Latest updates · 28 dated events · Newest log entry: 6 November 2026

Latest data center updates

Dated permits, filings, approvals and other project events from official records and attributed company statements, for sites DataCenterData tracks. Each links to its source, gives the date the source states and says what the event does not establish.

About these streams

Three different things, kept apart. Facility and project events happened in the world on the date the source gives. Evidence updates are DataCenterData publishing records; they are not events at a facility. Corrections to what DataCenterData published live in the corrections history, the corrections authority.

Newest in each stream

Latest policy changes, developments, events and corrections.

Up to 5 of the newest from each stream, newest first. Each date is the item's own date: the policy action, the development or event, or the correction. Full lists for each stream follow.

  1. Correction

    Governor of Nevada · NV · Taxes / incentives

  2. Correction

    Vantage Data Centers — OH2 Millersport campus · Millersport, OH · OPSB / generation status

  3. Correction

    Vantage Data Centers — OH2 Millersport campus · Millersport, OH · OPSB / generation status

  4. Correction

    Vantage Data Centers — OH2 Millersport campus · Millersport, OH · Power / developer claim

  5. Correction

    Water / permits · OH

  6. Policy change

    Pennsylvania: HB 2888 proposed reporting and community-benefit requirements — source document dated 4 November 2026

  7. Policy change

    City of Littleton, Colorado: proposed six-month moratorium on data center applications (Ordinance No. 22, Series 2026) — source document dated 21 October 2026

  8. Policy change

    City of Suffolk, Virginia: proposed zoning amendment listing data centers as a prohibited use in all districts (OTA2026-008) — source document dated 21 October 2026

  9. Policy change

    Oakland, California: proposed 10-month, 15-day extension of data center moratorium ordinance (File 27-0178) — source document dated 21 October 2026

  10. Policy change

    City of Memphis, Tennessee: proposed temporary data center permit moratorium (Ord. 5982) — source document dated 20 October 2026

  11. Project development

    Litigation: NMED's AQB 26-57 docket lists an Order Lifting Stay from the New Mexico Supreme Court (Doña Ana County, NM)

  12. Facility or project event

    Special use approved on 9 September 2026: Global AI (Colorado), LLC Data Center Project (CO) — county press release dated 10 September 2026

  13. Facility or project event

    Application deemed complete on 24 August 2026: Amazon Attalia Data Center Campus (WA) — county determination of completeness dated 24 August 2026

  14. Facility or project event

    Environmental review notice issued on 5 August 2026: Goodman Energy Park (GEP) data center (Vernon, CA) — state energy commission notice of preparation dated 5 August 2026

  15. Facility or project event

    Botetourt County permit issued in August 2026: Google Data Center Campus — Botetourt Center at Greenfield (VA) — land disturbance permit for Mass Grading Package No. 1 (phased grading)

  16. Facility or project event

    Air permit application received on 24 July 2026: Amazon Data Services — Hobart project (Hobart, IN) — state air permit application record dated 24 July 2026

  17. Project development

    Permit or regulatory change: Indianapolis commission recorded Thunderbird petition approvals (Marion County, IN)

  18. Project development

    Permit or regulatory change: GCEDC project page lists an April 16, 2026 public hearing on the STREAM STAMP project (Genesee County, NY)

  19. Project development

    Permit or regulatory change: Gilroy project page records a building permit issued March 19, 2026 (Santa Clara County, CA)

  20. Project development

    Permit or regulatory change: TCEQ index lists a Nexus Data Center Hubbard application received February 17, 2026 (Hill County, TX)

Project developments

Openings, expansions, construction milestones, financing, contracts and ownership changes, as well as delays, disputes, litigation, pauses and cancellations, are kept in their own stream, because they can rest on company filings and attributed reporting as well as official records. 8 reviewed developments so far. Project developments → Project developments feed

Facility and project events

What happened, by event date.

Newest event date first. Official records are stated in DataCenterData's voice; company statements are attributed to the company. None of these is a correction.

