Checked claims about Delaware data-center projects

1 checked claim so far about projects in Delaware — because those are the Delaware claims DataCenterData has checked, not a count of Delaware claims or data centers. Delaware records →

All evidence checks → · Search and filter → · Corrections

1 claim · newest check first

A verdict applies only to the wording shown.

Company claims are shown as stated; they are not findings.

Documented fact

Delaware Public Service Commission Order No. 10816 (3 September 2025) requires a Delmarva large-load tariff to be in place before any new customer of 25 MW or more monthly maximum demand is interconnected.

Verdict on the wording above: Supported

Said by the Delaware Public Service Commission · Delaware

Review scope: Delaware PSC documents captured 5 October 2026

Evidence and limits

Evidence limitation: Whether the Commission has approved a Delmarva large-load tariff, its terms, and whether any 25 MW-plus customer has been interconnected or has an interconnection date. The text of Order 10829, Delmarva's Dec 2025 tariff filing and the Hearing Examiner's findings were not read. Docket 25-0826 on DelaFile was not retrieved. No reviewed document in the sources checked establishes it.

Read the answer and sources →

Checked 5 October 2026

What this covers. 1 checked claim so far about projects in Delaware. That is because those are the Delaware claims DataCenterData has checked, not a count of claims or of data centers. Where a state, operator, project or topic shows no checked claim, read it as “not yet checked by DataCenterData”.

What a verdict means. A verdict applies only to the wording shown and the evidence linked on the check date. Where a separate question appears beside a statement checked, the verdict is about that statement, and the question has its own answer. “Unknown” means the reviewed evidence did not establish the point; it never means zero or false.