Question reviewed
Answer
Verdict on the wording above: Unknown as of December 2025 target We looked; the reviewed sources do not establish it. Unknown is not zero, not absent, not noncompliant. How verdicts work →
- How it was framed
- A question DataCenterData examined; no one is quoted.
- What the evidence establishes
- We looked. The reviewed sources do not establish it. The operator page supports a planned three-building campus with 192 MW of planned critical IT load. It still carries a December 2025 first-building target and does not say the building opened. Unknown is not zero, not absent and not a failure.
- Biggest limitation
- Whether any OH1 building has opened or is serving load.
- Checked
- 12 September 2026 · Next review: Dated operator or municipal opening confirmation · History (1) →
Evidence
What the evidence supports
The operator page supports a planned three-building campus with 192 MW of planned critical IT load. It still carries a December 2025 first-building target and does not say the building opened. Actual opening is unknown. The passed December 2025 target is stale.
Still unknown
Whether any OH1 building has opened or is serving load.
Sources
-
Vantage OH1 campus overview → Archived copy Company
Exact location planned three-building campus, 192 MW critical IT load, December 2025 first-building target without opening confirmation
What it supports Planned specifications and a stale opening target. Not current load, grid demand, or an opening confirmation.
Corrections and history
Correction · 12 September 2026 · Software-assisted second check
vantage-oh1-new-albany → Opening status
Field Opening status
From The tested opening proposition was attributed directly to Vantage Data Centers.
To The proposition is labeled as a common reading; Vantage is cited only for its December 2025 opening target.
Why The operator page states a forecast and does not claim that the first building opened or is operating.
Evidence https://vantage-dc.com/data-center-locations/north-america/new-albany-ohio →
Review details
Scope
- Unit
- opening / operating milestone
- Geography
- Vantage OH1, three-building campus
- Period
- projected December 2025; checked 2026-09-12
- As of
- December 2025 target
- Confidence
- medium — Operator page rechecked 2026-09-12; it states a target, not an opening confirmation.
- Kind
- Question reviewed
Conflicting evidence
We looked; the reviewed sources do not establish it. That is not zero and not absent. No conflicting record has been logged either.
Chronology
- Source retrieved
- Changed field recorded
- Checked by DataCenterData
- Date not established Next review: Dated operator or municipal opening confirmation
Data
Suggest a correction
Suggest a correction → Claim ID claim:vantage-oh1-new-albany:opening and this page are prefilled. Accepted material corrections appear publicly on Changes.