Water & cooling · Microsoft Quincy · WA

EPA documents an operating water-reuse system serving Microsoft's Quincy campus.

A verdict applies only to the wording shown.

Public statement checked

Answer

Verdict on the wording above: Supported as of EPA observations spanning operation from 2021, 2022 connection status and early-2023 context Independent evidence supports the claim as stated, for the stated period. Not permanent; not proof of related claims. How verdicts work →

Who stated it
Said in US EPA case study · government record →
What the evidence establishes
EPA documents operation beginning June 30, 2021 and describes a city-operated treatment and recirculation system serving Microsoft's campus. Applies to the wording and period shown (EPA observations spanning operation from 2021, 2022 connection status and early-2023 context).
Biggest limitation
Current measured withdrawal, consumption and discharge; a reconciled explanation of Microsoft's separate 380-million-gallon estimate; and operating changes after EPA's dated observations.
Checked
12 September 2026 · Next review: Recheck current operating status against a later agency or utility record · History (1) →

Evidence

What the evidence supports

EPA documents operation beginning June 30, 2021 and describes a city-operated treatment and recirculation system serving Microsoft's campus. EPA estimates 138 million gallons per year of potable-water savings, reports about 260 million gallons per year of canal-water makeup and says potable groundwater supplies about 5% of annual makeup. These are different measures and are not additive total consumption or a current meter audit.

Still unknown

Current measured withdrawal, consumption and discharge; a reconciled explanation of Microsoft's separate 380-million-gallon estimate; and operating changes after EPA's dated observations.

Sources

  1. US EPA case study → Archived copy Gov. record

    Exact location Project Highlights; Solution paragraphs 2-4; Make-up Water Sources paragraphs 2 and 4

    What it supports Operation since 2021, reuse-system design, estimated potable-water savings and reported makeup-water figures. Not current total consumption.

    Publication date unavailable · Accessed

Conflicting evidence

Corrections and history

Correction · 12 September 2026 · Software-assisted second check

microsoft-quincy → Cooling + water

Field Cooling + water

From Microsoft Quincy: Supported as delivered; combined measures and a 2021-2022 observation window

To EPA documents an operating reuse system; distinct estimates and dated observations are separated

Why The second review separated estimated savings, canal makeup and potable makeup share and removed an unsupported original-publication year.

Evidence No additional evidence link; see the linked record or claim.

Review details

Scope

Unit
cooling-water reuse; estimated annual potable savings; reported annual canal makeup; annual potable makeup share
Geography
City of Quincy reuse system serving Microsoft's Quincy campus
Period
operation since 2021; connection status reported for 2022 with some early-2023 context
As of
EPA observations spanning operation from 2021, 2022 connection status and early-2023 context
Confidence
high — government case study
Kind
Public statement checked

Chronology

  1. Source retrieved
  2. Sources re-read (software-assisted second check, not an outside audit)
  3. Changed wording recorded
  4. Checked by DataCenterData
  5. Date not established Stated by US EPA case study — statement date not established
  6. Date not established Next review: Recheck current operating status against a later agency or utility record

Data

This claim as JSON →

Reading guide

Compare before you share

Keep the original post where it is. This tool does not ask for or collect the post. Your comparison choices are not saved or sent by the tool.

This is not an automated fact-check of a post we have not seen. Compare the place, period and meaning before applying this finding elsewhere.

Same subject and place?

A different campus, utility territory or institution is a different claim.

Same time and stage?

A plan, approval or estimate is not a measured operating result.

Same quantity and meaning?

Check the unit and boundary. Similar words can describe different measures.

Compare the three details before relying on this answer.

Suggest a correction

Suggest a correction → Claim ID claim:microsoft-quincy:cooling-water and this page are prefilled. Accepted material corrections appear publicly on Changes.