Latest updates · 12 dated events · Newest log entry: 21 September 2026
Approvals: dated data center events
Decisions by an official body: rezonings, plans, plats, special uses, agreements, exemptions and contracts. An approval is not construction.
About these streams
Three different things, kept apart. Facility and project events happened in the world on the date the source gives. Evidence updates are DataCenterData publishing records; they are not events at a facility. Corrections to what DataCenterData published live in the corrections history, the corrections authority.
No reviewed milestones match these filters. This does not establish that no activity occurred.
Events, newest event date first
Special use approvedOfficial recordColorado
Special use approved on 9 September 2026: Global AI (Colorado), LLC Data Center Project (CO) — county press release dated 10 September 2026
The Weld County Board of County Commissioners voted 5-0 on September 9, 2026 to approve Use by Special Review permit USR26-0019 for Global AI (Colorado), LLC to operate a data center in an existing industrial facility near Windsor.
- Organization named in the record
- Weld County Board of County Commissioners
- Not established by this event
- Issuance of building or construction permits; Construction start; Completion, energization or operation; Approval of any future phase or expansion.
- Event date
- Source dated
- Added to Latest updates
Record: Global AI (Colorado), LLC Data Center ProjectProject timeline: recorded eventsSource: Weld County Commissioners approve Global AI data center permitArchived copy
Utility contract approvedOfficial recordIndiana
Utility contract approved on 17 June 2026: Amazon / NIPSCO northern Indiana service program (IN) — utility commission order dated 17 June 2026
The Indiana Utility Regulatory Commission approved the settlement, NIPSCO's 'Data Center Customer #1' special contract with Amazon Data Services, Inc., the NIPSCO–NIPSCO Generation power purchase agreement and related alternative regulatory plans.
- Organization named in the record
- Indiana Utility Regulatory Commission
- Not established by this event
- Service commencement; Construction of the GenCo generation or transmission assets; Any Amazon facility's construction or operation.
- Event date
- Source dated
- Added to Latest updates
Record: Amazon / NIPSCO northern Indiana service programProject timeline: recorded eventsSource: Order of the Commission, Cause No. 46322 (NIPSCO and NIPSCO Generation – Data Center Customer #1 Special Contract)Archived copy
Rezoning approvedOfficial recordAlabama
Rezoning approved on 21 April 2026: AL Bessemer Land Data Center Project (Bessemer, AL) — city ordinance dated 21 April 2026
The Bessemer City Council adopted, and the Mayor approved, Ordinance No. 3698 on April 21, 2026, rezoning the property in AL Bessemer Land, LLC's application from A-1 vacant Agricultural to I-1 Light Industrial for construction and operation of a multi-phased data center.
- Organization named in the record
- Bessemer City Council
- Not established by this event
- construction; building permits; operation.
- Event date
- Source dated
- Added to Latest updates
Record: AL Bessemer Land Data Center ProjectProject timeline: recorded eventsSource: City of Bessemer Ordinance No. 3698 (AL Bessemer Land LLC Rezoning Ordinance)Archived copy
Final plat approvedOfficial recordLouisiana
Final plat approved on 18 March 2026: Technology Park Data Center Project (LA) — parish government release dated 20 March 2026
The Bossier Parish Police Jury, at its March 18, 2026 regular agenda meeting, unanimously approved the Benton Metropolitan Planning Commission's final plat recommendation for the Technology Park supporting the new Amazon data center.
- Organization named in the record
- Bossier Parish Police Jury
- Not established by this event
- construction; building permits; operation.
- Event date
- Source dated
- Added to Latest updates
Record: Technology Park Data Center ProjectProject timeline: recorded eventsSource: Police Jury Awards Major Infrastructure Contracts, Approves Final Plat for Amazon Data Center Technology ParkArchived copy
Variance approvedOfficial recordIndiana
Variance approved on 18 March 2026: Sabey — Decatur Technology Park (Indianapolis, IN) — development commission hearing results dated 18 March 2026
The Indianapolis Metropolitan Development Commission approved, subject to commitments, petitions 2025-CAP-856 (modification of commitments) and 2025-CVR-856 (2nd Amended, variances for a data center technology park) filed by Sabey Data Center Properties, LLC for Kentucky Avenue/Camby Road parcels.
- Organization named in the record
- Indianapolis Metropolitan Development Commission
- Not established by this event
- Construction start; Final approval certification; Operation.
- Event date
- Source dated
- Added to Latest updates
Record: Sabey — Decatur Technology ParkSource: Metropolitan Development Commission Hearing (March 18, 2026) – MDC Hearing ResultsArchived copy
Rezoning approvedOfficial recordSouth Dakota
Rezoning approved on 6 January 2026: Gemini Addition (Sioux Falls, SD) — city council minutes dated 6 January 2026
The Sioux Falls City Council on January 6, 2026 adopted Ordinance No. 5-26 rezoning land south of E. Rice St. and east of Veterans Pkwy (petition 022049-2025) and Resolution No. 4-26 approving the Gemini Addition preliminary plan, conditioned on any data center being limited to domestic water usage; applicant Gemini Data Center SD, LLC.
- Organization named in the record
- Sioux Falls City Council
- Not established by this event
- Final plat or site-plan approval; Building permit or construction start; Operation.
