Claims · by state

Checked claims about Kansas data-center projects

1 checked claim so far about projects in Kansas — because those are the Kansas claims DataCenterData has checked, not a count of Kansas claims or data centers. Kansas records →

All evidence checks → · Search and filter → · Corrections

1 claim · newest check first

A verdict applies only to the wording shown.

Company claims are shown as stated; they are not findings.

Documented fact

Kansas statute K.S.A. 66-101j(c) makes a qualified data center ineligible for the statutory economic-development electric rate discount.

Verdict on the wording above: Supported

Said by Kansas Legislature (K.S.A. 66-101j) · Kansas

Review scope: Statute text captured 6 November 2026

Evidence and limits

Evidence limitation: The definition of qualified data center in K.S.A. 74-50,331 and its thresholds; whether any Kansas utility serves a data center under a commission-approved contract rate outside this section; what tariff or contract any named Kansas project, including the tracked Beale Data Center record, would take service under; and the 'cooperative' exclusion's effect on data centers served by cooperatives. No reviewed document in the sources checked establishes it.

Read the answer and sources →

Checked 6 November 2026

What this covers. 1 checked claim so far about projects in Kansas. That is because those are the Kansas claims DataCenterData has checked, not a count of claims or of data centers. Where a state, operator, project or topic shows no checked claim, read it as “not yet checked by DataCenterData”.

What a verdict means. A verdict applies only to the wording shown and the evidence linked on the check date. Where a separate question appears beside a statement checked, the verdict is about that statement, and the question has its own answer. “Unknown” means the reviewed evidence did not establish the point; it never means zero or false.

All 90 checked claims and what they cover → · Corrections log →