In plain English
Who it would affect: This draft covers one agreement, on modified standard forms, between Pacific Gas and Electric (PG&E) and Google LLC. The draft describes a new 250 megawatt data center load in San Jose, served at 230 kilovolts, which it calls transmission level.
What it would change: The draft would approve the agreement with changes. Google would make an added refundable up-front payment, called a capital advance, of $600,000 per megawatt. Yearly refunds would be limited to what PG&E collected that year through the transmission part of Google's rates and a per meter charge, adjusted for the Income Tax Component of Contribution. The refund period would grow from 10 to 15 years.
Easy to misread: The draft says it makes no decisions on broad policy questions and does not prejudice the pending case on a standard rule for such loads (Rule 30) or the Advanced Electric Rate Design proceeding.
- Proposed load: 250 MW at 230 kilovolts in San Jose (Summary)
- Proposed added capital advance: $600,000 per MW of requested capacity, refundable, paid the year before that capacity is both requested by Google and deemed available by PG&E (Therefore it is ordered, paragraph 2)
- Proposed annual refund limit: The annual net revenues PG&E collected from Google that year, adjusted for the Income Tax Component of Contribution (Therefore it is ordered, paragraph 4)
- Proposed refund period: 15 years, up from 10 (Therefore it is ordered, paragraph 4)
- Possible later change: Within one year after the decision in the Rule 30 case, A. 24-11-007, PG&E may file a Tier 2 Advice Letter, a utility filing, to update the advance (Therefore it is ordered, paragraph 3)
- Proposed cost cap report: An information-only Tier 1 Advice Letter within 30 days after the binding cost cap for refundable Applicant Work is finalized (Therefore it is ordered, paragraph 7)
Written from California Public Utilities Commission Draft Resolution E-5455, revision published 14 October 2026, printed date 29 October 2026, read on 3 November 2026. A reading aid, not legal advice. The document controls.
Summary
PG&E asked the California Public Utilities Commission in December 2025 (Advice Letter 7785-E) to approve an agreement to energize a new 250 megawatt data center load for Google LLC at transmission level. Draft Resolution E-5455 would approve it with modifications, including an added refundable capital advance of $600,000 per MW, a yearly limit on refunds and a refund period of 15 years instead of 10. The item was listed on the 17 September 2026 consent agenda. The latest draft, rev4, published on 14 October 2026, differs from the earlier draft only in its printed date and document number. The official index lists no final resolution.
Scope
The California Public Utilities Commission is considering Pacific Gas and Electric Company Advice Letter 7785-E, filed 18 December 2025, an exceptional case submittal under Electric Rules 2, 15 and 16 for an agreement to energize a new 250 megawatt data center load through transmission-level retail service for Google LLC in San Jose. Draft Resolution E-5455 proposes approval with modifications, including an additional refundable capital advance of $600,000 per MW, a yearly limit on refunds and a refund period extended from 10 to 15 years. The draft was listed on the 17 September 2026 consent agenda; the official index lists a further revised draft (rev4) published on 14 October 2026, which keeps these terms. No adopted resolution is recorded.
- Geographic scope
- Pacific Gas and Electric service territory, California
- Jurisdiction
- State
- Authority type
- Regulator or commission
- Issuing authority
- California Public Utilities Commission
Dates
- Adopted
- No adoption day is recorded
- Effective
- Not in effect (open proceeding)
- Scheduled expiration
- No expiration date recorded
- Ended
- Not recorded as ended
- Completion condition
- None stated
- Source document
- 22 September 2026
- Last checked
- 3 November 2026
About this date
This record was last checked before the tracker date, 14 November 2026. An earlier check date does not by itself mean the record's status has changed.
What this does not establish
- This is a draft resolution on a pending advice letter, not an adopted Commission decision; if adopted, the final resolution will be its own record.
- The 29 October 2026 date printed on rev4 is a scheduled meeting date on the Commission's list, not an adoption or effective date. Rev4's adoption line reads "held on [DATE]".
- Cost figures in the draft may change before adoption.
- The official index read on 3 November 2026 lists drafts only, and one index search surfaced no 29 October agenda. Whether the Commission acted on 29 October is not known.
Unresolved questions
- Whether the Commission adopts, modifies or rejects the draft resolution.
Relationships
Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.
- Related, not a replacement CPUC Resolution E-5420: PG&E transmission energization agreement for a STACK Infrastructure data center (In effect)
- Related, not a replacement CPUC Resolution E-5439: PG&E transmission energization agreement for a Microsoft data center (In effect)
- Related, not a replacement CPUC Resolution E-5433: PG&E transmission energization agreement for a Menlo Equities data center (In effect)
Sources
Primary source: California Public Utilities Commission page on docs.cpuc.ca.gov
- CPUC document search listing for E-5455 — Official index lists rev4 published 14 October 2026 and no final resolution when read on 3 November 2026.
- CPUC voting meeting agenda, 17 September 2026 — consent agenda listing of Res E-5455
- Draft Resolution E-5455, rev4 — latest draft found; read on 3 November 2026; printed date 29 October 2026 · 14 October 2026