Public statement checked
Answer
Verdict on the wording above: Unknown We looked; the reviewed sources do not establish it. Unknown is not zero, not absent, not noncompliant. How verdicts work →
- Who stated it
- Said by the City of Hammond · government record · 9 June 2025 →
- What the evidence establishes
- We looked. The reviewed sources do not establish it. The 9 June 2025 minutes describe a final NIPSCO agreement as gating the expansion. Unknown is not zero, not absent and not a failure.
- Biggest limitation
- Whether a NIPSCO agreement was ever executed, and which milestones failed; the executed development agreement, the extension resolutions and any NIPSCO filing for this expansion are not in the saved record.
- Checked
- 21 September 2026 · Next review: replacement proposal, new NIPSCO docket or new development agreement · History (3) →
Evidence
What the evidence supports
The 9 June 2025 minutes describe a final NIPSCO agreement as gating the expansion. No executed NIPSCO agreement is in the saved record, and the City's 1 July 2026 notice says the development agreement expired after two extensions because milestones were not satisfied by 30 June 2026, without naming which. The NIPSCO agreement remains unknown. The notice concerns the proposed 301 expansion, not the separate existing DX-1 facility; it does not freshly confirm current operation.
Still unknown
Whether a NIPSCO agreement was ever executed, and which milestones failed; the executed development agreement, the extension resolutions and any NIPSCO filing for this expansion are not in the saved record.
Sources
-
Hammond Common Council minutes, 9 June 2025 → Archived copy Gov. record
Exact location pp. 3–11 (resolution 25R-16 introduced p. 3; lease, jobs, tax terms and community impact payment p. 4; NIPSCO contingency p. 6)
What it supports Proposal, contemplated lease, jobs, tax terms, community payments and explicit power-agreement gating.
-
Hammond Common Council minutes, 22 December 2025 → Gov. record
Exact location pp. 1–4 ($80 million community-payment total p. 1; $25 million announced p. 2; 'Right now it's not part of it' p. 4); extension resolution at p. 10
What it supports Extension, utility negotiations and noncontractual $25 million discussion.
-
Hammond Announces Expiration of Data Center Development Agreement → Gov. record
Exact location News post body, first paragraph (byline July 1, 2026): 'The City of Hammond announced today that the Development Agreement for the proposed data center project at 301 Digital Crossroads has expired following two previously approved extensions.'
What it supports The development agreement among the City, the Redevelopment Commission, Decennial Group and CoreWeave expired after two extensions because milestones were not satisfied by the 30 June 2026 deadline. The notice does not say which milestones failed, does not show any payment or incentive as due or received, and concerns the proposed 301 expansion, not the separate existing DX-1 facility; it does not freshly confirm current operation.
Corrections and history
Correction · 11 September 2026 · DataCenterData review
coreweave-hammond → Power agreement
Field Power agreement
From Previous locator
To pp. 3–11 (resolution 25R-16 introduced p. 3; lease, jobs, tax terms and community impact payment p. 4; NIPSCO contingency p. 6)
Why 2026-09-11: previously 'pp. 3–4'.
Correction · 11 September 2026 · DataCenterData review
coreweave-hammond → Power agreement
Field Power agreement
From Previous locator
To pp. 1–4 ($80 million community-payment total p. 1; $25 million announced p. 2; 'Right now it's not part of it' p. 4); extension resolution at p. 10
Why 2026-09-11: previously 'pp. 1–2; extension resolution at p. 10'.
Correction · 21 September 2026 · DataCenterData review
coreweave-hammond → Power agreement
Field Power agreement
From No executed agreement located; exact failed milestones undisclosed.
To The 9 June 2025 minutes describe a final NIPSCO agreement as gating the expansion. No executed NIPSCO agreement is in the saved record, and the City's 1 July 2026 notice says the development agreement expired after two extensions because milestones were not satisfied by 30 June 2026, without naming which. The NIPSCO agreement remains unknown. The notice does not concern the operating DX-1 facility, which is a separate record.
Why City of Hammond notice of 1 July 2026: the development agreement expired after two extensions because milestones were not satisfied by 30 June 2026. The authorized terms (Resolution 25R-16, 8–0, 9 June 2025) are now recorded as lapsed; no payment, incentive or NIPSCO agreement is shown in the saved record. Verdict unchanged.
Evidence https://www.gohammond.com/hammond-announces-expiration-of-data-center-development-agreement/ →
Review details
Scope
- Unit
- power agreement
- Geography
- CoreWeave / Digital Crossroads expansion
- Period
- None recorded
- Confidence
- medium — city-council record
- Kind
- Public statement checked
Conflicting evidence
We looked; the reviewed sources do not establish it. That is not zero and not absent. No conflicting record has been logged either.
Chronology
- Stated by City of Hammond
- Published — Hammond Announces Expiration of Data Center Development Agreement
- Source retrieved
- Changed source locator recorded
- Source retrieved
- Source retrieved
- Changed field recorded
- Checked by DataCenterData
- Date not established Next review: replacement proposal, new NIPSCO docket or new development agreement