Lifecycle label: expanding; effective date not establishedStatus evidence: operator-reportedEvidence: Independently source-linkedReuse: Reference only
Facts at a glance
Record ID
applied-digital-polaris-forge-1-ellendale-nd
Record type
campus
Evidence confidence
high DataCenterData’s confidence in this record’s sourced fields, not in the project
Developer
Applied Digital
Operator
Applied Digital
Owner
Owner of record not established
Tenant
Not named in the cited records
Capacity
operator-reported live 175 MW Capacity type not recorded · campus scope Operator-reported "total live capacity at the campus" on July 1, 2026, after Phase 1 of Building 2 (75 MW) entered service. The release does not state whether this is critical IT load; the 10-K states the first building's roughly 100 MW as critical IT load. This is the operator's figure for capacity in service, not measured electricity use, utility service capacity or the planned total. The 400 MW contracted at full build-out is a separate planned figure (see physical scale).
Location
Ellendale, ND Approximate location — The SEC filing and the operator release name Ellendale, North Dakota. They give no street, parcel, county or coordinates. The filing separately describes a 180 MW Ellendale blockchain-hosting facility; its physical relationship to this HPC campus is unresolved.
Physical scale
The 10-K describes three HPC data-center buildings: the first (about 100 MW critical IT load) operational since October 2025, the second (about 150 MW expected) partially operational, and the third (about 150 MW expected) under construction with ready-for-service anticipated in calendar year 2027. Leases with CoreWeave, the anchor tenant, total 400 MW of contracted critical IT load at full build-out; that is a planned total, not operating capacity. CoreWeave is the tenant, not the operator. Filings and releases number the buildings differently (the release's "Building 2" is the filing's partially operational second data center), so no building count is asserted.
What the sources support
Applied Digital's Form 10-K for the fiscal year ended May 31, 2026, filed July 29, 2026, says the first HPC data center at its Ellendale campus (about 100 MW of critical IT load) became operational in October 2025, a second data center expected to add about 150 MW is partially operational, and a third, about 150 MW, is under construction. The company's July 1, 2026 release reports Ready for Service for Phase 1 of Building 2 and total live capacity at the campus of 175 MW. The campus is partly operating while construction continues; its planned full build-out is not operating.
Exact location Part I, Item 1, Business — HPC Hosting Business, 'Polaris Forge 1' paragraph; contracted HPC lease portfolio table as of May 31, 2026
What it supports Campus name and Ellendale location; Applied Digital designs, constructs, owns and operates; first building operational October 2025 at about 100 MW critical IT load; second building partially operational; third under construction; CoreWeave leases totalling 400 MW contracted critical IT load.
Why Applied Digital filed its Form 10-K describing the first building as operational since October 2025, the second as partially operational and the third as under construction.
Evidence No additional evidence link; see the linked record or claim.
DataCenterData record added · 26 September 2026 · DataCenterData review
Why Added as one partly operating campus with continuing construction; the operator-reported 175 MW live capacity is kept separate from the 400 MW contracted full build-out.
Evidence No additional evidence link; see the linked record or claim.
Recorded information
What this page records, grouped by topic, with the source's units and qualifications. Company-reported values stay labeled as company-reported. Related listings are shown separately.
Reviewed record applied-digital-polaris-forge-1-ellendale-nd
Campus · Applied Digital. Independently reviewed record. Values are shown with their recorded basis.
Location and precision
Shown above in Facts at a glance.
Roles
Shown above in Facts at a glance.
Lifecycle
Recorded status: expanding
Area, acreage and buildings
Shown above in Facts at a glance.
Power capacity
Shown above in Facts at a glance.
Not yet recorded here: Cooling, water, PUE and WUE · Connectivity · Services · Certifications and design ratings · Rack density · Availability · Specification links and contact · Permits, incentives, jobs and proceedings.
Update this profile with a public source. The request includes topics needing more information; this does not mean the facility lacks them. Corrections and additions are reviewed before publication.
Also listed as dcd-dir-000085 in the licensed third-party directory; that directory row is not independently verified.
Suggest a correction → Record ID applied-digital-polaris-forge-1-ellendale-nd and the page are prefilled. Accepted material corrections appear on Changes.
2 statement(s) naming an operator or presence at this site unit, one row per source. A building with several tenants is one facility with several presence rows.
expanding Status basis: Applied Digital's Form 10-K for the fiscal year ended May 31, 2026, filed July 29, 2026, says the first HPC data center at its Ellendale campus (about 100 MW of critical IT load) became operational in October 2025, a second data center expected to add about 150 MW is partially operational, and a third, about 150 MW, is under construction. The company's July 1, 2026 release reports Ready for Service for Phase 1 of Building 2 and total live capacity at the campus of 175 MW. The campus is partly operating while construction continues; its planned full build-out is not operating.