- Event date
- Source dated
- Added to Latest updates
Record: Gemini AdditionProject timeline: recorded eventsSource: Minutes — Regular City Council Meeting, January 6, 2026Archived copy
Development plan approvedOfficial recordOhio
Development plan approved on 15 December 2025: STACK Infrastructure — NAL01B (New Albany, OH) — planning commission minutes dated 15 December 2025
The New Albany Planning Commission voted 5-0 to approve, with conditions, final development plan FDP-96-2025 (PLFDP20250096) for a new two-story, approximately 330,000 sq ft STACK Infrastructure data center on the east side of Souder Road (parcel 222-005106); applicant EMH&T c/o Nicholas Ovens.
- Organization named in the record
- New Albany Planning Commission
- Not established by this event
- Construction start; Operation.
- Event date
- Source dated
- Added to Latest updates
Record: STACK Infrastructure — NAL01BSource: New Albany Planning Commission, Monday, December 15, 2025 Meeting Minutes – Approved (with appendix)Archived copy
Tax exemption approvedOfficial recordOhio
Tax exemption approved on 27 October 2025: The Constant Company — Springfield project (Springfield, OH) — tax credit authority minutes dated 27 October 2025
The Ohio Tax Credit Authority approved, 4-0, a 50%, 10-year data center sales and use tax exemption (2026–2035) for The Constant Company, LLC for a project in the City of Springfield, Clark County, tied to 20 FTE jobs and a $901,311,378 fixed-asset investment commitment.
- Organization named in the record
- Ohio Tax Credit Authority
- Not established by this event
- Construction start; Operation; Delivered jobs or investment.
- Event date
- Source dated
- Added to Latest updates
Record: The Constant Company — Springfield projectProject timeline: recorded eventsSource: Ohio Tax Credit Authority Meeting Minutes, Meeting Date October 27, 2025Archived copy
Development agreement approvedOfficial recordIndiana
Development agreement approved on 9 June 2025: CoreWeave / Digital Crossroads expansion (Hammond, IN) — city council minutes dated 9 June 2025
The Hammond Common Council adopted Resolution 25R-16 approving the development agreement among the City of Hammond, the Hammond Redevelopment Commission, 301 Digital Crossroads, LLC, Decennial Group, LLC and CoreWeave, Inc., by an 8-0 roll-call vote.
- Organization named in the record
- Hammond Common Council
- Not established by this event
- Construction start; A NIPSCO power agreement; Any expansion building's existence or operation.
- Event date
- Source dated
- Added to Latest updates
Record: CoreWeave / Digital Crossroads expansionProject timeline: recorded eventsSource: Minutes of the Common Council, June 09, 2025Archived copy
Rezoning approvedOfficial recordVirginia
Rezoning approved on 28 May 2025: Google Watkins Centre Data Center Project (VA) — county board minutes dated 28 May 2025
The Chesterfield County Board of Supervisors approved rezoning Case 25SN1040 (Watkins Centre South; 349.97 acres (8 parcels) known as 750 Watkins Centre Parkway et al.) from Agricultural (A) and General Industrial (I-2) to General Industrial (I-2), subject to conditions, by a 5-0 vote on May 28, 2025.
- Organization named in the record
- Chesterfield County Board of Supervisors
- Not established by this event
- construction; site plan approval; operation.
- Event date
- Source dated
- Added to Latest updates
Record: Google Watkins Centre Data Center ProjectProject timeline: recorded eventsSource: Chesterfield County Board of Supervisors Minutes — May 28, 2025Archived copy
Rezoning approvedOfficial recordVirginia
Rezoning approved on 28 May 2025: Google Upper Magnolia Green Data Center Project (VA) — county board minutes dated 28 May 2025
The Chesterfield County Board of Supervisors approved rezoning Case 25SN1038 (Upper Magnolia Green West Tract A & Tract B; 979.23 acres fronting Moseley Road and Mount Hermon Road) from Agricultural (A) and General Industrial (I-2) to General Industrial (I-2), subject to conditions, by a 5-0 vote on May 28, 2025.
- Organization named in the record
- Chesterfield County Board of Supervisors
- Not established by this event
- construction; site plan approval; operation.
- Event date
- Source dated
- Added to Latest updates
Record: Google Upper Magnolia Green Data Center ProjectProject timeline: recorded eventsSource: Chesterfield County Board of Supervisors Minutes — May 28, 2025Archived copy
Power plant exemption grantedOfficial recordCalifornia
Power plant exemption granted on 9 May 2025: STACK SVY03A Data Center Campus (Hayward, CA) — state energy commission order dated 9 May 2025
The California Energy Commission voted 5-0 at its May 8, 2025 business meeting to adopt the Mitigated Negative Declaration and grant a Small Power Plant Exemption for the STACK SVY03A Data Center Campus at 26062 Eden Landing Road, Hayward (docket 23-SPPE-01).
- Organization named in the record
- California Energy Commission
- Not established by this event
- City of Hayward entitlement (separate Planning Commission action); Construction start; Completion, energization or operation.
- Event date
- Source dated
- Added to Latest updates
Record: STACK SVY03A Data Center CampusProject timeline: recorded eventsSource: Order Adopting the Mitigated Negative Declaration and Granting the Small Power Plant Exemption, Order No. 25-0508-11 (TN 263075)Archived copy
How to read the dates
- Event date
- When the permit, filing, approval or other event happened, as the source states it. A month or year is shown when the source gives no day.
- Source dated
- The date printed on the source document (minutes, order, permit record or company statement). It can be later than the event.
- Source accessed
- When DataCenterData retrieved the source. Shown on each event page.
- Added to Latest updates
- When the entry entered this updates log. It is a publishing date, not an event date. An event may already have appeared elsewhere on DataCenterData, for example in the corrections history.