Texas index · last changed 1 October 2026

Texas data centers: what the public record shows.

Selected source-linked records are published below. This is not a complete inventory of Texas data centers.

13 sourced policy records for Texas ↓Facility register: 225 records · by county →4 published DataCenterData records · evidence status shown per row113 licensed directory leads · not independently verifiedThese counts overlap and are not added together

Explore Texas

Map, listings and checked facts.

Start with 113 licensed source leads, then inspect the separate public-evidence layer below. Licensed rows are not independently verified and are not a statewide census.

Texas map

Reported locations in Texas

113 licensed rows · 80 source localities · 6 map targets

Open interactive map
Source-reported points; some are approximate. Not parcel boundaries. Exact Approximate or representative Bounded nearby groupA number on a marker is the count of licensed rows it holds.Licensed layer only (Compute Atlas, source data through 14 October 2026). The interactive map lists 251 data-center source listings here across licensed, operator and DataCenterData layers (183 with a map point); 267 with government registry records. Source listings are not distinct sites.5 symbols are offset slightly for readability; thin connectors retain their projected anchors. Open the interactive map for source coordinates.
Browse 6 mapped areas as links
Map sources and method

The state outline is adapted from the U.S. Census Bureau 2025 cartographic boundary file. Facility coordinates are adapted from Compute Atlas by Edward Kubiak, edition 1.34.1, under CC BY 4.0. Outline and markers use one geographic projection before any explicitly disclosed readability offset. Exact singleton source anchors are never moved. A one-kilometre boundary tolerance prevents the simplified 1:20,000,000 outline from hiding legitimate border-area source points; farther conflicts are disclosed, not clamped. DataCenterData groups source-reported city coordinates only within a bounded map radius; the outline does not validate a facility record. Some locations in this layer are reported by the provider as derived from OpenStreetMap (© OpenStreetMap contributors, ODbL, https://www.openstreetmap.org/copyright) and Epoch AI (CC BY 4.0).

113 licensed rows63 reported city labels62 eligible organization labels

Browse all 113 rows below. Licensed rows are not independently verified and remain separate from the checked public-evidence layer.

  1. source-reported under constructionReported planned 540 MWSource updated 6 July 2026approximate location
  2. source-reported operationalReported operational 60 MWSource updated 1 September 2026exact location (provider label)

Separate layer

Also listed by operators

Sites that operators list on their own websites and that are not rows in the licensed directory above. They are kept apart and never added to the licensed rows.

113 operator-listed sites (mixed units; not added to licensed rows) in Texas →

47 of these sites have no supported coordinate. The map does not invent a pin or a metro placement for them.

Texas evidence at a glance

A few checked sites

Selected public evidence, not a statewide census. Each row shows whether it is independently source-linked, attributed, or unresolved; licensed leads remain separate.

Published project / campus
3
Published facility / building
1
Attributed or unresolved rows
0
Licensed directory leads
113 not independently verified
Capacity boundary stated
0 of 4 published DataCenterData rows
Review timing
Audit through 12 September 2026 · next 12 October 2026
Known coverage gap

The JETI current-agreements page was never opened, so the exclusion of data centers from that programme is unconfirmed.

Browse all 113 Texas licensed leads → · Why these counts differ →

Projects and Operating facilities

3 project records · 1 operating facility record. Names are as they appear on each record page.

