Oregon index · last changed 16 September 2026

Oregon data centers: what the public record shows.

Selected source-linked records are published below. This is not a complete inventory of Oregon data centers.

13 sourced policy records for Oregon ↓Facility register: 52 records · by county →1 published DataCenterData record · evidence status shown per row50 licensed directory leads · not independently verifiedThese counts overlap and are not added together

Explore Oregon

Map, listings and checked facts.

Start with 50 licensed source leads, then inspect the separate public-evidence layer below. Licensed rows are not independently verified and are not a statewide census.

Oregon map

Reported locations in Oregon

50 licensed rows · 14 source localities · 4 map targets

Open interactive map
Source-reported points; some are approximate. Not parcel boundaries. Exact Approximate or representative Bounded nearby groupA number on a marker is the count of licensed rows it holds.Licensed layer only (Compute Atlas, source data through 14 October 2026). The interactive map lists 76 data-center source listings here across licensed, operator and DataCenterData layers (51 with a map point); 80 with government registry records. Source listings are not distinct sites.3 symbols are offset slightly for readability; thin connectors retain their projected anchors. Open the interactive map for source coordinates.
Browse 4 mapped areas as links
Map sources and method

The state outline is adapted from the U.S. Census Bureau 2025 cartographic boundary file. Facility coordinates are adapted from Compute Atlas by Edward Kubiak, edition 1.34.1, under CC BY 4.0. Outline and markers use one geographic projection before any explicitly disclosed readability offset. Exact singleton source anchors are never moved. A one-kilometre boundary tolerance prevents the simplified 1:20,000,000 outline from hiding legitimate border-area source points; farther conflicts are disclosed, not clamped. DataCenterData groups source-reported city coordinates only within a bounded map radius; the outline does not validate a facility record. Some locations in this layer are reported by the provider as derived from OpenStreetMap (© OpenStreetMap contributors, ODbL, https://www.openstreetmap.org/copyright) and Epoch AI (CC BY 4.0).

50 licensed rows14 reported city labels26 eligible organization labels

Browse all 50 rows below. Licensed rows are not independently verified and remain separate from the checked public-evidence layer.

  1. source-reported operationalCapacity not established; source review excludes the published figureSource updated 14 October 2026approximate location
  2. source-reported operationalCapacity not statedSource updated 2 September 2026exact location (provider label)

Separate layer

Also listed by operators

Sites that operators list on their own websites and that are not rows in the licensed directory above. They are kept apart and never added to the licensed rows.

9 operator-listed sites (mixed units; not added to licensed rows) in Oregon →

8 of these sites have no supported coordinate. The map does not invent a pin or a metro placement for them.

Oregon evidence at a glance

A few checked sites

Selected public evidence, not a statewide census. Each row shows whether it is independently source-linked, attributed, or unresolved; licensed leads remain separate.

Published project / campus
1
Published facility / building
0
Attributed or unresolved rows
0
Licensed directory leads
50 not independently verified
Capacity boundary stated
0 of 1 published DataCenterData rows
Review timing
Audit through 12 September 2026 · next 11 March 2027
Known coverage gap

No current Oregon Department of Revenue enterprise zone or SIP annual report was located; the Business Oregon project list read here is from 2019 and the SIP worksheet from 2023.

Browse all 50 Oregon licensed leads → · Why these counts differ →

Campuses

1 campus record. Names are as they appear on each record page.

Campuses published for Oregon
Record / rolesStatusCapacity / scalePrimary evidence
Meta Prineville Data CenterOperator: Meta Platforms, Inc. operatingcampus UnknownNo independently supported figure Business Oregon currently tax-exempt energy projects and data centers →Gov. record

Where the records were checked

Statewide audit pending

A few checked sites

This is not a list of every data center in the state, and the number here is not a count of them. There are almost certainly more.

Statewide coverage is not complete. The records below are sourced; a full statewide count has not been published.

State research audit window ended 12 September 2026. Individual records and claims below show their own evidence dates and may be newer.

Next scheduled coverage review: 11 March 2027.

1 independently source-linked project/campus record; 0 independently source-linked facility/building records; 0 attributed or unresolved rows. These counts use different units and must not be added together.

Source families checked, selected records and remaining gaps

These notes name selected records, say which kinds of public evidence were checked and show what remains missing. They do not add anything to the published counts.

Local evidence by place

Licensed and operator listings, reviewed records, answers and local policy for each place. Listings overlap and are not added; a place without a line here has no published local evidence.

No local evidence answer, reviewed record or local policy record is published for Arlington, Beaverton, Bend, Boardman, Boardman area (Tower Road), Forest Grove, Hermiston, Portland, The Dalles, Umatilla. Their listings above are source listings to investigate. No statewide evidence answer is published for Oregon either; statewide and utility-territory rules are under Policy tracker below.

Policy tracker

Oregon policy records

13 sourced records are associated with this state context. They are grouped below as current, pending and nonbinding, and history, and each card shows its relevant date. These are not facility counts and do not cover every locality.