Provider row updated Provider-reported announcement date: June 2025 Provider dates do not establish when this status began or whether it remains current.
Layers disagree; not reconciled. Each value is what that layer states; DataCenterData does not pick one.
Capacity by kind
Each row is one kind of figure from one source. Utility, generation, design, critical IT and floor-area figures measure different things; they are never summed or totalled.
Kind
Value and evidence
Scope and timing
Date
Source
Provider-reported capacity
Operational: 100 MW; Planned: 400 MW (source-reported; boundary not independently verified; MW measure not stated by provider) provider-reported
Records are grouped by system and may describe requests or plans. A highlighted group does not prove every named component is installed or operating. Labels name the source, not a confidence rating. A part with no record here may still exist. Each part links to how it works.
Quote-bound facts: each shows the value, the source address, the capture hash (first 12 characters; the full SHA-256 is in the page markup) and the capture date. The source's exact wording stays in the capture record and is not republished here; the capture hash binds it.
No quote-bound fact with a hashed capture is recorded for this facility.
Other values by layer
Field
Value
Layer and basis
Date
Source
capacity unclassified
175 MW (operator-reported live)
Reviewed (DCD) · reviewed record
Latest source retrieval/capture date date not stated
The 10-K describes three HPC data-center buildings: the first (about 100 MW critical IT load) operational since October 2025, the second (about 150 MW expected) partially operational, and the third (about 150 MW expected) under construction with ready-for-service anticipated in calendar year 2027. Leases with CoreWeave, the anchor tenant, total 400 MW of contracted critical IT load at full build-out; that is a planned total, not operating capacity. CoreWeave is the tenant, not the operator. Filings and releases number the buildings differently (the release's "Building 2" is the filing's partially operational second data center), so no building count is asserted.
Reviewed (DCD) · reviewed record
Latest source retrieval/capture date date not stated
These citations belong to the linked reviewed records. They do not establish every figure or present-day operating status. Publication and retrieval dates are shown separately; an unstated date remains unknown.
26 fields in the shared profile are not established for this record. Each states why; missing information does not mean zero or absence.
Street address · not recorded for this field in the register
Postal code · not recorded for this field in the register
Map location precision · not recorded for this field in the register
Operator-stated status · not recorded for this field in the register
Status in public records · not recorded for this field in the register
Critical IT capacity (MW) · not recorded for this field in the register
Requested utility capacity (MW) · not recorded for this field in the register
Reported total power (MW) · not recorded for this field in the register
Generation capacity (MW) · not recorded for this field in the register
Company-announced design capacity (MW) · not recorded for this field in the register
Floor area (sq ft) · not recorded for this field in the register
Data hall or IT floor area (sq ft) · not recorded for this field in the register
Cooling redundancy · not recorded for this field in the register
UPS redundancy · not recorded for this field in the register
Backup generator redundancy · not recorded for this field in the register
Tier design rating · not recorded for this field in the register
Opening year or expected opening year · not recorded for this field in the register
Network presence · not recorded for this field in the register
Service · not recorded for this field in the register
Certification or compliance claims · not recorded for this field in the register
Rack density · not recorded for this field in the register
Space or power availability · not recorded for this field in the register
Specifications and facility pages · not recorded for this field in the register
Business contact · not recorded for this field in the register
Public registration · not recorded for this field in the register
Fact supported by a source quotation · not recorded for this field in the register
Jurisdiction and policy actions
Policy actions are matched to this facility by jurisdiction (state, county, municipality or utility), never by the facility's name. A match means the action covers the place, not that it names or affects this facility.
We plan to re-check this facility every 90 days because it has a reviewed record whose status may still change. Next check due . The last-checked date is the newest evidence date among this facility's sources. Dates are measured against the newest input date, , not the day this page was built.
Update this profile with a public source. The request includes topics needing more information; this does not mean the facility lacks them. Corrections and additions are reviewed before publication.
These questions are open. Nothing has been merged or dismissed; a reviewer resolves each with captured evidence.
A possible duplicate source row (Operator-listed capture dcd-op-000547) is under review (reason: city_only_single_candidate, opened ; hold hold-000176). Evidence needed: A street address, parcel id or coordinate source for the city-only row, or a reviewed decision on the candidate.
A possible duplicate source row (Operator-listed capture dcd-op-000548) is under review (reason: city_only_single_candidate, opened ; hold hold-000177). Evidence needed: A street address, parcel id or coordinate source for the city-only row, or a reviewed decision on the candidate.
Rights for this record
For each populated field, the origin of the value shown on this page and the terms it carries. Values that are not redistributable may be read and cited here but are not relicensed.
Values marked Compute Atlas are adapted from Compute Atlas by Edward Kubiak under CC BY 4.0: Compute-infrastructure data from Compute Atlas by Edward Kubiak. DataCenterData did not independently verify them.