  1. Special use approvedOfficial recordColorado

    Special use approved on 9 September 2026: Global AI (Colorado), LLC Data Center Project (CO) — county press release dated 10 September 2026

    The Weld County Board of County Commissioners voted 5-0 on September 9, 2026 to approve Use by Special Review permit USR26-0019 for Global AI (Colorado), LLC to operate a data center in an existing industrial facility near Windsor.

    Organization named in the record
    Weld County Board of County Commissioners
    Not established by this event
    Issuance of building or construction permits; Construction start; Completion, energization or operation; Approval of any future phase or expansion.
    Event date
    Source dated
    Added to Latest updates
  2. Application deemed completeOfficial recordWashington

    Application deemed complete on 24 August 2026: Amazon Attalia Data Center Campus (WA) — county determination of completeness dated 24 August 2026

    Walla Walla County Community Development Department determined on August 24, 2026 that the Site Development Permit and SEPA applications (SDP26-01, SEPA26-05) filed by Amazon Data Services, Inc. were complete for review; the applications concern the Amazon Attalia Data Center Campus, and the county stated that no final decision had been made.

    Organization named in the record
    Walla Walla County Community Development Department
    Not established by this event
    Any approval or permit issuance; Construction start; Completion, energization or operation.
    Event date
    Source dated
    Added to Latest updates
  3. Environmental review notice issuedOfficial recordCalifornia

    Environmental review notice issued on 5 August 2026: Goodman Energy Park (GEP) data center (Vernon, CA) — state energy commission notice of preparation dated 5 August 2026

    California Energy Commission staff issued a Notice of Preparation of a Draft EIR on August 5, 2026 for GIC Vernon LLC's Vernon Backup Generating Facility (docket 25-SPPE-01), which the notice describes as part of the Goodman Energy Park Data Center in Vernon.

    Organization named in the record
    California Energy Commission staff
    Not established by this event
    Any approval, exemption or permit; Construction start; Operation or energization; That 99 MW of backup generation equals IT load.
    Event date
    Source dated
    Added to Latest updates
  4. Permit issuedOfficial recordVirginia

    Botetourt County permit issued in August 2026: Google Data Center Campus — Botetourt Center at Greenfield (VA) — land disturbance permit for Mass Grading Package No. 1 (phased grading)

    Botetourt County reported that Google had received a County Land Disturbance Permit, after the County completed review of Mass Grading Package No. 1, allowing phased grading on its 312-acre site in the Botetourt Center at Greenfield.

    Organization named in the record
    Botetourt County
    Not established by this event
    start of grading or construction; building permits; state or federal environmental permits; completion, energization or operation.
    Event date
    Source dated
    Added to Latest updates
  5. Air permit application receivedOfficial recordIndiana

    Air permit application received on 24 July 2026: Amazon Data Services — Hobart project (Hobart, IN) — state air permit application record dated 24 July 2026

    IDEM's Office of Air Quality received (by email, July 24, 2026) an application filed on behalf of Amazon Data Services, Inc. for New Source Minor PSD/EO construction approval and a FESOP covering data-center sites SBN520 (4751 E. 61st Avenue) and SBN750 (6197 Colorado St.) in Hobart.

    Organization named in the record
    Indiana Department of Environmental Management
    Not established by this event
    Permit issuance; Construction start; Operation.
    Event date
    Source dated
    Added to Latest updates
  6. Stormwater permit notice filedOfficial recordOhio

    Stormwater permit notice filed on 21 July 2026: QTS Data Centers — Van Wert campus (Van Wert, OH) — state stormwater notice of intent dated 21 July 2026

    QTS Realty Trust Inc. electronically submitted to Ohio EPA a Notice of Intent for new coverage under Construction Site Stormwater General Permit OHC000006 for the 'QTS Data Center' at 8002 Mendon Road, Van Wert (792 acres of proposed land disturbance).

