Adopted measures with unverified effect, adopted future measures, open proceedings, proposals, drafts and nonbinding context stay separate from current rules.
Reporting or resource-use requirement
Adopted—not yet effective · California · State
Effective: 1 January 2027
Issuing authority: California Legislature
California AB 1577, approved by the Governor and chaptered on 21 September 2026 as chapter 434, adds data center reporting duties.
Read the sourced record · Primary source · Reviewed alternate official source (23 September 2026)
Enacted legislation or regulation
Adopted—not yet effective · California · State
Effective: 1 January 2027
Issuing authority: California Legislature
California AB 2383, approved and chaptered on 21 September 2026 as chapter 435, adds Public Utilities Code sections on data center electric tariffs.
Read the sourced record · Primary source · Reviewed alternate official source (23 September 2026)
Enacted legislation or regulation
Adopted—not yet effective · California · State
Effective: 1 January 2027
Issuing authority: California Legislature
California AB 2469, approved and chaptered on 21 September 2026 as chapter 436, bars cities and counties from approving a permit or entitlement for construction of a data center, or an expansion that increases maximum peak water use, unless the applicant provides a water supply assessment, projected water use and efficiency measures, workforce disclosures and, from 1 January 2028, a water scarcity plan, and pays for required water infrastructure.
Read the sourced record · Primary source · Reviewed alternate official source (23 September 2026)
Reporting or resource-use requirement
Adopted—not yet effective · California · State
Effective: 1 January 2027
Issuing authority: California Legislature
California AB 2619, approved and chaptered on 21 September 2026 as chapter 437, requires data center owners or operators to give their water supplier and the city or county a good faith water-use estimate at initial business licensing, under penalty of perjury, and to report the previous year's total and direct water use and cooling system type at each license renewal.
Read the sourced record · Primary source · Reviewed alternate official source (23 September 2026)
Enacted legislation or regulation
Adopted—not yet effective · California · State
Effective: 1 January 2027
Issuing authority: California Legislature
California SB 1168, approved and chaptered on 21 September 2026 as chapter 440, requires the Public Utilities Commission to assess, in a new or existing proceeding, rate structures that make data centers pay a reasonable share of transmission and distribution costs and their proportionate share of load-driven procurement, while easing cost pressure on residential customers, including low-income program customers.
Read the sourced record · Primary source · Reviewed alternate official source (23 September 2026)
Enacted legislation or regulation
Adopted—not yet effective · California · State
Effective: 1 January 2027
Issuing authority: California Legislature
California SB 886, approved and chaptered on 21 September 2026 as chapter 438, requires the Public Utilities Commission by 1 January 2028 to set new tariffs or rules for interconnection of, and electric service to, participating data center customers that prevent stranded costs or cost shifts to other customers.
Read the sourced record · Primary source · Reviewed alternate official source (23 September 2026)
Enacted legislation or regulation
Adopted—not yet effective · California · State
Effective: 1 January 2027
Issuing authority: California Legislature
California SB 887, approved and chaptered on 21 September 2026 as chapter 439, makes the California Environmental Quality Act apply to entitlements for developing and operating a data center, defines data center for that purpose and bars categorical exemptions for such projects as specified.
Read the sourced record · Primary source · Reviewed alternate official source (23 September 2026)
Legislation introduced (any outcome) · Oakland only (local rule)
Proposed · Oakland, California · Local
Source document: 21 October 2026
Issuing authority: Oakland City Council
Oakland file 27-0178, created on 21 October 2026, is a proposed interim emergency ordinance that would extend Interim Emergency Ordinance No. 13899 C.M.S., the city's temporary moratorium on approving land use entitlements and agreements for the development or operation of data centers, for ten months and fifteen days.
Read the sourced record · Primary source
Local construction moratorium · San Francisco only (local rule)
Adopted; effective status unverified · City and County of San Francisco, California · Local
Adopted: 6 October 2026
Issuing authority: San Francisco Board of Supervisors
On 6 October 2026 the San Francisco Board of Supervisors passed File No. 261021, an urgency ordinance under Government Code Section 65858, by 11 ayes.
Read the sourced record · Primary source
Regulatory or tariff proceeding
Pending proceeding · Pacific Gas and Electric service territory, California · State
Source document: 22 September 2026
Issuing authority: California Public Utilities Commission
PG&E asked the California Public Utilities Commission in December 2025 (Advice Letter 7785-E) to approve an agreement to energize a new 250 megawatt data center load for Google LLC at transmission level.
Read the sourced record · Primary source
Regulatory or tariff proceeding
Pending proceeding · California · State
Source document: 10 April 2026
Issuing authority: California Public Utilities Commission
The California Public Utilities Commission opened Rulemaking 26-04-009 on advanced electric rate design; the order was filed on 9 April 2026 and issued on 10 April 2026.
Read the sourced record · Primary source
Reporting or resource-use requirement
Informational—not binding · California · State
Last checked: 23 September 2026
Issuing authority: California Energy Commission
The California Energy Commission explains that it does not permit data centers but includes projected data center load in its demand forecast (since 2024) and reviews data centers' larger on-site power plants, most often backup generators, through its Small Power Plant Exemption, certification or opt-in programs under CEQA.
Read the sourced record · Primary source