September 2026 · Software-assisted second check
Cumulus Group LLC Buffalo Data Center → Publication
To Added as one proposed project from the live application and pending register; generator ratings and a possible Google relationship were not promoted.
Evidence https://apps.dep.wv.gov/Documents/DAQ/NSRPermits/079-00208/Draft/079-00208APP.pdf →
DataCenterData record added · 13 September 2026 · Software-assisted second check
Paducah Site AI/HPC Innovation Campus → Publication
To Added as one proposed campus; the 1.8 GW remains an announced design figure and separate generation and storage figures were excluded.
DataCenterData record added · 13 September 2026 · Software-assisted second check
Project Cardinal Data Center Campus → Publication
To Added with approved status bounded to the annexation agreement after independent review of Yorkville's project dockets.
Evidence https://www.yorkville.il.us/906/Project-Cardinal-Data-Center-Campus-Anne →
DataCenterData record added · 13 September 2026 · Software-assisted second check
Beale Data Center → Publication
To Added as one construction-stage campus after separate review of current City pages; planned buildings were kept out of operating-facility counts and operator identity remains unknown.
DataCenterData record added · 13 September 2026 · Software-assisted second check
Global AI (Colorado), LLC Data Center Project → Publication
To Added as one land-use-approved reuse project; construction, operation, capacity and operator remain unproven.
DataCenterData record added · 13 September 2026 · Software-assisted second check
To Added as one approved building after separate review of City permit and planning records; non-official capacity and construction claims were excluded.
Evidence https://www.cityofnampa.us/DocumentCenter/View/20607/Monthly-Activity-Report---April-2026 →
DataCenterData record added · 13 September 2026 · Software-assisted second check
Mineral Gap Data Center → Publication
To Added as a bounded operating-facility record after independent review of the cited Wise County source.
Evidence https://elevatewisecounty.com/top-industries/data-centers/ →
DataCenterData record added · 13 September 2026 · Software-assisted second check
Solis Arx / Fluidstack Progress Park Project → Publication
To Added as a bounded proposed-stage project after independent review of the cited Wythe County record.
DataCenterData record added · 13 September 2026 · Software-assisted second check
Apple Maiden Data Center Campus → Publication
To Added as one operating campus at Maiden/Catawba precision after separate review of the County statement; directory address, date, capacity and scale details were excluded.
DataCenterData record added · 13 September 2026 · Software-assisted second check
EdgeCore Shannon Hill Data Center Project → Publication
To Added as a bounded proposed-stage project after independent review of the cited Louisa County record.
Evidence https://www.louisacounty.gov/CivicAlerts.aspx?AID=470 →
DataCenterData record added · 13 September 2026 · Software-assisted second check
HostDime AI/Data Center → Publication
To Added as one construction-stage building after fresh review of the municipal packet and meeting page; directory naming, capacity and opening claims were excluded.
DataCenterData record added · 13 September 2026 · Software-assisted second check
To Added as a proposed data-center project after a second review of the Commission source; the separate generation-certificate approval is preserved without promoting the project lifecycle.
Evidence https://www.azcc.gov/news/home/2026/02/06/february-4--2026-open-meeting-highlights →
DataCenterData record added · 13 September 2026 · Software-assisted second check
Google West Memphis Campus → Publication
To Added as one construction-stage campus after fresh review of state, utility-commission and utility sources; unverified building, parcel and capacity details were excluded.
DataCenterData record added · 13 September 2026 · Software-assisted second check
Meta Tulsa Data Center → Publication
To Added as one construction-stage project; grid-energy capacity and industrial-park acreage were excluded from the data-center record.
Evidence https://www.okcommerce.gov/meta-breaks-ground-on-data-center-in-tulsa/ →
DataCenterData record added · 13 September 2026 · Software-assisted second check
STREAM U.S. Data Centers at STAMP (Project Double Reed) → Publication
To Added as one proposed project after fresh review of current GCEDC materials; the rescinded 2025 configuration was not counted separately and 500 MW was typed only as an applicant estimate.
