Claims
A verdict applies only to the wording shown.
Company claims are shown as stated; they are not findings.
Construction & status · Digital Crossroad Hammond campus
ContradictedA question DataCenterData examined; no one is quoted.
Checked 11 September 2026 · Next check: no trigger recorded
The expiration of Hammond's CoreWeave agreement means the existing Digital Crossroad data center closed.
What the evidence supports
Hammond says the separate agreement for the proposed 301 Digital Crossroads expansion expired. June 9, 2025 council minutes identify CoreWeave as an existing tenant at 100 Digital Crossroads Drive. The failed expansion and existing DX-1 site are not the same lifecycle event; the notice does not establish closure of the existing facility.
Biggest limitation
These records do not freshly confirm the existing facility’s current operating status.
Construction & status · CoreWeave / Digital Crossroads expansion
OutdatedSaid by the City of Hammond · government record · 10 June 2025 →
Checked 11 September 2026 · Next check: replacement proposal, new NIPSCO docket or new development agreement
450,000 square feet; 180 MW; contemplated 20-year CoreWeave lease
What the evidence supports
Development agreement expired; expansion not delivered.
Biggest limitation
Exact unsatisfied milestones.
Jobs · CoreWeave / Digital Crossroads expansion
OutdatedSaid by the City of Hammond · government record · 9 June 2025 →
Checked 11 September 2026 · Next check: replacement proposal, new NIPSCO docket or new development agreement
35 to 90 jobs paying more than $75,000
What the evidence supports
Not delivered; due status not established.
Biggest limitation
Evidence basis: city-council projection
Community impact · CoreWeave / Digital Crossroads expansion
OutdatedSaid by the City of Hammond · government record · 9 June 2025 →
Checked 21 September 2026 · Next check: replacement proposal, new NIPSCO docket or new development agreement
Up to $4 million per year for 20 years
What the evidence supports
Authorized, then lapsed. The Common Council adopted Resolution 25R-16 approving the development agreement on 9 June 2025 by an 8–0 roll-call vote (one member absent); the 22 December 2025 minutes record an extension. The City announced on 1 July 2026 that the agreement for 301 Digital Crossroads had expired after two extensions because milestones were not satisfied by the 30 June 2026 deadline. No community impact payment is shown as due or received in the saved record, and the notice concerns the proposed 301 expansion, not the separate existing DX-1 facility; it does not freshly confirm current operation.
Biggest limitation
The executed agreement and its payment-trigger clauses, the two extension resolutions, which milestones failed…
Still unknown
The executed agreement and its payment-trigger clauses, the two extension resolutions, which milestones failed and any City payment ledger are not in the saved record; whether any payment was ever due or made is not established.
Community impact · CoreWeave / Digital Crossroads expansion
UnknownSaid by the City of Hammond · government record · 22 December 2025 →
Checked 21 September 2026 · Next check: replacement proposal, new NIPSCO docket or new development agreement
$25 million lump sum discussed
What the evidence supports
Discussed, not contracted, then the agreement lapsed. The 22 December 2025 minutes record the $25 million as announced but 'Right now it's not part of it'. The City announced on 1 July 2026 that the development agreement had expired after two extensions. No payment is shown as due or received in the saved record.
Biggest limitation
Whether the $25 million was ever written into an executed instrument;
Still unknown
Whether the $25 million was ever written into an executed instrument; the executed agreement, the extension resolutions and any City payment ledger are not in the saved record.
Taxes & incentives · CoreWeave / Digital Crossroads expansion
OutdatedSaid by the City of Hammond · government record · 9 June 2025 →
Checked 21 September 2026 · Next check: replacement proposal, new NIPSCO docket or new development agreement
10-year construction abatement and 20-year 100% technology deduction
What the evidence supports
Authorized terms, then lapsed. The 9 June 2025 minutes describe the contemplated 10-year construction abatement and 20-year 100% technology deduction alongside the development agreement adopted by Resolution 25R-16 (8–0, one member absent); the scope and terms of the CoreWeave equipment deduction and the Decennial construction abatement requested at the same meeting were not part of that resolution's vote and are not reviewed. The City announced on 1 July 2026 that the agreement had expired after two extensions. No abatement or deduction is shown as adopted, claimed or received in the saved record.
Biggest limitation
The executed agreement, any separate abatement or deduction instrument (and whether one was ever adopted…
Still unknown
The executed agreement, any separate abatement or deduction instrument (and whether one was ever adopted, claimed or received), the extension resolutions and any payment or abatement ledger are not in the saved record.
