Amazon AWS Gilroy Data Center

source-reported under construction

Amazon Web Services

8050 Camino Arroyo · Gilroy · Santa Clara County · California · 95020

Reported planned 98 MWSource updated 14 September 2026exact location (provider label) · provider confidence label: confirmed
How to read this page

This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.

Reported geography

Source-reported location for Amazon AWS Gilroy Data Center.

Exact source coordinates (provider label); this is not a parcel claim. Nearby source points are combined into one accessible target that opens this exact map scope. View these exact rows on the interactive map →

Exact source coordinates Approximate or representative coordinates Nearby-point group. This relative plot uses only source-supplied points, makes no parcel claim and loads no map tiles.

Source row snapshot

Operator as published
Amazon Web Services
Address and locality
8050 Camino Arroyo · Gilroy · Santa Clara County · California · 95020
Official metro area
San Jose-Sunnyvale-Santa Clara, CA
Source-reported status
under construction
Provider facility type
data center
Reported capacity
Planned: 98 MW (source-reported; boundary not independently verified; MW measure not stated by provider)
Source freshness
14 September 2026
Location precision
exact (provider label)
Compute Atlas confidence label
confirmed (provider's classification; not a DataCenterData check)
Stable directory ID
dcd-dir-000064

Reported details

Source-reported by Compute Atlas; not independently verified by DataCenterData. Provider wording is kept; long provider notes are shortened and marked …; unknown is not zero; none of these values is totaled, ranked or compared.

Electric utility
Pacific Gas & Electric (PG&E)Utility as named by the provider.
Power source
GridProvider label.
Cooling
HybridProvider label.
Reported water use
0.016 million gallons per day (source-reported)Whether this is metered use, a permit limit or a request is not established; see the provider water note.
Land area
56 acres (source-reported; parcel boundary not established)
Announced investment
$2 billionAnnounced figure; whether it covers one building, a campus or a multi-phase program is not established.
Community response
Provider label: contestedCompute Atlas characterization, not a DataCenterData assessment. Open cited source →
AI-use label (provider)
mixed useCompute Atlas classification, not a DataCenterData finding.
Announced
July 2025Provider-reported announcement date.

Provider notes

Energy. Phase 1: 49MW PG&E grid connection. Potential 50MW Battery Energy Storage System (BESS) on-site. Phase 2 adds a second 218,000 sq ft building with alternative backup power solutions. Total planned capacity ~98MW across both phases.

Water. Final EIR-certified use is 23 acre-feet/year total (~7.49 million gallons/yr) at full build-out — 18 AFY for cooling (~0.016 MGD), 3 AFY landscaping, 2 AFY domestic (FEIR p.186); drawn from Gilroy potable supply pending a recycled-water pipeline. Evaporative cooling is triggered only when outdoor temperature exceeds 83F (~3% of the year). Amazon's promotional figure of ~4 million gallons/yr (~36 households) is roughly half the FEIR-certified total and is disputed in a CEQA challenge; Amazon says it aims for 100% reclaimed cooling water by 2030.

Community. Organized resident opposition active. Concerns cited: utility cost spikes, noise, fire and explosion risk from large-scale lithium BESS, and objection to AI use. An appeal was filed July 21, 2025, subsequently withdrawn August 18, 2025. Opponents requested Amazon guarantee the facility would not be used exclusively for AI workloads.

What the source record says

Status updated to under_construction: grading permit issued December 11, 2025; building permit issued March 19, 2026; City of Gilroy lists project as Under Construction as of July 2026. Site at 8050 Camino Arroyo in east Gilroy along Hwy 101. Full build-out: 438,000 sq ft across 56 acres. Amazon cites a ~$2 billion investment for the Gilroy project (recorded as investmentUsd); its broader Northern California investment of ~$5.1B and ~1,890 jobs since 2009 is regional and not attributable to this site. The 2020 land purchase was $31.3M. Operational job figures conflict and are unconfirmed: the FEIR says employment 'may grow to 50 full-time employees' (a ceiling), the permit application lists 25, and Amazon's promotional materials cite ~90 on-site; the construction workforce is not disclosed.

Capacity is not ranked or totaled here.

Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.