    Organization named in the record
    Ohio EPA
    Not established by this event
    Permit coverage granted; Construction start; Operation.
    Event date
    Source dated
    Added to Latest updates
  7. Environmental review notice issuedOfficial recordCalifornia

    Environmental review notice issued on 21 July 2026: Northtown Data Center (NTDC) (San Jose, CA) — state energy commission notice of preparation dated 21 July 2026

    California Energy Commission staff issued a Notice of Preparation of a Draft EIR on July 21, 2026 for GIC San Jose LLC's NorthTown Backup Generating Facility (docket 25-SPPE-02), which the notice describes as planned as part of the NorthTown Park Data Center in San José.

    Organization named in the record
    California Energy Commission staff
    Not established by this event
    Any approval, exemption or permit; Construction start; Operation or energization; That 97.3 MW of backup generation equals IT load.
    Event date
    Source dated
    Added to Latest updates
  8. Construction reportedOfficial recordVirginia

    Construction reported in July 2026: Google Bermuda Hundred Data Center Campus (VA) — county project status table dated July 2026

    Chesterfield County's 'Data Center Project Status as of July 2026' table lists Peanut LLC at 2100 Bermuda Hundred Road as 'Under construction; three buildings'.

    Organization named in the record
    Chesterfield County
    Not established by this event
    construction start date; completion; energization or operation.
    Event date
    Source dated
    Added to Latest updates
  9. Agreement expiredOfficial recordIndiana

    Agreement expired on 30 June 2026: CoreWeave / Digital Crossroads expansion (Hammond, IN) — city notice dated 1 July 2026

    The City of Hammond announced that the four-party development agreement for the proposed data center at 301 Digital Crossroads (City, Redevelopment Commission, Decennial Group and CoreWeave) expired because required milestones were not satisfied by the June 30, 2026 deadline.

    Organization named in the record
    City of Hammond
    Not established by this event
    Closure of the existing Digital Crossroad DX-1 facility; Cancellation of any CoreWeave activity elsewhere.
    Event date
    Source dated
    Added to Latest updates
  10. Utility contract approvedOfficial recordIndiana

    Utility contract approved on 17 June 2026: Amazon / NIPSCO northern Indiana service program (IN) — utility commission order dated 17 June 2026

    The Indiana Utility Regulatory Commission approved the settlement, NIPSCO's 'Data Center Customer #1' special contract with Amazon Data Services, Inc., the NIPSCO–NIPSCO Generation power purchase agreement and related alternative regulatory plans.

    Organization named in the record
    Indiana Utility Regulatory Commission
    Not established by this event
    Service commencement; Construction of the GenCo generation or transmission assets; Any Amazon facility's construction or operation.
    Event date
    Source dated
    Added to Latest updates
  11. Construction reportedOfficial recordMissouri

    Construction reported on 21 May 2026: Rifle Range Road Data Center Project (MO) — county commission update dated 21 May 2026

    The Webster County Commission's May 21, 2026 update describes a data center project as currently under construction on Rifle Range Road in rural Webster County, north and east of Marshfield.

    Organization named in the record
    Webster County Commission
    Not established by this event
    Construction start date; Completion, energization or operation.
    Event date
    Source dated
    Added to Latest updates
  12. Rezoning approvedOfficial recordAlabama

    Rezoning approved on 21 April 2026: AL Bessemer Land Data Center Project (Bessemer, AL) — city ordinance dated 21 April 2026

    The Bessemer City Council adopted, and the Mayor approved, Ordinance No. 3698 on April 21, 2026, rezoning the property in AL Bessemer Land, LLC's application from A-1 vacant Agricultural to I-1 Light Industrial for construction and operation of a multi-phased data center.

    Organization named in the record
    Bessemer City Council
    Not established by this event
    construction; building permits; operation.
    Event date
    Source dated
    Added to Latest updates
  13. Construction reportedOfficial recordUtah

    Construction reported on 17 April 2026: QTS Eagle Mountain Campus (Eagle Mountain, UT) — city press release dated 20 April 2026

    Eagle Mountain City reported that on April 17, 2026 crews placed the final beam on the first QTS data center building in Eagle Mountain, and that construction will continue on interior systems and the remaining buildings.

