Project development · Permit or regulatory change · Official record
Permit or regulatory change: Gilroy project page records a building permit issued March 19, 2026 (Santa Clara County, CA)
The City of Gilroy's Gilroy Data Center (by Amazon Web Services) project page states that a building permit was issued on March 19, 2026 for project AS 20-23.
What this is. The source (municipal project and permit page, dated August 2026) records this. It does not change the project’s status on DataCenterData; only a separate reviewed record change can.
- Source dated
- Page carries no page-level date; its newest dated timeline entry reads 'August 2026' and an FAQ answer says 'updated on 08/12/2026'. Used as the latest stated content month, not an upload date.
- Development date
- The city's project page states the building permit was issued on March 19, 2026.
- Source read
- Retrieved by DataCenterData; linked, not republished.
- Added to DataCenterData
- When this entry entered the updates log; not a development date.
- Kind of development
- Permit or regulatory change
- Source
- Tier 1 · Official record · City of Gilroy
- Confidence
- HighThe city's own project page states the date and the project number AS 20-23 together; the record is bound by the same page.
- Project status on DataCenterData
- Under construction (as recorded) — unchanged by this entrySource statement only; canonical project status is unchanged.
What the source says
Building permit issued on March 19, 2026.
Where: Project Background and Information block, Project Number AS 20-23
Source: Gilroy Data Center (by Amazon Web Services) - project page, captured 2026-10-05
What the source supports
- Development as stated
- Gilroy project page records a building permit issued March 19, 2026The page names project AS 20-23, 8050 Camino Arroyo and the Gilroy Data Center; the published DCD record gilroy-data-center cites this same page and number.
Claims this source leaves unresolved
- Permit number and scope of the building permit
- Construction progress
- Completion or opening timing
What this does not establish
- Construction start
- Operation
- Completion
Still unknown
- Permit number and scope of the building permit
- Construction progress
- Completion or opening timing
Underlying document
This source is itself the underlying document.
Linked records
- Project (subject): Gilroy Data Center
The page names project AS 20-23, 8050 Camino Arroyo and the Gilroy Data Center; the published DCD record gilroy-data-center cites this same page and number.
Identifiers
Entry ID 586628c0e6407ee834f4af6047fa958a1da15069100122ec4fadc066ec05ff9a. The ID is derived from the entry itself and never changes. A later correction or stronger source is published as a separate, linked entry.