Current 8 records

Recorded as in effect on the dataset date. This does not mean every project in a represented state is restricted or approved.

Enacted legislation or regulation

PGE large-load tariff compliance approval

In effect · Portland General Electric service territory in Oregon · State

Source document: 10 July 2026

Issuing authority: Oregon Public Utility Commission

Order No. 26-239, entered 10 July 2026, approves Portland General Electric's Advice No. 26-24 compliance filing, including the stated errata, which updates rate schedules and rules in response to Order No. 26-154.

Read the sourced record · Primary source

Enacted legislation or regulation

PGE Schedule 496 Data Center Cost-of-Service Opt-Out (20,000 kW and above)

In effect · Portland General Electric service territory, Oregon · Utility territory

Effective: 8 July 2026

Issuing authority: Portland General Electric Company

Portland General Electric's Schedule 496 is a data-center-specific tariff schedule for facilities of 20,000 kW or more whose end use is a data center, covering service for data center customers that opt out of cost-of-service pricing.

Read the sourced record · Primary source

Enacted legislation or regulation

PGE Schedule 596 Data Center Direct Access Service (20,000 kW and above)

In effect · Portland General Electric service territory, Oregon · Utility territory

Effective: 8 July 2026

Issuing authority: Portland General Electric Company

Portland General Electric's Schedule 596 is a data-center-specific tariff schedule for facilities of 20,000 kW or more whose end use is a data center, covering direct access service for data center customers.

Read the sourced record · Primary source

Enacted legislation or regulation

PGE Schedule 96 Data Center Standard Service (20,000 kW and above)

In effect · Portland General Electric service territory, Oregon · Utility territory

Effective: 8 July 2026

Issuing authority: Portland General Electric Company

Portland General Electric's Schedule 96 is a data-center-specific tariff schedule for facilities of 20,000 kW or more whose end use is a data center, covering standard (cost-of-service) electric service.

Read the sourced record · Primary source

Enacted legislation or regulation

POWER Act: separate rate class for 20 MW+ large energy use facilities (data centers)

In effect · Oregon · State

Effective: 16 June 2025

Issuing authority: Oregon Legislative Assembly

Oregon House Bill 3546 (2025), the POWER Act, requires the Public Utility Commission to create a separate electricity rate class for large energy use facilities of 20 megawatts or more that are primarily engaged in the data processing and hosting services of NAICS code 518210, with tariffs that assign the costs of serving them to that class and contracts of at least 10 years.

Read the sourced record · Primary source

Pending or nonbinding 3 records

Adopted measures with unverified effect, adopted future measures, open proceedings, proposals, drafts and nonbinding context stay separate from current rules.

Incentive or explicitly supportive policy

DEQ streamlined air permit path for data centers with Tier 4-level backup engines

Informational—not binding · Oregon · State

Last checked: 23 September 2026

Issuing authority: Oregon Department of Environmental Quality

Oregon's Department of Environmental Quality offers data centers a faster air-permit process if all critical-load backup diesel engines are Tier 2 certified and fitted with controls such as selective catalytic reduction and diesel particulate filters so that they operate at Tier 4 emission levels.

Read the sourced record · Primary source

Incentive or explicitly supportive policy

Governor's Data Center Advisory Committee (recommendations pending)

Informational—not binding · Oregon · State

Last checked: 23 September 2026

Issuing authority: Office of the Governor of Oregon (Oregon Department of Energy, host)

Governor Tina Kotek convened the Oregon Data Center Advisory Committee to recommend a statewide regulatory framework for data center development that pursues economic development while keeping utility costs, infrastructure investments and environmental impacts sustainable.

Read the sourced record · Primary source

History 2 records

Expired, repealed, vetoed, failed, blocked, superseded and completed measures remain visible without being presented as current.

Legislation introduced (any outcome)

HB 3698 (2025) data center water/electricity reporting and generator emissions (did not pass)

Did not pass · Oregon · State

Ended: 27 June 2025

Issuing authority: Oregon Legislative Assembly

Oregon HB 3698 (2025) would have required data centers to report quarterly water and electricity use to state agencies, with public summaries, and would have directed the Environmental Quality Commission to set emissions standards for data center standby generators.

Read the sourced record · Primary source

Open the Oregon policy comparison

Review dates: the 13 Oregon records were last checked 22 September 2026 to 3 November 2026. 7 scheduled reviews are overdue as of the tracker date 3 November 2026: PGE large-load tariff compliance approval, PGE Schedule 496 Data Center Cost-of-Service Opt-Out (20,000 kW and above), DEQ streamlined air permit path for data centers with Tier 4-level backup engines, Governor's Data Center Advisory Committee (recommendations pending), PUC POWER Act biennial report on data center load (2026) (last checked 23 September 2026, review due 23 October 2026); Enterprise-zone limits for data centers (last checked 2 October 2026, review due 30 October 2026); PGE data-center cost-allocation order (last checked 22 September 2026, review due 22 October 2026). Overdue means not re-read yet, not changed. No single record, and not this list, establishes complete statewide policy coverage.