Checked claims about Kentucky data-center projects

1 checked claim so far about projects in Kentucky — because those are the Kentucky claims DataCenterData has checked, not a count of Kentucky claims or data centers. Kentucky records →

All evidence checks → · Search and filter → · Corrections

1 claim · newest check first

A verdict applies only to the wording shown.

Company claims are shown as stated; they are not findings.

Public statement checked

Customers on LG&E and KU's Extremely High Load Factor rate must sign a 15-year contract, commit to paying for at least 80% of the power they reserve, and provide deposits equal to between 12 and 24 months of their service.

Verdict on the wording above: Partially supported

Said by LG&E and KU · Kentucky

Review scope: Tariff, order and company page read 1 November 2026

Partially supported because only Louisville Gas and Electric's Rate EHLF tariff was checked; Kentucky Utilities' parallel tariff was not read.

Evidence and limits

Evidence limitation: Kentucky Utilities' parallel EHLF tariff was not read. Which customers have signed EHLF agreements and on what terms; agreements are to be filed with the Commission.

Read the answer and sources →

Checked 1 November 2026

What this covers. 1 checked claim so far about projects in Kentucky. That is because those are the Kentucky claims DataCenterData has checked, not a count of claims or of data centers. Where a state, operator, project or topic shows no checked claim, read it as “not yet checked by DataCenterData”.

What a verdict means. A verdict applies only to the wording shown and the evidence linked on the check date. Where a separate question appears beside a statement checked, the verdict is about that statement, and the question has its own answer. “Unknown” means the reviewed evidence did not establish the point; it never means zero or false.

All 90 checked claims and what they cover → · Corrections log →