campus · CA · last checked 18 September 2026

Northtown Data Center (NTDC)

Lifecycle label: proposed; effective date not established Status evidence: Governor's Office of Land Use and Climate Innovation (LCI) / State Clearinghouse CEQAnet, SCH 2026070839; Document Type row 'NOP - Notice of Preparation of a Draft EIR'; Document Description, first sentence. The CEQAnet date label for 2026-07-21 is 'Received' - receipt of the notice by the State Clearinghouse, not a publication or posting date. California Energy Commission project page for the NorthTown Backup Generating Facility, docket 25-SPPE-02, summary table row 'Project Status: Under Review'. A Notice of Preparation begins CEQA environmental review; it is not an approval, exemption, permit, entitlement, construction start or operation. Evidence: Independently source-linked Reuse: Reference only

Facts at a glance

Record ID
northtown-data-center-san-jose-ca
Record type
campus
Developer
Not named in the cited records
Operator
Not named in the cited records
Owner
Owner of record not established
Tenant
Not named in the cited records
Capacity
up to 97.3 MW onsite generation planned · campus scope
Proposed emergency backup generation only. Both cited records describe up to 97.3 MW of backup emergency generation for the campus. This is not IT load, utility service capacity, or permitted generation, and it must not be summed with the 110 MVA substation rating.
Location
San Jose, CA
County: Santa Clara County
approximate — CEQAnet and the CEC page describe the site as the southwest corner of West Trimble Road and Orchard Parkway, San Jose, on parcels 101-02-018 and 101-02-021.
Physical scale
Physical scale: Two data-center buildings labelled DC North and DC West in the CEC notice.

What the sources support

A CEQAnet Notice of Preparation received on 21 July 2026, and the California Energy Commission project page for docket 25-SPPE-02, describe a proposed Northtown Data Center campus of two buildings in San Jose with a backup generating facility still under review. A notice of preparation is not an approval, permit, construction start or operation. A CEC Project Owner row for the backup-generating-facility docket is not campus ownership.

Definitions: record units · roles · capacity boundaries · lifecycle stages.

What remains unknown

Sources

Record history

Record history · 21 July 2026 · DataCenterData review

northtown-data-center-san-jose-ca → Record

Why The State Clearinghouse received the CEC Notice of Preparation of a Draft EIR (SCH 2026070839). Received is not a publication or approval date.

Evidence No additional evidence link; see the linked record or claim.

DataCenterData record added · 18 September 2026 · DataCenterData review

northtown-data-center-san-jose-ca → Publication

Why Added from the opened CEQAnet and CEC records. Backup-generation capacity is recorded as proposed onsite generation, not IT load.

Evidence No additional evidence link; see the linked record or claim.

Data + actions

Permanent link for citing this record →

Suggest a correction → Record ID northtown-data-center-san-jose-ca and the page are prefilled. Accepted material corrections appear on Changes.