Scope
Portland General Electric tariff Schedule 496 (P.U.C. Oregon No. E-19), Data Center Cost-of-Service Opt-Out (Facilities of 20,000 kW or more), sets terms and rates for service for data center customers that opt out of cost-of-service pricing to facilities whose end use is a data center, applying to Large Nonresidential Customers of 20,000 kW or more engaged in data center services (NAICS code 518210) or landlords of such tenants, including individually metered tenants on data center campuses whose aggregated site meets the threshold. The sheets were issued under Advice No. 26-24 and are effective for service on and after 8 July 2026 in PGE's service territory.
- Geographic scope
- Portland General Electric service territory, Oregon
- Jurisdiction
- Utility territory
- Authority type
- Utility
- Issuing authority
- Portland General Electric Company
Dates
- Adopted
- No adoption day is recorded
- Effective
- 8 July 2026
- Scheduled expiration
- See completion condition
- Ended
- Not recorded as ended
- Completion condition
- The schedule states no expiration.
- Source document
- 30 June 2026
- Last checked
- 23 September 2026 (earlier than tracker date 5 October 2026; not an automatic status change)
Summary
Portland General Electric's Schedule 496 is a data-center-specific tariff schedule for facilities of 20,000 kW or more whose end use is a data center, covering service for data center customers that opt out of cost-of-service pricing. It took effect for service on and after 8 July 2026 under Advice No. 26-24, which the Oregon Public Utility Commission approved in Order No. 26-239 following Order No. 26-154. It applies only in PGE's Oregon service territory.
What this does not establish
- This is a utility tariff schedule, not a statute; the Commission orders that required and approved it are separate records (or-puc-order-26-154-pge-large-load, or-puc-order-26-239-pge-tariff-approval).
- The schedule sheets carry issue dates of 3 June 2026 and 30 June 2026; the later date is stored as the document date.
- Rates and charges are not restated.
- Companion data-center Schedules 96, 496 and 596 are recorded separately; Schedule 696 (New Large Load Data Center Cost-of-Service Opt-Out) is not recorded here.
Unresolved questions
None recorded.
Relationships
Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.
- Related, not a replacement PGE Schedule 96 Data Center Standard Service (20,000 kW and above) (In effect)
- Related, not a replacement PGE Schedule 596 Data Center Direct Access Service (20,000 kW and above) (In effect)
- Related, not a replacement PGE data-center cost-allocation order (In effect)
- Related, not a replacement PGE large-load tariff compliance approval (In effect)
Sources
https://assets.ctfassets.net/416ywc1laqmd/4G5Cjkm6exKc90QwoNWs6U/15a50a55698518518cf13695dcfe785a/Sched_496.pdf
- PGE tariff index (page data) official index listing the schedule and its file