Energization: dated data center events
Utility service energized, as stated by an official record. Energization is not operation.
Three different things, kept apart. Facility and project events happened in the world on the date the source gives. Evidence updates are DataCenterData publishing records; they are not events at a facility. Corrections to what DataCenterData published live in the corrections history, the corrections authority.
Events, newest event date first
EnergizationOfficial recordIndiana
Energization in November 2024: Google — Fort Wayne (Fort Wayne, IN) — utility commission order dated 29 April 2026
In its April 29, 2026 final order in Cause No. 46276, the Indiana Utility Regulatory Commission records that Indiana Michigan Power energized Google's Fort Wayne site in November 2024.
- Event date
- Source dated
- Added to Latest updates
Record: Google — Fort WayneSource: Order of the Commission, Cause No. 46276Archived copy
How to read the dates
- Event date
- When the permit, filing, approval or other event happened, as the source states it. A month or year is shown when the source gives no day.
- Source dated
- The date printed on the source document (minutes, order, permit record or company statement). It can be later than the event.
- Source accessed
- When DataCenterData retrieved the source. Shown on each event page.
- Added to Latest updates
- When the entry entered this updates log. It is a publishing date, not an event date. An event may already have appeared elsewhere on DataCenterData, for example in the corrections history.