Power · CoreWeave / Digital Crossroads expansion
UnknownSaid by the City of Hammond · government record · 9 June 2025 →
Checked 21 September 2026 · Next check: replacement proposal, new NIPSCO docket or new development agreement
Final NIPSCO agreement explicitly described as gating
What the evidence supports
The 9 June 2025 minutes describe a final NIPSCO agreement as gating the expansion. No executed NIPSCO agreement is in the saved record, and the City's 1 July 2026 notice says the development agreement expired after two extensions because milestones were not satisfied by 30 June 2026, without naming which. The NIPSCO agreement remains unknown. The notice concerns the proposed 301 expansion, not the separate existing DX-1 facility; it does not freshly confirm current operation.
Biggest limitation
Whether a NIPSCO agreement was ever executed, and which milestones failed;
Still unknown
Whether a NIPSCO agreement was ever executed, and which milestones failed; the executed development agreement, the extension resolutions and any NIPSCO filing for this expansion are not in the saved record.
Construction & status · CoreWeave / Digital Crossroads expansion
Company claimSaid by Digital Crossroad · company statement in Digital Crossroad Indiana data center page →
Checked 10 September 2026 · Next check: replacement proposal, new NIPSCO docket or new development agreement
DX-1 operating; operator publishes 105,000 square feet and up to 20 MW
What the evidence supports
Digital Crossroad said this. DataCenterData has not found an independent record that confirms or contradicts it; it is shown as the company’s statement, not as a finding either way.
Biggest limitation
Capacity scope is not classified as critical IT load.
History
Correction · 11 September 2026 · DataCenterData review
coreweave-hammond → Expansion design
Field Expansion design
From Previous locator
To pp. 3–11 (resolution 25R-16 introduced p. 3; lease, jobs, tax terms and community impact payment p. 4; NIPSCO contingency p. 6)
Why 2026-09-11: previously 'pp. 3–4'.
Correction · 11 September 2026 · DataCenterData review
coreweave-hammond → Permanent jobs
Field Permanent jobs
From Previous locator
To pp. 3–11 (resolution 25R-16 introduced p. 3; lease, jobs, tax terms and community impact payment p. 4; NIPSCO contingency p. 6)
Why 2026-09-11: previously 'pp. 3–4'.
Correction · 11 September 2026 · DataCenterData review
coreweave-hammond → Community impact payments
Field Community impact payments
From Previous locator
To pp. 3–11 (resolution 25R-16 introduced p. 3; lease, jobs, tax terms and community impact payment p. 4; NIPSCO contingency p. 6)
Why 2026-09-11: previously 'pp. 3–4'.
Correction · 11 September 2026 · DataCenterData review
coreweave-hammond → Community impact payments
Field Community impact payments
From Previous locator
To pp. 1–4 ($80 million community-payment total p. 1; $25 million announced p. 2; 'Right now it's not part of it' p. 4); extension resolution at p. 10
Why 2026-09-11: previously 'pp. 1–2; extension resolution at p. 10'.
Correction · 21 September 2026 · DataCenterData review
coreweave-hammond → Community impact payments
Field Community impact payments
From Not shown due or paid.
To Authorized, then lapsed. The Common Council adopted Resolution 25R-16 approving the development agreement on 9 June 2025 by an 8–0 roll-call vote (one member absent); the 22 December 2025 minutes record an extension. The City announced on 1 July 2026 that the agreement for 301 Digital Crossroads had expired after two extensions because milestones were not satisfied by the 30 June 2026 deadline. No community impact payment is shown as due or received in the saved record, and the notice does not concern the operating DX-1 facility, which is a separate record.
Why City of Hammond notice of 1 July 2026: the development agreement expired after two extensions because milestones were not satisfied by 30 June 2026. The authorized terms (Resolution 25R-16, 8–0, 9 June 2025) are now recorded as lapsed; no payment, incentive or NIPSCO agreement is shown in the saved record. Verdict unchanged.
Evidence https://www.gohammond.com/hammond-announces-expiration-of-data-center-development-agreement/ →
Correction · 11 September 2026 · DataCenterData review
coreweave-hammond → Additional payment
Field Additional payment
From Previous locator
To pp. 1–4 ($80 million community-payment total p. 1; $25 million announced p. 2; 'Right now it's not part of it' p. 4); extension resolution at p. 10
Why 2026-09-11: previously 'pp. 1–2; extension resolution at p. 10'.