Status history supplied by the source

  1. 2020-11 · source-reported proposed

    Permit application initially received by City of Gilroy; Amazon purchased 56-acre site for $31.3M in 2020

    Open cited source →

  2. 2025-07 · source-reported permitted

    Gilroy Community Development Director Sharon Goei approved Phase 1 (218,000 sq ft building, 49MW PG&E connection) on July 3, 2025; appeal filed July 21, 2025, withdrawn August 18, 2025

    Open cited source →

  3. 2026-03 · source-reported under construction

    Grading permit issued December 11, 2025; building permit issued March 19, 2026; City of Gilroy project listing shows status as Under Construction

    Open cited source →

Sources and attribution

These sources are listed for the whole row. Unless a figure links to its own source, the provider does not mark which one gave it, so a figure may not appear in every source.

Adapted from Compute Atlas by Edward Kubiak, edition 1.34.1, under CC BY 4.0. Upstream ID amazon-gilroy-ca. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added. Some locations in this layer are reported by the provider as derived from OpenStreetMap (© OpenStreetMap contributors, ODbL, https://www.openstreetmap.org/copyright) and Epoch AI (CC BY 4.0).

Compute Atlas 1.34.1 with retained prior rows and publication holds. This is a DataCenterData composite, not an unmodified publisher edition. This row uses the captured source from 1.34.1, source as of 2026-10-14T20:40:52.293Z.

No reviewed record is linked to this row yet.

That does not mean the row is wrong, and it does not mean no reviewed record exists for the same place. A link is added only when an identifier or source establishes the match.

Recorded information

What this page records, grouped by topic, with the source's units and qualifications. Company-reported values stay labeled as company-reported. Related listings are shown separately.

Licensed directory listing dcd-dir-000064

Licensed directory row. Licensed directory label. Source-reported and not independently verified.

Provider notes and the source narrative are printed on this page and are not repeated here.

Identity and relationships

  • Provider facility type: data center

    Provider facility type.

  • AI-use label (provider): mixed use

    Compute Atlas classification, not a DataCenterData finding.

Location and precision

  • 8050 Camino Arroyo, Gilroy, CA 95020 · Santa Clara (Exact location)

Roles

  • Operator: Amazon Web Services

    Operator label as published by the provider; no parent company is inferred.

Lifecycle

  • Source-stated status: source-reported under construction

    Provider status label; not a DataCenterData finding that the facility is operating.

  • Announced: July 2025

    Provider-reported announcement date.

  • Status history: 2020-11 · source-reported proposed

    Status history supplied by the source.

  • Status history: 2025-07 · source-reported permitted

    Status history supplied by the source.

  • Status history: 2026-03 · source-reported under construction

    Status history supplied by the source.

Area, acreage and buildings

  • Land area: 56 acres (source-reported; parcel boundary not established)

Power capacity

  • Reported capacity: Planned: 98 MW (source-reported; boundary not independently verified; MW measure not stated by provider)

    Reproduced as the page prints it; not ranked or totaled; unknown is not zero.

  • Electric utility: Pacific Gas & Electric (PG&E)

    Utility as named by the provider.

  • Power source: Grid

    Provider label.

Cooling, water, PUE and WUE

  • Cooling: Hybrid

    Provider label.

  • Reported water use: 0.016 million gallons per day (source-reported)

    Whether this is metered use, a permit limit or a request is not established; see the provider water note.

Permits, incentives, jobs and proceedings

  • Announced investment: $2 billion

    Announced figure; whether it covers one building, a campus or a multi-phase program is not established.

  • Community response: Provider label: contested

    Compute Atlas characterization, not a DataCenterData assessment.

Sources, dates, limitations and corrections

  • Provider update date: 2026-09-14

    Provider update date is not a DataCenterData verification date.

Not yet recorded here: Connectivity · Services · Certifications and design ratings · Rack density · Availability · Specification links and contact.

Licensed values: adapted from Compute Atlas by Edward Kubiak under CC BY 4.0. Source-reported and not independently verified.

Update this profile with a public source. The request includes topics needing more information; this does not mean the facility lacks them. Corrections and additions are reviewed before publication.

Corrections

Report an error in this row →