Projects and Operating facilities published for Texas
Record / rolesStatusCapacity / scalePrimary evidence
Goodnight Data Center proposedproject UnknownNo independently supported figure TCEQ Plain Language Summary — permit 182880 →Gov. record
Nexus Data Center Hubbard proposedproject UnknownNo independently supported figure TCEQ Plain Language Summary — permits 183046, GHGPSDTX269 and PSDTX1700 →Gov. record
ADC Plano operatingoperating facility UnknownNo independently supported figure TCEQ Plain Language Summary — renewal permit 131651 →Gov. record
Microsoft Corporation (SAT 89-90)Operator: Microsoft Corporation · Owner: Microsoft Corporation unknownproject · Texas Comptroller qualifying large-project list retrieved 19 September 2026; TDLR TABS project TABS2025012765 retrieved the same day UnknownNo independently supported figureNo selected Comptroller or TDLR record states critical-IT or other MW. TDLR estimated cost and 489,400 square feet gross building area are not IT load and are not published as capacity. Registered Qualifying Large Data Center Projects — Microsoft Corporation (SAT 89-90) →Gov. record

Where the records were checked

Statewide audit pending

A few checked sites

This is not a list of every data center in the state, and the number here is not a count of them. There are almost certainly more.

Statewide coverage is not complete. The records below are sourced; a full statewide count has not been published.

State research audit window ended 12 September 2026. Individual records and claims below show their own evidence dates and may be newer.

Coverage review was due 12 October 2026; no later coverage review is recorded as of 3 November 2026.

3 independently source-linked project/campus records; 1 independently source-linked facility/building record; 0 attributed or unresolved rows. These counts use different units and must not be added together.

Source families checked, selected records and remaining gaps

These notes name selected records, say which kinds of public evidence were checked and show what remains missing. They do not add anything to the published counts.

Local evidence by place

Licensed and operator listings, reviewed records, answers and local policy for each place. Listings overlap and are not added; a place without a line here has no published local evidence.

No local evidence answer, reviewed record or local policy record is published for Abernathy, Abilene, Allen, Austin, Childress, Dallas, Denton, Garland, Irving, Red Oak, San Antonio. Their listings above are source listings to investigate. No statewide evidence answer is published for Texas either; statewide rules are under Policy tracker below.

6 Texas answers are not tied to a published record, so they are not placed here: Texas answers.

Policy tracker

Texas policy records

13 sourced records are associated with this state context. They are grouped below as current, pending and nonbinding, and history, and each card shows its relevant date. These are not facility counts and do not cover every locality.

Texas: Temporary approval and permit pauses pending reviews—not a permanent ban on existing facilities.

How the Texas actions fit together

These Texas records are related instruments. None is recorded as superseding another. Together, the approval and permit directives are a temporary approval and permit pause pending an audit. This is not a permanent ban on existing facilities. The 3 August 2026 letter tells the Public Utility Commission and ERCOT to audit data centers advancing through ERCOT interconnection before any additional data centers are approved to move forward. It states no end date. ERCOT's 3 August 2026 market notice postponed Batch Zero classification of large loads past 7 August 2026. ERCOT's 20 August 2026 presentation says energization approvals are paused for data centers and virtual-currency mining facilities of 75 MW or greater until Batch Zero eligibility verification is complete. The 14 September 2026 board update says that pause continues until the verification and audit and the community-impact review are complete. Those materials give 10 December 2026 as a report-filing goal, not as a legal expiration. That energization pause does not, on ERCOT's description, apply to non-data-center large loads or to medium loads. The 21 September 2026 letter tells TCEQ to halt permits sought by data centers until ERCOT completes its review, and it says no other state agency should move regulatory approvals forward until the requested information is acquired. 19 October 2026 is a compliance-update date, not an expiration. The same letter says the governor will seek legislation to eliminate data-center financial incentives. That legislation is not recorded as enacted. The Comptroller was still describing the sales-tax exemption program on 22 September 2026. The Public Utility Commission's rule 16 TAC section 25.194, adopted on 18 September 2026 with an effective date of 8 October 2026, implements Senate Bill 6 for large loads generally; it is a separate instrument and does not end these pauses. ERCOT's 14 September 2026 request for information (M-B091426-01) sets a 12 October 2026 response date; that is a response deadline, not an expiration. TCEQ's 19 October 2026 letter says the agency has paused issuance of permits for infrastructure directly supporting data centers and is screening pending applications. The STEERS page marked modified on 22 October 2026 says that filing system is temporarily down for that review. Neither document ends the pause or lists individual permits. 19 October 2026 remains a compliance-update date, not an expiration.

