Claims · by state

Checked claims about Tennessee data-center projects

1 checked claim so far about projects in Tennessee — because those are the Tennessee claims DataCenterData has checked, not a count of Tennessee claims or data centers. Tennessee records →

All evidence checks → · Search and filter → · Corrections

1 claim · newest check first

A verdict applies only to the wording shown.

Company claims are shown as stated; they are not findings.

Public statement checked

xAI was connected to a newly constructed electric substation (#63) from which it is now receiving 150MW of grid power from MLGW and TVA.

Verdict on the wording above: Partially supported

Said by Greater Memphis Chamber · Tennessee

Review scope: Chamber release and MLGW update read 1 November 2026

Evidence and limits

Evidence limitation: Metered load at the site, whether the second 150 MW has since been approved and energized, and the substation numbering, which MLGW's update does not give.

Read the answer and sources →

Checked 1 November 2026

What this covers. 1 checked claim so far about projects in Tennessee. That is because those are the Tennessee claims DataCenterData has checked, not a count of claims or of data centers. Where a state, operator, project or topic shows no checked claim, read it as “not yet checked by DataCenterData”.

What a verdict means. A verdict applies only to the wording shown and the evidence linked on the check date. Where a separate question appears beside a statement checked, the verdict is about that statement, and the question has its own answer. “Unknown” means the reviewed evidence did not establish the point; it never means zero or false.

All 90 checked claims and what they cover → · Corrections log →