Facts at a glance
- Record ID
goodman-energy-park-data-center-vernon-ca- Record type
- campus
- Evidence confidence
- medium
DataCenterData’s confidence in this record’s sourced fields, not in the project - Developer
- Not named in the cited records
- Operator
- Not named in the cited records
- Owner
- Owner of record not established
- Tenant
- Not named in the cited records
- Capacity
- up to 99 MW Planned on-site generation · campus scope
Proposed emergency backup generation only. The CEC page states the facility would be used exclusively to provide up to 99 MW of backup emergency generation when Vernon Public Utility electricity is unavailable. This is not IT load, utility service capacity, or permitted generation. Do not aggregate it with other figures. - Location
- Vernon, CA
County: Los Angeles County
Approximate location — CEQAnet and the CEC page place two data-center buildings at 3163 and 3049 East Vernon Avenue, Vernon, on parcels 6303-005-035 and 6303-005-036. - Physical scale
- Two data-center buildings at 3163 and 3049 East Vernon Avenue, as stated in the CEC and CEQAnet notices.
What the sources support
A CEQAnet Notice of Preparation received on 5 August 2026, and the California Energy Commission project page for docket 25-SPPE-01, describe a proposed Goodman Energy Park data-center campus of two buildings in Vernon with a backup generating facility still under review. A notice of preparation is not an approval, permit, construction start or operation. A CEC Project Owner row for the backup-generating-facility docket is not campus ownership.
Definitions: record units · roles · capacity boundaries · lifecycle stages.
What remains unknown
- critical IT capacity
- utility service capacity or requested load from Vernon Public Utility
- developer
- operator
- tenant
- owner of the data-center buildings as distinct from the backup-generating-facility docket applicant
- whether the City of Vernon has granted any land-use entitlement
- whether the CEC has granted or denied the Small Power Plant Exemption
- building floor areas
- construction start or completion dates
Sources
-
Governor's Office of Land Use and Climate Innovation (LCI) / State Clearinghouse CEQAnet →Gov. record
Exact location SCH 2026080118, NOP document page 'Vernon Backup Generating Facility'; Summary rows SCH Number / Lead Agency / Document Type / Received; Document Description; Contact Information; Location Parcel Number; Total Acres; Notice of Completion review-period rows
What it supports CEQAnet listing for the California Energy Commission Notice of Preparation of a Draft EIR, received by the State Clearinghouse 8/5/2026. Lead Agency: California Energy Commission. Document Description states that GIC Vernon LLC is applying to the CEC for a Small Power Plant Exemption for the Vernon Backup Generating Facility, a 99 MW emergency only power system that will support the Goodman Energy Park (GEP) data center in the City of Vernon; that the GEP consists of two data center buildings near Vernon Avenue and Soto Street at 3163 and 3049 East Vernon Avenue; forty (40) diesel generators, thirty eight (38) at 3 MW for data center critical loads and two 1 MW house generators; designed to operate only when electricity from Vernon Public Utility is unavailable; will not connect to the regional transmission grid or export power. Location rows give Cities 'Vernon', Counties 'Los Angeles', Cross Streets 'Vernon Avenue and Soto Street', Zip 90058, Total Acres 11.55, Parcel # 6303-005-035 and 6303-005-036, Coordinates 34°0'24.89"N 118°13'4.68"W. Contact Information names Ward Mace, Agency Name GIC Vernon LLC, Job Title Regional Director, Contact Types 'Project Applicant'.
-
Vernon Backup Generating Facility (VBGF) - California Energy Commission project page →Gov. record
Exact location Summary table rows 'Project Owner', 'Docket Number', 'Capacity', 'Location', 'Technology', 'Project Status', 'Project Type'; 'Project Description' paragraphs 1-2; 'Data Centers' section; 'Small Power Plant Exemption' section
What it supports California Energy Commission project page for docket 25-SPPE-01. Summary table: Project Owner 'GIC Vernon LLC'; Capacity '99 MW'; Location 'Vernon, California'; Technology 'Backup Generating System'; Project Status 'Under Review'; Project Type 'Small Power Plant Exemption'. Project Description states the VBGF would consist of forty (40) diesel fired generators used exclusively to provide up to 99 megawatts (MW) of backup emergency generation to support the Goodman Energy Park Data Center (GEP) when electricity from Vernon Public Utility (VPU) is unavailable; that the GEP would consist of two data center buildings, Building 1 at 3163 East Vernon Avenue and Building 2 at 3049 East Vernon Avenue; that the VBGF would not be electrically interconnected to the transmission grid; that VPU would own and operate a new switching station on the GEP site; and that the project applicant GIC Vernon would own and operate the Project Substation. The page states the CEC does not permit data centers, and that in granting an SPPE the CEC is not the final approval necessary for construction and operation of a project.