Current 12 records

Recorded as in effect on the dataset date. This does not mean every project in a represented state is restricted or approved.

Statewide permit or approval pause

TCEQ data-center permit pause

In effect · Texas · State

Effective: 21 September 2026

Issuing authority: Governor of Texas

On 21 September 2026, Governor Greg Abbott directed the Texas Commission on Environmental Quality to halt permits sought by data centers and to pause issuance of permits related to data center projects until ERCOT completes its review.

Read the sourced record · Primary source

Reporting or resource-use requirement

Water-use reporting enforcement directive

In effect · Texas · State

Effective: 14 September 2026

Issuing authority: Governor of Texas

On 14 September 2026, Governor Greg Abbott directed the Texas Water Development Board to enforce existing water-use survey obligations against major water users, including data centers, and to partner with ERCOT so the data-center audit collects water-use information.

Read the sourced record · Primary source

Grid-interconnection pause

ERCOT large-load interconnection pause

In effect · ERCOT region in Texas · Regional grid

Source document: 20 August 2026

Issuing authority: Electric Reliability Council of Texas

ERCOT's 20 August 2026 presentation says energization approvals are paused for data centers and virtual-currency mining facilities of 75 MW or greater until Batch Zero eligibility verification is complete.

Read the sourced record · Primary source

Enacted legislation or regulation

Order letting ERCOT delay Batch Zero classification during the data-center audit

In effect · ERCOT power region, Texas · State

Effective: 20 August 2026

Issuing authority: Public Utility Commission of Texas

On 20 August 2026 the Public Utility Commission of Texas granted ERCOT good-cause exceptions in Project No. 59142 so that ERCOT could delay classifying Large Loads for Batch Zero, include certain eligible but unclassified loads in the August and November 2026 stability assessments, and extend its review of dynamic data.

Read the sourced record · Primary source

Reporting or resource-use requirement · Fort Worth only (local rule)

Fort Worth: water and wastewater criteria for data centers

In effect · Fort Worth, Texas · Local

Effective: 11 August 2026

Issuing authority: City of Fort Worth

Fort Worth's revised water and wastewater design criteria, effective 11 August 2026, require data center developments to obtain a Non-Significant Industrial User permit for discharges to the city wastewater system.

Read the sourced record · Primary source

Statewide permit or approval pause

ERCOT approval pause pending audit

In effect · Texas · State

Effective: 3 August 2026

Issuing authority: Governor of Texas

On 3 August 2026, Governor Greg Abbott directed the Public Utility Commission of Texas and ERCOT to audit data centers advancing through ERCOT interconnection before any additional data centers are approved to move forward, and to deny grid connection to a project that fails that process.

Read the sourced record · Primary source

Enacted legislation or regulation

ERCOT ride-through requirements for large computational loads (NOGRR 282)

In effect · ERCOT region, Texas · Regional grid

Effective: 1 August 2026

Issuing authority: Electric Reliability Council of Texas

ERCOT Nodal Operating Guide Revision Request 282 sets frequency and voltage ride-through requirements for Large Computational Loads, the load type defined in NPRR 1308 to include data centers and cryptocurrency mining facilities.

Read the sourced record · Primary source

Enacted legislation or regulation

ERCOT definition of Large Computational Load (NPRR 1308)

In effect · ERCOT region, Texas · Regional grid

Effective: 1 August 2026

Issuing authority: Electric Reliability Council of Texas

ERCOT Nodal Protocol Revision Request 1308 defines a Large Computational Load as a Large Load (75 MW or more at a site) in which at least half of the demand is power-electronic computational load, such as data centers and cryptocurrency mining facilities.