    Organization named in the record
    Eagle Mountain City
    Not established by this event
    Building completion (structural topping-out only); Energization or operation.
    Event date
    Source dated
    Added to Latest updates
  14. Permit issuedOfficial recordWashington

    Washington Ecology permit 26AQ-E016 issued on 6 April 2026: Intergate Quincy — Sabey Data Center Properties (Quincy, WA) — approval order adding 13 emergency generators for Building E

    Washington Ecology issued Notice of Construction Approval Order 26AQ-E016 on April 6, 2026 to Intergate Quincy – Sabey Data Center Properties, approving 13 additional emergency generators for Building E at the existing data center at 2200 M Street NE, Quincy.

    Organization named in the record
    Washington Ecology
    Not established by this event
    Installation or operation of the added generators; Building E completion or operation; IT capacity (generator MWe is not IT load).
    Event date
    Source dated
    Added to Latest updates
  15. Air permit application receivedOfficial recordPennsylvania

    Air permit application received in April 2026: Amazon Falls Township Data Center Project (Falls Township, PA) — state environmental agency release dated 13 July 2026

    The Pennsylvania DEP states that in April 2026 Amazon submitted an air quality plan approval application (Minor New Source Plan Approval Application No. 09-0261A) for 280 natural gas-fired generator engines and three diesel-fired emergency generator engines for the Amazon data center at the Keystone Trade Center in Falls Township.

    Organization named in the record
    Pennsylvania DEP
    Not established by this event
    plan approval issuance; generator installation; construction start or completion; energization or operation.
    Event date
    Source dated
    Added to Latest updates
  16. Permit issuedOfficial recordMaryland

    Maryland Department of the Environment permit issued on 25 March 2026: Amazon Data Services BWI-150–BWI-153 Campus (MD) — construction permit (control no. B-08076) for 99 diesel emergency generators at BWI-150 to BWI-153

    The Maryland Department of the Environment issued a Construction Permit (Control No. B-08076) to Amazon Data Services, Inc. for BWI-150 through BWI-153 at 3250 Digital Drive, Frederick, covering 99 diesel-fired emergency generators.

    Organization named in the record
    Maryland Department of the Environment
    Not established by this event
    construction of the data-center buildings; generator installation or operation; facility operation or energization.
    Event date
    Source dated
    Added to Latest updates
  17. Final plat approvedOfficial recordLouisiana

    Final plat approved on 18 March 2026: Technology Park Data Center Project (LA) — parish government release dated 20 March 2026

    The Bossier Parish Police Jury, at its March 18, 2026 regular agenda meeting, unanimously approved the Benton Metropolitan Planning Commission's final plat recommendation for the Technology Park supporting the new Amazon data center.

    Organization named in the record
    Bossier Parish Police Jury
    Not established by this event
    construction; building permits; operation.
    Event date
    Source dated
    Added to Latest updates
  18. Variance approvedOfficial recordIndiana

    Variance approved on 18 March 2026: Sabey — Decatur Technology Park (Indianapolis, IN) — development commission hearing results dated 18 March 2026

    The Indianapolis Metropolitan Development Commission approved, subject to commitments, petitions 2025-CAP-856 (modification of commitments) and 2025-CVR-856 (2nd Amended, variances for a data center technology park) filed by Sabey Data Center Properties, LLC for Kentucky Avenue/Camby Road parcels.