Sourced classifications
Only values a cited source states for this site are shown; every other dimension is unknown. These are not national shares or rankings.
- Power source: Utility grid service
“The GEP would be supplied electricity by VPU through a new switching station on the GEP site that would be owned and operated by VPU (VPU Switching Station).” — Vernon Backup Generating Facility (VBGF) — project page, Docket 25-SPPE-01, Project Description, second paragraph, retrieved 24 September 2026
Not established: Energization; service capacity; generation mix of the utility supply. - Power source: On-site generation (backup, diesel or renewable diesel)
“The Vernon Backup Generating Facility (VBGF) would consist of a total of forty (40) diesel fired generators that would be used exclusively to provide up to 99 megawatts (MW) of backup emergency generation to support the Goodman Energy Park Data Center (GEP)” — Vernon Backup Generating Facility (VBGF) — project page, Docket 25-SPPE-01, Project Description, first paragraph, retrieved 24 September 2026
Not established: Exemption approval, installation or operation; that the campus runs on diesel. - Power counterparty: Vernon Public Utility (VPU) — Serving utility (agreement planned)
“The VBGF would not be electrically interconnected to the electrical transmission grid. The GEP would be supplied electricity by VPU through a new switching station on the GEP site that would be owned and operated by VPU (VPU Switching Station).” — Vernon Backup Generating Facility (VBGF) — project page, Docket 25-SPPE-01, Project Description, second paragraph, retrieved 24 September 2026
Not established: An executed service agreement; contracted or delivered MW; that the project is approved or built (SPPE status: Under Review).
Connected records
Each connection below is a stored, reviewed relationship with its own basis. It does not change this record’s status.
Metro area: Los Angeles-Long Beach-Anaheim, CA
Dated events
Real-world events recorded for this record, newest event date first. Each event page shows its source, dates and what it does not establish.
Environmental review notice issuedOfficial recordCalifornia
Environmental review notice issued on 5 August 2026: Goodman Energy Park (GEP) data center (Vernon, CA) — state energy commission notice of preparation dated 5 August 2026
- Event date
- Source dated
- Added to Latest updates
Record history
Record history · 5 August 2026 · DataCenterData review
goodman-energy-park-data-center-vernon-ca → Record
Why The State Clearinghouse received the CEC Notice of Preparation of a Draft EIR (SCH 2026080118). Received is not a publication or approval date.
Evidence No additional evidence link; see the linked record or claim.
Dated event entry: Environmental review notice issued · 5 August 2026
DataCenterData record added · 18 September 2026 · DataCenterData review
goodman-energy-park-data-center-vernon-ca → Publication
Why Added from the opened CEQAnet and CEC records. Backup-generation capacity is recorded as proposed onsite generation, not IT load.
Evidence No additional evidence link; see the linked record or claim.
Recorded information
What this page records, grouped by topic, with the source's units and qualifications. Company-reported values stay labeled as company-reported. Related listings are shown separately.
Reviewed record goodman-energy-park-data-center-vernon-ca
Campus.
Location and precision
- Shown above in Facts at a glance.
Lifecycle
- Recorded status: proposed
Area, acreage and buildings
- Shown above in Facts at a glance.
Power capacity
- Shown above in Facts at a glance.
Not yet recorded here: Roles · Cooling, water, PUE and WUE · Connectivity · Services · Certifications and design ratings · Rack density · Availability · Specification links and contact · Permits, incentives, jobs and proceedings.
Update this profile with a public source. The request includes topics needing more information; this does not mean the facility lacks them. Corrections and additions are reviewed before publication.
Data + actions
Permanent link for citing this record →
Suggest a correction → Record ID goodman-energy-park-data-center-vernon-ca and the page are prefilled. Accepted material corrections appear on Changes.