Aligned Data Centers Project Caprock

source-reported under construction

Aligned Data Centers

Abernathy · Hale County · Texas

Reported planned 540 MWSource updated 6 July 2026approximate location · provider confidence label: confirmed
How to read this page

This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.

Reported geography

Source-reported location for Aligned Data Centers Project Caprock.

Approximate source coordinates; this is not a parcel claim. Nearby source points are combined into one accessible target that opens this exact map scope. View these exact rows on the interactive map →

Exact source coordinates Approximate or representative coordinates Nearby-point group. This relative plot uses only source-supplied points, makes no parcel claim and loads no map tiles.

Source row snapshot

Operator as published
Aligned Data Centers
Address and locality
Abernathy · Hale County · Texas
Official metro area
Outside an official metropolitan boundary
Source-reported status
under construction
Provider facility type
data center
Reported capacity
Planned: 540 MW (source-reported; boundary not independently verified; MW measure not stated by provider)
Source freshness
6 July 2026
Location precision
approximate (provider label: exact; the provider's own note describes an approximate location)
Compute Atlas confidence label
confirmed (provider's classification; not a DataCenterData check)
Stable directory ID
dcd-dir-000049

Reported details

Source-reported by Compute Atlas; not independently verified by DataCenterData. Provider wording is kept; long provider notes are shortened and marked …; unknown is not zero; none of these values is totaled, ranked or compared.

Electric utility
Xcel EnergyUtility as named by the provider.
Power source
GridProvider label.
Cooling
Closed-loopProvider label.
Land area
313 acres (source-reported; parcel boundary not established)
Community response
Provider label: mixedCompute Atlas characterization, not a DataCenterData assessment. Open cited source →
AI-use label (provider)
likelyCompute Atlas classification, not a DataCenterData finding.
Announced
April 2026Provider-reported announcement date.

Provider notes

Energy. Aligned is building and funding dedicated electrical infrastructure to protect local ratepayers. Xcel Energy is the key power partner. Regional renewable resources (solar, wind) available in Texas Panhandle.

Water. DeltaFlow liquid cooling technology with closed-loop air-cooled heat rejection; no Ogallala Aquifer water use per developer.

Community. Hale County finalized a development agreement and the April 2026 groundbreaking was billed as the largest data-center groundbreaking in West Texas; Aligned emphasized funding dedicated electrical infrastructure to protect local ratepayers. Local coverage also documents some resident concern; no formal opposition or litigation found.

What the source record says

Six facilities totaling 1.65 million sq ft across 313 acres. Largest data center groundbreaking in West Texas at time of announcement. TeraWulf separately targeting a data center campus in Abernathy for Fluidstack. Coordinates corrected: Abernathy TX is at approximately 33.84°N, 101.84°W; original record had longitude −101.55 which is ~15 miles east of the city.

Capacity is not ranked or totaled here.

Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.

Status history supplied by the source

  1. 2025-12 · source-reported proposed

    Site selection and development agreement finalized in Hale County.

    Open cited source →

  2. 2026-04 · source-reported under construction

    Groundbreaking April 9, 2026. LBB-01 inaugural data center targets Q1 2027 service date. Ryan Companies is general contractor.

    Open cited source →

Sources and attribution

These sources are listed for the whole row. Unless a figure links to its own source, the provider does not mark which one gave it, so a figure may not appear in every source.

Adapted from Compute Atlas by Edward Kubiak, edition 1.34.1, under CC BY 4.0. Upstream ID aligned-project-caprock-hale-county-tx. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added. Some locations in this layer are reported by the provider as derived from OpenStreetMap (© OpenStreetMap contributors, ODbL, https://www.openstreetmap.org/copyright) and Epoch AI (CC BY 4.0).

Compute Atlas 1.34.1 with retained prior rows and publication holds. This is a DataCenterData composite, not an unmodified publisher edition. This row uses the captured source from 1.34.1, source as of 2026-10-14T20:40:52.293Z.

No reviewed record is linked to this row yet.

That does not mean the row is wrong, and it does not mean no reviewed record exists for the same place. A link is added only when an identifier or source establishes the match.

Recorded information

What this page records, grouped by topic, with the source's units and qualifications. Company-reported values stay labeled as company-reported. Related listings are shown separately.

Licensed directory listing dcd-dir-000049

Licensed directory row. Licensed directory label. Source-reported and not independently verified.

Provider notes and the source narrative are printed on this page and are not repeated here.

Identity and relationships

  • Provider facility type: data center

    Provider facility type.

  • AI-use label (provider): likely

    Compute Atlas classification, not a DataCenterData finding.

Location and precision

  • Abernathy, TX · Hale (Approximate location)

Roles

  • Operator: Aligned Data Centers

    Operator label as published by the provider; no parent company is inferred.

Lifecycle

  • Source-stated status: source-reported under construction

    Provider status label; not a DataCenterData finding that the facility is operating.

  • Announced: April 2026

    Provider-reported announcement date.

  • Status history: 2025-12 · source-reported proposed

    Status history supplied by the source.

  • Status history: 2026-04 · source-reported under construction

    Status history supplied by the source.

Area, acreage and buildings

  • Land area: 313 acres (source-reported; parcel boundary not established)

Power capacity

  • Reported capacity: Planned: 540 MW (source-reported; boundary not independently verified; MW measure not stated by provider)

    Reproduced as the page prints it; not ranked or totaled; unknown is not zero.

  • Electric utility: Xcel Energy

    Utility as named by the provider.

  • Power source: Grid

    Provider label.

Cooling, water, PUE and WUE

  • Cooling: Closed-loop

    Provider label.

Permits, incentives, jobs and proceedings

  • Community response: Provider label: mixed

    Compute Atlas characterization, not a DataCenterData assessment.

Sources, dates, limitations and corrections

  • Provider update date: 2026-07-06

    Provider update date is not a DataCenterData verification date.

Not yet recorded here: Connectivity · Services · Certifications and design ratings · Rack density · Availability · Specification links and contact.

Licensed values: adapted from Compute Atlas by Edward Kubiak under CC BY 4.0. Source-reported and not independently verified.

Update this profile with a public source. The request includes topics needing more information; this does not mean the facility lacks them. Corrections and additions are reviewed before publication.

Corrections

Report an error in this row →