    Organization named in the record
    Indianapolis Metropolitan Development Commission
    Not established by this event
    Construction start; Final approval certification; Operation.
    Event date
    Source dated
    Added to Latest updates
  19. Permit issuedOfficial recordWashington

    Washington Ecology permit 26AQ-E008 issued on 22 January 2026: CyrusOne — Quincy Data Center (Quincy, WA) — revised approval order cutting permitted emergency generators from 42 to 22

    Washington Ecology issued Notice of Construction Approval Order 26AQ-E008 on January 22, 2026 to CyrusOne LLC for its existing Quincy data center at 1025 D Street NW, reducing the facility's permitted emergency generators from 42 to 22 and revising the permit's conditions.

    Organization named in the record
    Washington Ecology
    Not established by this event
    Any change in IT capacity or operating status; Closure or downsizing of IT load (a generator-count reduction is not a capacity statement).
    Event date
    Source dated
    Added to Latest updates
  20. Rezoning approvedOfficial recordSouth Dakota

    Rezoning approved on 6 January 2026: Gemini Addition (Sioux Falls, SD) — city council minutes dated 6 January 2026

    The Sioux Falls City Council on January 6, 2026 adopted Ordinance No. 5-26 rezoning land south of E. Rice St. and east of Veterans Pkwy (petition 022049-2025) and Resolution No. 4-26 approving the Gemini Addition preliminary plan, conditioned on any data center being limited to domestic water usage; applicant Gemini Data Center SD, LLC.

    Organization named in the record
    Sioux Falls City Council
    Not established by this event
    Final plat or site-plan approval; Building permit or construction start; Operation.
    Event date
    Source dated
    Added to Latest updates

All 28 dated events →

Policy changes

What changed in data-center policy.

320 sourced policy records have a dated adoption, effective or source-document action. Newest policy action dated 4 November 2026. These are the dates of the policy actions, not the dates entries were added to this log, so policy changes have their own list and feed.

All policy changes, newest first →Policy changes feed (Atom) →Moratoriums and pauses in effect now →

Evidence updates

What DataCenterData published.

Newly published evidence records, newest first. Publishing a record is not an event at a facility; its status label is the reviewed evidence label on the date shown.

  1. Evidence updateDataCenterData publicationVirginia

    Evidence record published: EdgeCore AS01 (Sterling, VA)

    Published on DataCenterData
  2. Evidence updateDataCenterData publicationVirginia

    Evidence record published: Pacific Corporate Park (PowerHouse Pacific) (Sterling, VA)

    Published on DataCenterData
  3. Evidence updateDataCenterData publicationVirginia

    Evidence record published: EdgeCore AS02 (Sterling, VA)

    Published on DataCenterData
  4. Evidence updateDataCenterData publicationVirginia

    Evidence record published: PowerHouse Arcola (VA)

    Published on DataCenterData
  5. Evidence updateDataCenterData publicationNorth Dakota

    Evidence record published: Polaris Forge 1 (Ellendale, ND)

    Published on DataCenterData
  6. Evidence updateDataCenterData publicationVirginia

    Evidence record published: Google data center, Prince William County (VA)

    Published on DataCenterData
  7. Evidence updateDataCenterData publicationWashington

    Evidence record published: CyrusOne — Quincy Data Center (Quincy, WA)

    Published on DataCenterData
  8. Evidence updateDataCenterData publicationWashington

    Evidence record published: Vantage Data Centers — Quincy Campus (Quincy, WA)

    Published on DataCenterData

All 68 evidence updates →

Corrections

Corrections to wording, locators, source dates, classifications or facts that DataCenterData previously published are not updates about a facility. They are logged, with the old and new values, in the corrections history.

Follow updates

Feeds carry the same wording as these pages. Feed timestamps are when an entry entered this updates log, never an event date or a record's publication date.

How to read the dates
Event date
When the permit, filing, approval or other event happened, as the source states it. A month or year is shown when the source gives no day.
Source dated
The date printed on the source document (minutes, order, permit record or company statement). It can be later than the event.
Source accessed
When DataCenterData retrieved the source. Shown on each event page.
Added to Latest updates
When the entry entered this updates log. It is a publishing date, not an event date. An event may already have appeared elsewhere on DataCenterData, for example in the corrections history.