Memphis Ordinance No. 5982 would declare a temporary moratorium on the acceptance, processing, approval and issuance of zoning, land use, building and other associated infrastructure permits for data center developments within the City of Memphis. The official 6 October 2026 City Council agenda lists it for third and final reading, held from 15 September. The agenda records no adoption or vote.

Geographic scope
City of Memphis, Tennessee
Jurisdiction
Local
Authority type
Local government
Issuing authority
Memphis City Council

Dates

Adopted
No adoption day is recorded
Effective
Not enacted
Scheduled expiration
No expiration date recorded
Ended
Not recorded as ended
Completion condition
None stated
Source document
15 September 2026
Last checked
6 October 2026
About this date

This record was last checked before the tracker date, 30 October 2026. An earlier check date does not by itself mean the record's status has changed.

Summary

Memphis Ordinance No. 5982 would temporarily stop the city from accepting, processing, approving or issuing zoning, land use, building and related infrastructure permits for data center developments. The official City Council agenda for 6 October 2026 lists it for third and final reading, held from 15 September. No adopted text, vote or minutes showing final passage were found, so it is recorded as a proposal and applies only to the City of Memphis if adopted.

What this does not establish

  • Only the official agenda listing was relied on; the minutes of the 15 September 2026 meeting were not posted on the council agenda page when checked, so the outcome of the third reading is not recorded.
  • Earlier draft PDFs of a moratorium ordinance on memphistn.gov are unsigned drafts and were not used for the terms.
  • The unsigned text in the 15 September 2026 agenda documents would run the moratorium until the earlier of twelve months after its effective date, adoption of comprehensive data center zoning regulations, or repeal or amendment; the text as finally voted may differ.
  • The council agenda headed October 6, 2026 lists Ordinance No. 5982 for third and final reading and marks it held from the September 15, 2026 meeting. The agenda records no vote. That meeting had not occurred when the agenda was captured on October 5, 2026. The agendas page captured the same day links September 15 agendas and does not link September 15 minutes.
  • The official agenda and meeting index were re-read on 6 October 2026. An agenda records a scheduled reading, not its outcome. No signed enacted text or minutes establishing a vote were found in the reviewed documents; proposed status and no effective date are retained.

Unresolved questions

  • Whether the Council adopts, amends, defers or rejects Ordinance No. 5982 on third reading.

Relationships

Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.

  • No related action is recorded.

Sources

Primary source: Memphis City Council page on memphistn.gov

Back to the policy tracker · Tennessee policy module