Correction · 21 September 2026 · DataCenterData review
coreweave-hammond → Additional payment
Field Additional payment
From Minutes say it was not yet in the agreement.
To Discussed, not contracted, then the agreement lapsed. The 22 December 2025 minutes record the $25 million as announced but 'Right now it's not part of it'. The City announced on 1 July 2026 that the development agreement had expired after two extensions. No payment is shown as due or received in the saved record.
Why City of Hammond notice of 1 July 2026: the development agreement expired after two extensions because milestones were not satisfied by 30 June 2026. The authorized terms (Resolution 25R-16, 8–0, 9 June 2025) are now recorded as lapsed; no payment, incentive or NIPSCO agreement is shown in the saved record. Verdict unchanged.
Evidence https://www.gohammond.com/hammond-announces-expiration-of-data-center-development-agreement/ →
Correction · 11 September 2026 · DataCenterData review
coreweave-hammond → Incentives
Field Incentives
From Previous locator
To pp. 3–11 (resolution 25R-16 introduced p. 3; lease, jobs, tax terms and community impact payment p. 4; NIPSCO contingency p. 6)
Why 2026-09-11: previously 'pp. 3–4'.
Correction · 11 September 2026 · DataCenterData review
coreweave-hammond → Incentives
Field Incentives
From Previous locator
To pp. 1–4 ($80 million community-payment total p. 1; $25 million announced p. 2; 'Right now it's not part of it' p. 4); extension resolution at p. 10
Why 2026-09-11: previously 'pp. 1–2; extension resolution at p. 10'.
Correction · 21 September 2026 · DataCenterData review
coreweave-hammond → Incentives
Field Incentives
From Claimed or received amounts not established.
To Authorized terms, then lapsed. The 9 June 2025 minutes describe the contemplated 10-year construction abatement and 20-year 100% technology deduction alongside the development agreement adopted by Resolution 25R-16 (8–0, one member absent); the scope and terms of the CoreWeave equipment deduction and the Decennial construction abatement requested at the same meeting were not part of that resolution's vote and are not reviewed. The City announced on 1 July 2026 that the agreement had expired after two extensions. No abatement or deduction is shown as adopted, claimed or received in the saved record.
Why City of Hammond notice of 1 July 2026: the development agreement expired after two extensions because milestones were not satisfied by 30 June 2026. The authorized terms (Resolution 25R-16, 8–0, 9 June 2025) are now recorded as lapsed; no payment, incentive or NIPSCO agreement is shown in the saved record. Verdict unchanged.
Evidence https://www.gohammond.com/hammond-announces-expiration-of-data-center-development-agreement/ →
Correction · 11 September 2026 · DataCenterData review
coreweave-hammond → Power agreement
Field Power agreement
From Previous locator
To pp. 3–11 (resolution 25R-16 introduced p. 3; lease, jobs, tax terms and community impact payment p. 4; NIPSCO contingency p. 6)
Why 2026-09-11: previously 'pp. 3–4'.
Correction · 11 September 2026 · DataCenterData review
coreweave-hammond → Power agreement
Field Power agreement
From Previous locator
To pp. 1–4 ($80 million community-payment total p. 1; $25 million announced p. 2; 'Right now it's not part of it' p. 4); extension resolution at p. 10
Why 2026-09-11: previously 'pp. 1–2; extension resolution at p. 10'.
Correction · 21 September 2026 · DataCenterData review
coreweave-hammond → Power agreement
Field Power agreement
From No executed agreement located; exact failed milestones undisclosed.
To The 9 June 2025 minutes describe a final NIPSCO agreement as gating the expansion. No executed NIPSCO agreement is in the saved record, and the City's 1 July 2026 notice says the development agreement expired after two extensions because milestones were not satisfied by 30 June 2026, without naming which. The NIPSCO agreement remains unknown. The notice does not concern the operating DX-1 facility, which is a separate record.
Why City of Hammond notice of 1 July 2026: the development agreement expired after two extensions because milestones were not satisfied by 30 June 2026. The authorized terms (Resolution 25R-16, 8–0, 9 June 2025) are now recorded as lapsed; no payment, incentive or NIPSCO agreement is shown in the saved record. Verdict unchanged.
Evidence https://www.gohammond.com/hammond-announces-expiration-of-data-center-development-agreement/ →
Dated events
Real-world events recorded for this record, newest event date first. Each event page shows its source, dates and what it does not establish.
