Plain-English guide · Power

A megawatt of what?

Data-center announcements and filings quote megawatts, but a megawatt figure can describe very different things. Here are real figures from public records, each placed on the part of a site it describes.

The short answer

A megawatt figure may be a utility contract, the size of a substation, the power planned for computing, permitted backup generators, a proposed power plant or a solar deal somewhere else. These measure different things, for different parts of a site, at different stages. None of these figures, by itself, establishes how much electricity a site actually uses. A figure can be accurate and still be misread; this page is about what each kind establishes.

Going to a meeting? Ask of any figure: What does it measure? Which part of the site? What stage is it at? Is it a maximum, a design figure or an average? Who said it, and when? When would any generation run? The full questions →

Put a real figure on the picture

Illustration of a data-center site, not to scale. Solar panels stand on a separate plot elsewhere on the grid. Power lines reach a fenced substation, pass a meter and enter an open-topped building, where electrical rooms feed rows of computing racks and a cooling plant behind. Backup generators stand beside the building, and a generating plant at or near the site stands behind it.
PowerStandby
A contract elsewhere · B grid connection · C substation · D meter · E computing · F cooling and support · G backup generators · H generation at or near the site

Illustration, not a particular facility and not any company’s drawing, and not to scale. It shows where each kind of figure belongs; it does not depict the selected project. Equipment and combinations vary by site. Arrows show direction, not measured amounts.

Project Cannoli, Van Buren Township, Michigan

Utility testimony · Testimony in MPSC Case U-22058 (filing date not printed) · Checked 21 September 2026 · A common reading, tested · Site’s answer on that reading, not on the company: Contradicted

Reading tested: Treating DTE Electric's 1,000 MW Google contract as current measured load or critical IT capacity.

On the picture
Measures B, the grid connection.
What it measures
“the maximum load at the facility is 1,000 MW”, also called “contract capacity”.
Stage
“planned to begin materializing in December 2027, with max load achieved by December 2028”. It is “prefiled testimony, not an MPSC order, measured load, a stated critical IT capacity, or generation”.
Why it matters anyway
Minimum charges can be based on contract capacity even when actual use is lower. The utility’s testimony says “even if actual usage never reaches the 1,000 MW contract capacity, minimum monthly charges are calculated from that contract capacity”.
Not known from this record
MPSC final disposition of U-22058; whether load has materialized; measured load; critical IT capacity; executed public (non-confidential) contract text.

Read the full checked answer →
Original source: Qualifications and Public Direct Testimony of Neal T. Foley, DTE Electric Company, MPSC Case U-22058

Gilroy Data Center, California (AWS is the applicant)

City statement · Page date not stated · Checked 21 September 2026 · Site’s answer: Supported

Phase I of the Gilroy Data Center requires a 49 MW connection to PG&E.

On the picture
Measures B, the grid connection.
What it measures
A “city-stated Phase I utility-connection requirement”.
Which part
Phase I only. “the page does not state critical IT capacity, a campus-wide design capacity, or measured load”.
Stage
The city lists the project as “under construction”. “A building permit is permission to build, not opening or operation.”
Not known from this record
Critical IT capacity, measured load and the actual opening date.

Read the full checked answer →
Original source: Gilroy Data Center (by Amazon Web Services) — AS 20-23

Vantage, Fredericksburg, Virginia

Company web page · Page date not stated · Checked 1 October 2026 · Site’s answer: Company claim

Vantage says the Fredericksburg campus will have a private 270 MW on-site substation.

On the picture
Measures C, the substation and E, computing.
What they measure
Two figures from one page. “The 270 MW figure is the stated substation size. The page's 192 MW figure is combined critical IT load.” The 192 MW is a planned campus total.
Do they add?
No. A substation size and a computing load are different measurements of one campus, not two blocks of power. Subtracting them gives 78 MW, but that arithmetic alone does not show missing power, support load or efficiency.
Stage
“substation described as planned”. “The page does not say the substation is operating or that 270 MW is IT capacity.”
Not known from this record
Whether the substation is built or energized, and any utility filing that states its capacity.

Read the full checked answer →
Original source: Vantage Data Centers, Fredericksburg VA4 campus page
The 192 MW figure has its own checked answer: see that answer (Company claim) →

Polaris Forge 2, North Dakota

Company filing with the SEC · SEC filing dated 8 April 2026 · Project record, status: construction

200 MW: critical IT load

On the picture
Measures E, computing.
What it measures
“contracted future critical IT load, not current or measured load, utility-service capacity or an entire future-campus total”.
Which part
“phased across the initial two buildings”, not the whole planned campus.
Not known from this record
Current or measured load, utility-service capacity and the future-campus total.

Read the full project record →
Original source: Applied Digital Form 10-Q for the quarter ended February 28, 2026

Intergate Quincy (Sabey), Washington

State air-quality approval · Approval dated 6 April 2026 · Project record, status: operating

248.1 MW: permitted backup generation

On the picture
Measures G, backup generators.
What it measures
“Combined permitted emergency-generator capacity; not IT load or utility demand.”
Which part
The whole campus, stated as “up to” this figure.
Why it matters anyway
This permitted generator total shows what emergency equipment is approved, which is why it appears in an air-quality record. It does not show what the site draws day to day.
Not known from this record
Critical IT capacity, utility service capacity and measured load.

