Latest updates · 4 dated events · Newest log entry: 21 September 2026

Construction: dated data center events

Groundbreaking ceremonies, dated construction starts, and official records describing a project as under construction on a stated date. A ceremony is not proof that site work began.

About these streams

Three different things, kept apart. Facility and project events happened in the world on the date the source gives. Evidence updates are DataCenterData publishing records; they are not events at a facility. Corrections to what DataCenterData published live in the corrections history, the corrections authority.

Find planning and project milestones

Clear filters

Month or year dates match when their possible range overlaps your dates. These are reviewed historical milestones; check the project timeline and source for later changes.

Events, newest event date first

  1. Construction reportedOfficial recordVirginia

    Construction reported in July 2026: Google Bermuda Hundred Data Center Campus (VA) — county project status table dated July 2026

    Chesterfield County's 'Data Center Project Status as of July 2026' table lists Peanut LLC at 2100 Bermuda Hundred Road as 'Under construction; three buildings'.

    Organization named in the record
    Chesterfield County
    Not established by this event
    construction start date; completion; energization or operation.
    Event date
    Source dated
    Added to Latest updates
  2. Construction reportedOfficial recordMissouri

    Construction reported on 21 May 2026: Rifle Range Road Data Center Project (MO) — county commission update dated 21 May 2026

    The Webster County Commission's May 21, 2026 update describes a data center project as currently under construction on Rifle Range Road in rural Webster County, north and east of Marshfield.

    Organization named in the record
    Webster County Commission
    Not established by this event
    Construction start date; Completion, energization or operation.
    Event date
    Source dated
    Added to Latest updates
  3. Construction reportedOfficial recordUtah

    Construction reported on 17 April 2026: QTS Eagle Mountain Campus (Eagle Mountain, UT) — city press release dated 20 April 2026

    Eagle Mountain City reported that on April 17, 2026 crews placed the final beam on the first QTS data center building in Eagle Mountain, and that construction will continue on interior systems and the remaining buildings.

    Organization named in the record
    Eagle Mountain City
    Not established by this event
    Building completion (structural topping-out only); Energization or operation.
    Event date
    Source dated
    Added to Latest updates
  4. Construction reportedOfficial recordOhio

    Construction reported on 15 September 2025: Amazon — Scioto Darby campus (Hilliard, OH) — siting board staff report dated 15 September 2025

    The Ohio Power Siting Board staff report on AEP Ohio's Scioto Darby Creek Road fuel-cell project describes the latest Amazon Data Services data center building on the 142-acre Hilliard campus as under construction; it says earlier buildings on the campus have already been constructed.

    Organization named in the record
    Ohio Power Siting Board staff
    Not established by this event
    Completion or operation of the latest building; Original operating date of the campus.
    Event date
    Source dated
    Added to Latest updates

All latest updates →

How to read the dates
Event date
When the permit, filing, approval or other event happened, as the source states it. A month or year is shown when the source gives no day.
Source dated
The date printed on the source document (minutes, order, permit record or company statement). It can be later than the event.
Source accessed
When DataCenterData retrieved the source. Shown on each event page.
Added to Latest updates
When the entry entered this updates log. It is a publishing date, not an event date. An event may already have appeared elsewhere on DataCenterData, for example in the corrections history.