Evidence https://www.gcedc.com/projects →
DataCenterData record added · 13 September 2026 · Software-assisted second check
Amazon Vicksburg Project → Publication
To Added as one state-announced proposed project; site, county, roles, approvals and capacity remain unknown.
DataCenterData record added · 13 September 2026 · Software-assisted second check
Goodnight Data Center → Publication
To Added as a permit-defined proposed project after independent review of current TCEQ records.
DataCenterData record added · 13 September 2026 · Software-assisted second check
Related Digital Cheyenne Data Center Campus → Publication
To Added as one construction-stage campus; the 302 MW and first-facility figures remain explicitly planned rather than current or operating.
DataCenterData record added · 13 September 2026 · Software-assisted second check
Apple Reno Data Center → Publication
To Added as a bounded operating-campus record after a second review of the Nevada GOED minutes and application packet.
Evidence https://goed.nv.gov/wp-content/uploads/2024/09/3.-GOED-Board-Meeting-Minutes-July-25-2024.pdf →
DataCenterData record added · 13 September 2026 · Software-assisted second check
Amazon Falls Township Data Center Project → Publication
To Added as one land-development-approved project; construction, operating roles and capacity remain unproven.
Evidence https://www.fallstwp.com/resources/news/article/?id=10070 →
DataCenterData record added · 13 September 2026 · Software-assisted second check
Massaponax Tech Campus → Publication
To Added as a bounded under-review project after independent review of Spotsylvania County case records.
12 September 20262 entries
DataCenterData record added · 12 September 2026 · Software-assisted second check
QTS Eagle Mountain Campus → Publication
To Added as a bounded construction-stage campus record after a second review of the cited Eagle Mountain City sources.
DataCenterData record added · 12 September 2026 · Software-assisted second check
Vantage Lighthouse Campus → Publication
To Added as a bounded construction-stage campus record after a second review of the cited Wisconsin DNR sources.
Evidence https://dnr.wisconsin.gov/topic/EIA/Portwashington.html →
Lifecycle events
30 June 20261 entry
agreement expired · CoreWeave / Digital Crossroads expansion
Hammond says required milestones were not satisfied and the expansion agreement expired after two extensions. The existing DX-1 facility remains a separate operating record.
Hammond agreement-expiration notice
Re-verified as a dated event entry: Agreement expired · 30 June 2026
11 February 20261 entry
groundbreaking · Meta — Lebanon
Meta and Indiana reported the Lebanon campus groundbreaking. Operation and promised outcomes are not yet due or established by this event.
9 June 20251 entry
development agreement approved · CoreWeave / Digital Crossroads expansion
Hammond approved a development agreement for a proposed CoreWeave-occupied expansion at 301 Digital Crossroads.
Hammond Common Council minutes
Re-verified as a dated event entry: Development agreement approved · 9 June 2025
Date not recorded6 entries
groundbreaking · Microsoft — La Porte
Microsoft reported groundbreaking in La Porte. Its job and cooling statements remain projections or design claims rather than observed outcomes.
partial operation · AWS — New Carlisle
Amazon says the multi-site Project Rainier compute cluster is operational and identifies New Carlisle as one site. Full New Carlisle campus completion is not established.
energization · Google — Fort Wayne
Indiana Michigan Power told the IURC that the site was energized in November 2024. The same 2026 order says Google had begun operation while construction continued, but it does not date the start of operation to November 2024.
IURC final order, Cause No. 46276
Re-verified as a dated event entry: Energization · November 2024
operator portfolio addition · Expedient — CMH3 / Lewis Center
Expedient announced that it added the former Nationwide facility to its portfolio in 2024. Nationwide remained the landlord while Expedient took operational control.
acquisition · STACK Infrastructure — NAL01 campus
STACK announced acquisition of a New Albany campus containing an existing purpose-built Tier III data center. The reviewed record does not establish whether that building is today's NAL01A or NAL01B.
acquisition · DataBank — CLE1
DataBank says it acquired the Cleveland facility from 365 Data Centers in 2017. The former operator is history, not a second facility.
Machine-readable files: changes.json, corrections.json, lifecycle-events.json and Atom feed.