Summary
Order No. 26-239, entered 10 July 2026, approves Portland General Electric's Advice No. 26-24 compliance filing, including the stated errata, which updates rate schedules and rules in response to Order No. 26-154. The order says the decision was made and effective at the 7 July 2026 public meeting. Its stamp says the order was made, entered, and effective on 10 July 2026. The staff report attached to the order lists 8 July 2026 as an effective date. Because the opened order uses all three dates, this record does not store one of them as the only effective day. The approval implements the May order. It does not replace that order, and it does not say an operating data center must close.
Scope
Oregon Public Utility Commission Order No. 26-239, entered 10 July 2026 in docket UM 2377, approves Portland General Electric Advice No. 26-24, including the errata filed 30 June 2026 and 2 July 2026, updating rate schedules and rules in response to Order No. 26-154. The order says the decision was made and effective at the 7 July 2026 public meeting and that the written order was made, entered, and effective on 10 July 2026. The attached staff report lists an effective date of 8 July 2026. This record does not choose among those three dates. The order does not say it repeals Order No. 26-154, and it does not order a data center to stop operating.
- Geographic scope
- Portland General Electric service territory in Oregon
- Jurisdiction
- State
- Authority type
- Regulator or commission
- Issuing authority
- Oregon Public Utility Commission
Dates
- Adopted
- No adoption day is recorded
- Effective
- Several dates apply; see the source
- Scheduled expiration
- See completion condition
- Ended
- Not recorded as ended
- Completion condition
- The order approves the compliance filing. It states no expiration. Order No. 26-154 remains the directive that required the filing.
- Source document
- 10 July 2026
- Last checked
- 23 September 2026
About this date
This record was last checked before the tracker date, 11 November 2026. An earlier check date does not by itself mean the record's status has changed.
What this does not establish
- The order, the meeting narrative, and the staff report do not use the same effective day. None of 7, 8, or 10 July 2026 is stored as the sole effective date.
- The approved tariff sheets' megawatt thresholds and contract terms were not copied out of Advice No. 26-24 in this review.
- This order does not supersede Order No. 26-154. It approves the filing that order required.
- A commission press release describing Schedule 96 and a surcharge was not used as the legal text.
Unresolved questions
- Which of the three stated dates is the tariff's legal effective day was not resolved by a later errata.
- Pacific Power's separate compliance case was not decided by this order.
Relationships
Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.
- Related, not a replacement PGE data-center cost-allocation order (In effect)
- Related, not a replacement PGE Schedule 96 Data Center Standard Service (20,000 kW and above) (In effect)
- Related, not a replacement PGE Schedule 496 Data Center Cost-of-Service Opt-Out (20,000 kW and above) (In effect)
- Related, not a replacement PGE Schedule 596 Data Center Direct Access Service (20,000 kW and above) (In effect)
Sources
Primary source: Oregon Public Utility Commission page on apps.puc.state.or.us
- Oregon PUC Order No. 26-154 — earlier order that required the compliance filing approved here · 7 May 2026