Licensed lead · not independently verified · dcd-dir-000133

AWS Cosgray Road Campus

source-reported operational

Amazon Web Services

4580-4640 Cosgray Rd · Hilliard · Franklin County · Ohio

Capacity not statedSource updated 14 October 2026exact location (provider label) · provider confidence label: reported
How to read this page

This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.

Reported geography

Source-reported location for AWS Cosgray Road Campus.

Exact source coordinates (provider label); this is not a parcel claim. Nearby source points are combined into one accessible target that opens this exact map scope. View these exact rows on the interactive map →

Exact source coordinates Approximate or representative coordinates Nearby-point group. This relative plot uses only source-supplied points, makes no parcel claim and loads no map tiles.

Source row snapshot

Operator as published
Amazon Web Services
Address and locality
4580-4640 Cosgray Rd · Hilliard · Franklin County · Ohio
Official metro area
Columbus, OH
Source-reported status
operational
Provider facility type
data center
Reported capacity
Not stated
Source freshness
14 October 2026
Location precision
exact (provider label)
Compute Atlas confidence label
reported (provider's classification; not a DataCenterData check)
Stable directory ID
dcd-dir-000133

Reported details

Source-reported by Compute Atlas; not independently verified by DataCenterData. Provider wording is kept; long provider notes are shortened and marked …; unknown is not zero; none of these values is totaled, ranked or compared.

Electric utility
AEP Ohio (Ohio Power Company)Utility as named by the provider.
Power source
GridProvider label.
On-site generation
72.9 MW (source-reported)On-site figures often describe backup generators rather than primary supply; read the provider energy note.
Community response
Provider label: contestedCompute Atlas characterization, not a DataCenterData assessment. Open cited source →

Provider notes

Energy. 228 Bloom Energy solid-oxide fuel cell units totalling 72.9 MW, to be built and operated behind the meter by Ohio Power Company (an AEP Ohio subsidiary) on about 6.4 acres at 4186 Scioto Darby Creek Road, serving Amazon Data Services only and not exporting to the grid. Ohio Power Siting Board approval 2025-09-22; construction began January 2026; in service expected September 2027.

Community. Hilliard has asked AEP and Bloom Energy to install carbon-capture technology, citing an air permit that allows emissions of up to 1.45 million pounds of CO2 per day, and the air permit is in administrative-court litigation. The array sits adjacent to an elementary school and a neighborhood park.

What the source record says

Separate AWS Hilliard campus on Cosgray Road, in active litigation: the City of Hilliard appealed an Ohio EPA air permit for a 228-unit Bloom Energy fuel-cell array (73MW, the largest fuel-cell array in North America), and AWS is separately seeking a permit for 158 diesel backup generators. Approved by the Ohio Power Siting Board under Ohio's HB15 behind-the-meter law, overriding local zoning. Distinct from the Scioto Darby campus. Coordinates are now parcel-exact via the Franklin County Auditor (parcel 050-011455, 4580-4640 Cosgray Rd, Amazon Data Services Inc, data-center use class, ~95 ac).

Capacity is not ranked or totaled here.

Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.

Status history supplied by the source

  1. 2026 · source-reported under construction

    In active litigation over a 228-unit Bloom Energy fuel-cell array (73MW, largest fuel-cell array in North America) plus backup generators; approved by the Ohio Power Siting Board under HB15.

    Open cited source →

  2. 2026-07-19 · source-reported operational

    Flipped under_construction -> operational. Franklin County Auditor assessed building area is populated (880,352 sq ft) on the campus parcel (050-011455, land-use class 'data center', Amazon Data Services Inc) = built, not a bare shell; data-center directories (DC Byte / datacenterHawk) list the Cosgray buildings as operational. The Bloom Energy fuel-cell / backup-generator permitting litigation noted in the record concerns on-site power and does not bear on the data buildings' operational status.

    Open cited source →

Sources and attribution

These sources are listed for the whole row. Unless a figure links to its own source, the provider does not mark which one gave it, so a figure may not appear in every source.

Adapted from Compute Atlas by Edward Kubiak, edition 1.34.1, under CC BY 4.0. Upstream ID aws-cosgray-hilliard-oh. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added. Some locations in this layer are reported by the provider as derived from OpenStreetMap (© OpenStreetMap contributors, ODbL, https://www.openstreetmap.org/copyright) and Epoch AI (CC BY 4.0).

Compute Atlas 1.34.1 with retained prior rows and publication holds. This is a DataCenterData composite, not an unmodified publisher edition. This row uses the captured source from 1.34.1, source as of 2026-10-14T20:40:52.293Z.

No reviewed record is linked to this row yet.

That does not mean the row is wrong, and it does not mean no reviewed record exists for the same place. A link is added only when an identifier or source establishes the match.

Recorded information

What this page records, grouped by topic, with the source's units and qualifications. Company-reported values stay labeled as company-reported. Related listings are shown separately.

Licensed directory listing dcd-dir-000133

Licensed directory row. Licensed directory label. Source-reported and not independently verified.

Provider notes and the source narrative are printed on this page and are not repeated here.

Identity and relationships

  • Provider facility type: data center

    Provider facility type.

Location and precision

  • 4580-4640 Cosgray Rd, Hilliard, OH · Franklin (Exact location)

Roles

  • Operator: Amazon Web Services

    Operator label as published by the provider; no parent company is inferred.

Lifecycle

  • Source-stated status: source-reported operational

    Provider status label; not a DataCenterData finding that the facility is operating.

  • Status history: 2026 · source-reported under construction

    Status history supplied by the source.

  • Status history: 2026-07-19 · source-reported operational

    Status history supplied by the source.

Power capacity

  • Reported capacity: Not stated

    Reproduced as the page prints it; not ranked or totaled; unknown is not zero.

  • Electric utility: AEP Ohio (Ohio Power Company)

    Utility as named by the provider.

  • Power source: Grid

    Provider label.

  • On-site generation: 72.9 MW (source-reported)

    On-site figures often describe backup generators rather than primary supply; read the provider energy note.

Permits, incentives, jobs and proceedings

  • Community response: Provider label: contested

    Compute Atlas characterization, not a DataCenterData assessment.

Sources, dates, limitations and corrections

  • Provider update date: 2026-10-14

    Provider update date is not a DataCenterData verification date.

Not yet recorded here: Area, acreage and buildings · Cooling, water, PUE and WUE · Connectivity · Services · Certifications and design ratings · Rack density · Availability · Specification links and contact.

Licensed values: adapted from Compute Atlas by Edward Kubiak under CC BY 4.0. Source-reported and not independently verified.

Update this profile with a public source. The request includes topics needing more information; this does not mean the facility lacks them. Corrections and additions are reviewed before publication.

Corrections

Report an error in this row →