Read the sourced record · Primary source

Reporting or resource-use requirement

Directive on data-center infrastructure costs

In effect · Texas · State

Effective: 10 June 2026

Issuing authority: Governor of Texas

On 10 June 2026 Governor Greg Abbott directed the Public Utility Commission of Texas to take action to require data centers to pay for all of their electric infrastructure costs so that residential ratepayers are not burdened, and directed the commission and ERCOT to review their authorities and send a joint memorandum by 17 July 2026.

Read the sourced record · Primary source

Incentive or explicitly supportive policy

Data center sales-tax exemption

In effect · Texas · State

Last checked: 23 September 2026

Issuing authority: Texas Comptroller of Public Accounts

As of 22 September 2026, the Texas Comptroller's public program page still describes certification and a temporary state sales-tax exemption for qualifying data centers and qualifying large data center projects.

Read the sourced record · Primary source

History 1 record

Expired, repealed, vetoed, failed, blocked, superseded and completed measures remain visible without being presented as current.

Reporting or resource-use requirement

One-time energy and water use survey of data centers

Completed · Texas · State

Ended: 10 July 2026

Issuing authority: Public Utility Commission of Texas

The Public Utility Commission of Texas ran a one-time Energy and Water Use survey of data centers and virtual currency mining facilities that operate, or plan to operate, in Texas by 2030, to fulfil a study requirement in the General Appropriations Act and inform the state water plan.

Read the sourced record · Primary source

Federal and multistate

Federal and multistate instruments that cover all or part of Texas

These federal, reliability-organization and multistate grid or utility instruments are stored once and listed for every jurisdiction they name. They do not add to the record count, in-effect total or map shading for Texas. Territorial coverage does not establish that an instrument applies to any particular site, utility or project.

Enacted legislation or regulation · Listed coverage: part of Texas

Southwest Power Pool: Conditional High Impact Large Load Service accepted by FERC (ER26-1323)

In effect · Southwest Power Pool region (multistate) · Regional grid

Effective: 1 July 2026

Issuing authority: Federal Energy Regulatory Commission

On 5 June 2026 the Federal Energy Regulatory Commission accepted Southwest Power Pool tariff revisions, effective 1 July 2026, that add Conditional High Impact Large Load Service, a non-firm transmission service that can serve a large load such as a data center before long-term firm service is available, for up to seven years and subject to curtailment.

Read the sourced record · Primary source

Enacted legislation or regulation · Listed coverage: part of Texas

Southwest Power Pool: High Impact Large Load study processes accepted by FERC (ER26-247)

In effect · Southwest Power Pool region (multistate) · Regional grid

Effective: 15 January 2026

Issuing authority: Federal Energy Regulatory Commission

On 14 January 2026 the Federal Energy Regulatory Commission accepted Southwest Power Pool tariff revisions, effective 15 January 2026, that add a High Impact Large Load study process and a generation assessment for those loads.

Read the sourced record · Primary source

Open the Texas policy comparison

Review dates: the 13 Texas records were last checked 23 September 2026 to 25 October 2026. 12 scheduled reviews are overdue as of the tracker date 3 November 2026: TCEQ data-center permit pause (last checked 25 October 2026, review due 1 November 2026); ERCOT data center state and community impact information request, Water-use reporting enforcement directive, Order letting ERCOT delay Batch Zero classification during the data-center audit, Fort Worth: water and wastewater criteria for data centers, ERCOT ride-through requirements for large computational loads (NOGRR 282), ERCOT definition of Large Computational Load (NPRR 1308), Directive on data-center infrastructure costs, San Angelo: zoning standards for data centers (Sec. 430), Data center sales-tax exemption (last checked 23 September 2026, review due 23 October 2026); ERCOT large-load interconnection pause, ERCOT approval pause pending audit (last checked 23 September 2026, review due 28 October 2026). Overdue means not re-read yet, not changed. No single record, and not this list, establishes complete statewide policy coverage.