Ohio data center updates

Dated facility and project events and DataCenterData evidence updates for Ohio. Not a complete record of activity in Ohio.

Three different things, kept apart. Facility and project events happened in the world on the date the source gives. Evidence updates are DataCenterData publishing records; they are not events at a facility. Corrections to what DataCenterData published live in the corrections history, the corrections authority.

Facility and project events

  1. Stormwater permit notice filedOfficial recordOhio

    Stormwater permit notice filed on 21 July 2026: QTS Data Centers — Van Wert campus (Van Wert, OH) — state stormwater notice of intent dated 21 July 2026

    QTS Realty Trust Inc. electronically submitted to Ohio EPA a Notice of Intent for new coverage under Construction Site Stormwater General Permit OHC000006 for the 'QTS Data Center' at 8002 Mendon Road, Van Wert (792 acres of proposed land disturbance).

    Event date
    Source dated
    Added to Latest updates
  2. Development plan approvedOfficial recordOhio

    Development plan approved on 15 December 2025: STACK Infrastructure — NAL01B (New Albany, OH) — planning commission minutes dated 15 December 2025

    The New Albany Planning Commission voted 5-0 to approve, with conditions, final development plan FDP-96-2025 (PLFDP20250096) for a new two-story, approximately 330,000 sq ft STACK Infrastructure data center on the east side of Souder Road (parcel 222-005106); applicant EMH&T c/o Nicholas Ovens.

    Event date
    Source dated
    Added to Latest updates
  3. Tax exemption approvedOfficial recordOhio

    Tax exemption approved on 27 October 2025: The Constant Company — Springfield project (Springfield, OH) — tax credit authority minutes dated 27 October 2025

    The Ohio Tax Credit Authority approved, 4-0, a 50%, 10-year data center sales and use tax exemption (2026–2035) for The Constant Company, LLC for a project in the City of Springfield, Clark County, tied to 20 FTE jobs and a $901,311,378 fixed-asset investment commitment.

    Event date
    Source dated
    Added to Latest updates
  4. Construction reportedOfficial recordOhio

    Construction reported on 15 September 2025: Amazon — Scioto Darby campus (Hilliard, OH) — siting board staff report dated 15 September 2025

    The Ohio Power Siting Board staff report on AEP Ohio's Scioto Darby Creek Road fuel-cell project describes the latest Amazon Data Services data center building on the 142-acre Hilliard campus as under construction; it says earlier buildings on the campus have already been constructed.

    Event date
    Source dated
    Added to Latest updates

Evidence updates

No evidence updates for Ohio in this log.

All latest updates →

How to read the dates
Event date
When the permit, filing, approval or other event happened, as the source states it. A month or year is shown when the source gives no day.
Source dated
The date printed on the source document (minutes, order, permit record or company statement). It can be later than the event.
Source accessed
When DataCenterData retrieved the source. Shown on each event page.
Added to Latest updates
When the entry entered this updates log. It is a publishing date, not an event date. An event may already have appeared elsewhere on DataCenterData, for example in the corrections history.