Public statement checked
Answer
Verdict on the wording above: Company claim as of Vantage campus page checked 2026-10-01 The only support is the company or its agents. Shown as stated, not adopted. Not a finding that it is true or false. How verdicts work →
- Who stated it
- Said by Vantage Data Centers · company statement in Vantage Fredericksburg VA4 campus page →
- What the evidence establishes
- The same page states a private 270 MW on-site substation served by Dominion Energy. That is utility equipment, not the 192 MW critical IT figure. Shown as the company's statement, not as a finding either way.
- Biggest limitation
- Whether the substation is built or energized, and any utility filing that states its capacity.
- Checked
- 1 October 2026 · Next review: A utility filing or energization record for this substation
Evidence
What the evidence supports
The Vantage page says power is provided by Dominion Energy and that a private 270 MW on-site substation will provide dedicated power. The 270 MW figure is the stated substation size. The page's 192 MW figure is combined critical IT load. The page does not say the substation is operating or that 270 MW is IT capacity.
Still unknown
Whether the substation is built or energized, and any utility filing that states its capacity.
Sources
-
Vantage Data Centers, Fredericksburg VA4 campus page → Company
Exact location Electrical section: Power provided by Dominion Energy. Private 270 MW on-site substation.
What it supports States a planned private on-site substation of 270 MW. Not the critical IT figure.
Review details
Scope
- Unit
- on-site substation MW
- Geography
- VA4, 225 Centreport Parkway, Fredericksburg, Virginia
- Period
- page date not stated; substation described as planned
- As of
- Vantage campus page checked 2026-10-01
- Confidence
- medium — Operator campus page only. No utility filing reviewed.
- Kind
- Public statement checked
Conflicting evidence
None recorded when this claim was checked. That records what we logged, not a finding that no conflicting record exists.
Chronology
- Source retrieved
- Checked by DataCenterData
- Date not established Stated by Vantage Data Centers — statement date not established
- Date not established Next review: A utility filing or energization record for this substation
Corrections and history
No corrections or wording changes recorded for this claim.
Data
Suggest a correction
Suggest a correction → Claim ID vantage-fredericksburg-substation and this page are prefilled. Accepted material corrections appear publicly on Changes.