Facility and project events
Air permit application receivedOfficial recordPennsylvania
Air permit application received in April 2026: Amazon Falls Township Data Center Project (Falls Township, PA) — state environmental agency release dated 13 July 2026
The Pennsylvania DEP states that in April 2026 Amazon submitted an air quality plan approval application (Minor New Source Plan Approval Application No. 09-0261A) for 280 natural gas-fired generator engines and three diesel-fired emergency generator engines for the Amazon data center at the Keystone Trade Center in Falls Township.
- Event date
- Source dated
- Added to Latest updates
Record: Amazon Falls Township Data Center ProjectSource: DEP to Host Community Meeting on Proposed Air Quality Permit for Amazon Data Center in Falls Township, Bucks CountyArchived copy
Evidence updates
Evidence updateDataCenterData publicationPennsylvania
Evidence record published: Amazon Falls Township Data Center Project (Falls Township, PA)
- Published on DataCenterData
How to read the dates
- Event date
- When the permit, filing, approval or other event happened, as the source states it. A month or year is shown when the source gives no day.
- Source dated
- The date printed on the source document (minutes, order, permit record or company statement). It can be later than the event.
- Source accessed
- When DataCenterData retrieved the source. Shown on each event page.
- Added to Latest updates
- When the entry entered this updates log. It is a publishing date, not an event date. An event may already have appeared elsewhere on DataCenterData, for example in the corrections history.