Read the full project record →
Original source: Washington Ecology Approval Order 26AQ-E016 and technical support document

Project Jupiter, Doña Ana County, New Mexico

State hearing notice · Notice filed 12 August 2026 · Checked 21 September 2026 · A common reading, tested · Site’s answer on that reading, not on the company: Contradicted

Reading tested: Treating the requested 2,462 MW YGI Microgrid as issued generation capacity or data-center IT load.

On the picture
Measures H, generation at or near the site.
What it measures
Planned “solid-oxide fuel cells to generate 2,462 MW to power a nearby data center”. The record says “nearby”; the exact relationship to the site is not established.
Stage
“2,462 MW is requested generation in a pending air-permit application. It is not issued capacity, not utility demand, and not data-center IT load.”
When checked
The proceeding was stayed by the state Supreme Court before the scheduled September hearing. A newspaper later “reported on September 17, 2026 that the Court lifted the stay”. “This check found no hearing outcome, secretary's order, or issued permit.”
Not known from this record
Rescheduled hearing date and outcome; whether NSR 10883 is later issued, denied, or withdrawn; data-center IT load; utility demand.

Read the full checked answer →
Original source: Amended Notice of Public Hearing — Yucca Growth Infrastructure, LLC, YGI Microgrid, AQB 26-57(P), NSR 10883

Meta, Lebanon, Indiana

Company statement · Said on 11 February 2026 · Checked 11 September 2026 · Site’s answer: Company claim

1 GW designed capacity

On the picture
Possible readings the record does not settle: B, a utility service; E, computing; or E and F together.
What it measures
“1 GW designed capacity”. This record does not say whether that means computing, computing plus support, or a utility service, so the figure sits off the equipment here.
Stage
A second record on this site says the reviewed sources “do not establish current metered load, a completed buildout or a comparable utility-service commitment”.
Not known from this record
Contracted, energized and measured load.

Read the full checked answer →
Original source: Company statement
Reading this as current measured grid demand is tested separately: see that answer (Contradicted) →

TotalEnergies and Google, Texas

Company news release · Said on 9 February 2026 · Checked 1 October 2026 · Site’s answer: Company claim

TotalEnergies signed two long-term power purchase agreements for 1 GW of solar capacity, described as 28 TWh over 15 years, from Wichita and Mustang Creek in Texas.

On the picture
Measures A, a contract elsewhere.
What it measures
Solar nameplate capacity under contract: “1 GW of solar capacity, equivalent to 28 TWh of renewable electricity over 15 years”.
Which part
No particular data-center building or IT load is identified. “The page does not name a data-center building, an IT capacity, or hourly matching.”
Capacity is not output
Arithmetic from those two numbers: 1 GW running flat out for 15 years would be about 131 TWh, and 28 TWh is about a fifth of that. Solar panels do not generate at night, so continuous output at nameplate is only a hypothetical comparison. This does not establish actual generation.
Stage
“A company announcement of an agreement is not a record that the electricity has been generated.”
Not known from this record
Whether the plants are built or the energy is generated. Which Google facility takes it. Hourly or physical matching. The contract text itself.

Read the full checked answer →
Original source: TotalEnergies news release, 9 February 2026

“Contradicted” on a tested reading means that reading of the figure does not hold; it is not a finding against the figure or the company. “Company claim” records what a company said, without a finding either way. Quotation marks show words from this site’s record of each figure, which may itself quote the source. This page relies on those records and does not review each company’s full documents.

One site can have several numbers at once

Why these project figures should not be added into a national total

Adding them would mix contracts, equipment, computing loads and plans, and these records are not a census. This site’s methodology says capacities of different kinds are never added together. This is what the capacity field of the 86 national project records holds today:

What the record’s figure isProject records
Utility request or connection3
Critical IT load2
Planned generation, including proposed backup6
Permitted backup generation2
Company design figure1
A figure whose kind is not established1
No value in the project capacity field71

An empty field is not a claim that a project is small, and some records mention other figures elsewhere. This table summarizes the project capacity field; it does not establish measured electricity use.

Power is not energy

A megawatt (MW) is a rate of power at a moment. A megawatt-hour (MWh) is energy used over time. The U.S. Energy Information Administration puts it this way: a generator with 1 MW of capacity that runs at that level for one hour produces 1 MWh, and “Many generators do not operate at full capacity all the time.” A request, capacity or rating is not an average draw. You can try the arithmetic in the guide’s calculator.

What each part of the picture is

Six questions to ask about any megawatt figure

  1. What does it measure: a request, a contract, equipment size, computing load, generation or actual use?
  2. Which part: one building, one phase, the campus, full build-out, or a separate generation project?
  3. What stage is it: requested, approved, permitted, built, running or measured?
  4. Is it a maximum (“up to”), a design figure, or an average?
  5. Who said it, in what document, and when?
  6. When would any generation run: regularly, intermittently, for testing or in emergencies? Would it also export to the grid?

Plain words

Go further on this site

How data centers work · Types of data center · Power answers · Project records

Sources for the definitions: U.S. Energy Information Administration, generation capacity and generation and measuring electricity, and this site’s guide. Each figure’s own sources are on its record. This is a general explanation, not a description of any facility on this site. Figures and counts are from this site’s records as built.