Summary
ERCOT Nodal Protocol Revision Request 1308 defines a Large Computational Load as a Large Load (75 MW or more at a site) in which at least half of the demand is power-electronic computational load, such as data centers and cryptocurrency mining facilities. The Public Utility Commission approved it on 9 July 2026 in Project No. 54445 and it took effect on 1 August 2026. The definition distinguishes this load type so that specific rules, such as the ride-through requirements in NOGRR 282, can apply to it.
Scope
Nodal Protocol Revision Request 1308 adds the defined term Large Computational Load to the ERCOT Protocols: a Large Load in which 50% or more of the demand at the site is power-electronic computational load, such as data centers and cryptocurrency mining facilities. It was approved by the Public Utility Commission on 9 July 2026 and is effective 1 August 2026. The definition itself imposes no requirement; the ride-through requirements that use it are in NOGRR 282.
- Geographic scope
- ERCOT region, Texas
- Jurisdiction
- Regional grid
- Authority type
- Grid operator
- Issuing authority
- Electric Reliability Council of Texas
Dates
- Adopted
- 9 July 2026
- Effective
- 1 August 2026
- Scheduled expiration
- See completion condition
- Ended
- Not recorded as ended
- Completion condition
- The revision states no expiration.
- Source document
- 9 July 2026
- Last checked
- 23 September 2026
About this date
This record was last checked before the tracker date, 16 November 2026. An earlier check date does not by itself mean the record's status has changed.
What this does not establish
- The definition text was read in ERCOT's PUCT report document for NPRR 1308 (a Word file); its redline shows the earlier term Large Electronic Load being replaced.
- The definition names data centers as examples of computational load; whether a particular site meets the 50% test is not established here.
- The Large Load threshold (75 MW at a site) comes from the same redline's existing definition, not from a new rule in this revision.
Unresolved questions
None recorded.
Relationships
Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.
- Related, not a replacement ERCOT ride-through requirements for large computational loads (NOGRR 282) (In effect)
Sources
Primary source: Electric Reliability Council of Texas page on ercot.com
- ERCOT PUCT Report for NPRR 1308 (9 July 2026) — approved definition text and decision record · 9 July 2026