Agreement expiredOfficial recordIndiana
Agreement expired on 30 June 2026: CoreWeave / Digital Crossroads expansion (Hammond, IN) — city notice dated 1 July 2026
- Event date
- Source dated
- Added to Latest updates
Development agreement approvedOfficial recordIndiana
Development agreement approved on 9 June 2025: CoreWeave / Digital Crossroads expansion (Hammond, IN) — city council minutes dated 9 June 2025
- Event date
- Source dated
- Added to Latest updates
Timeline
Council approves the development agreement
Minutes: Decennial constructs; CoreWeave locates in a new 450,000 ft² building at 301 Digital Crossroads under a contemplated 20-year lease; CoreWeave already a tenant at 100 Digital Crossroads. Community impact payment described as up to $4 million/year for 20 years if abatements are agreed. Timeline begins once Decennial and NIPSCO sign a power agreement.
First extension discussed and approved
Minutes/resolution: utility negotiations continue; NIPSCO had submitted a proposed power agreement to Decennial. A separate $25 million lump-sum commitment is discussed as being finalized during a short extension—described as not yet fully documented in the agreement at that meeting.
Extended deadline passes
After two extensions, required obligations and milestones remain unsatisfied. The city does not name the exact failed milestones.
City announces expiration
Hammond says it will grant no further extension. The notice concerns the proposed project at 301 Digital Crossroads and does not address DX-1.
Source evidence
- Hammond Common Council minutes — 9 Jun 2025 →Primary municipal PDF · proposal, lease, jobs, tax terms, community payment and power contingency
- Hammond Common Council minutes — 22 Dec 2025 →Primary municipal PDF · extension, power negotiations and noncontractual $25M discussion
- City of Hammond — development agreement approval notice →Primary municipal announcement · contingent on NIPSCO power agreement and lease execution
- City of Hammond — expiration notice →Primary municipal outcome record · 1 Jul 2026
- Digital Crossroad — existing DX-1 facility →Operator source · current facility status
- Machine-readable claim ledger →DataCenterData normalization · version 0.2
- Classification methodology →Why an unsatisfied precondition is not automatically a missed payment
Review date follows the coreweave-hammond record check token; it is not advanced merely because this ledger was clarified against the captured minutes and notices.
Recorded information
What this page records, grouped by topic, with the source's units and qualifications. Company-reported values stay labeled as company-reported. Related listings are shown separately.
Reviewed record coreweave-hammond
Project · CoreWeave.
The expired agreement concerns the proposed 301 project. June 2025 council minutes describe existing tenancy at 100; these records do not freshly confirm current operation.
Location and precision
- Hammond, IN · Lake County (Place centre, not the site)
Roles
- Owner: Decennial Group / Digital Crossroads
- Developer: Decennial Group / Digital Crossroads
- Operator: CoreWeave
Lifecycle
- Recorded status: expired
Hammond says the separate development agreement expired after required milestones were not satisfied by the June 30, 2026 deadline. June 9, 2025 council minutes identify existing CoreWeave tenancy at 100 Digital Crossroads Drive, separate from the proposed 301 project. These records do not freshly confirm current operation.
Power capacity
- Power detail: 180 MW
Recorded with its stated kind; not a measured load and not comparable across records.
- Capacity — Not yet recorded here.
Cooling, water, PUE and WUE
- Cooling and water: Not established in the reviewed city release.
Permits, incentives, jobs and proceedings
- Projected permanent jobs: 35 to 90 positions paying more than $75,000
not delivered; due status not established because the expansion agreement expired
Announced job figures are not observed headcount. Different scopes stay separate.
- Announced investment: multibillion-dollar
Announced figure, not spending.
- Incentives and commitments: The expired agreement referenced Community Impact Payments. No payment is treated as delivered without evidence that it came due and was paid.
Sources, dates, limitations and corrections
- Sources: 4 cited sources, listed on this page
- Evidence still needed: independently supported demand figure
Not yet recorded here: Area, acreage and buildings · Connectivity · Services · Certifications and design ratings · Rack density · Availability · Specification links and contact.
Next research question
- Archive and extract the expired agreement, determine which milestones failed, and monitor any replacement development proposal separately from the operating DX-1 facility.
Update this profile with a public source. The request includes topics needing more information; this does not mean the facility lacks them. Corrections and additions are reviewed before publication.