A verdict applies only to the wording shown.
Company claims are shown as stated; they are not findings.
Public statement checked
Verdict on the wording above: Partially supported
Said by Loudoun County · Virginia
Review scope: County pages and adopted budget summaries read 1 November 2026
Partially supported means the 40% figure fits the adopted General Fund; it does not fit the $5.4 billion the county calls its budget, and the $1.3 billion was not independently confirmed.
Evidence and limits
Evidence limitation: The adopted budget's data center revenue lines (the $1.3 billion figure was not found in the adopted documents read) and which base the county meant by 'total budget'.
Read the answer and sources →
Checked 1 November 2026
Public statement checked
Verdict on the wording above: Company claim
Said by Vantage Data Centers · Virginia
Review scope: Vantage campus page checked 1 October 2026
Evidence and limits
Evidence limitation: Whether construction has started, any building is operating, or the stated IT load, area, or water-use figure has been measured. Utility power is a separate figure on the same page.
Read the answer and sources →
Checked 1 October 2026
Question reviewed
Verdict on the wording above: Unknown
Question examined by DataCenterData · Virginia
Review scope: Vantage campus page checked 1 October 2026
Evidence and limits
Evidence limitation: The wording of the unopened social post and wire release. Any permit or company record that states a phase size or a job count.
Read the answer and sources →
Checked 1 October 2026
Public statement checked
Verdict on the wording above: Company claim
Said by Vantage Data Centers · Virginia
Review scope: Vantage campus page checked 1 October 2026
Evidence and limits
Evidence limitation: Whether the substation is built or energized, and any utility filing that states its capacity.
Read the answer and sources →
Checked 1 October 2026
Public statement checked
Verdict on the wording above: Company claim
Said by DataBank · Virginia
Review scope: DataBank pages captured 25 September 2026
Evidence and limits
Evidence limitation: Whether either building is under construction or operating. Utility power. Metered load. The wording of the unopened construction post.
Read the answer and sources →
Checked 25 September 2026
Documented fact
Verdict on the wording above: Supported
Said by Chesterfield County · Google Bermuda Hundred Data Center Campus
Review scope: Chesterfield table as of July 2026
Evidence and limits
Evidence limitation: Current measured withdrawal or consumption; operator and title-owner legal roles; reconciliation of 2100 versus 2400 and 2700 Bermuda Hundred Road.
Read the answer and sources →
Checked 21 September 2026