Power / timing · checked 11 September 2026

Reading Meta Lebanon's 1 GW design as current measured grid demand.

A verdict applies only to the wording shown.

Company claims are shown as stated; they are not findings.

Power / timing · IN · meta-lebanon

Contradicted

Common reading; no one is quoted

Checked 11 September 2026

Reading Meta Lebanon's 1 GW design as current measured grid demand.

What the evidence supports

Meta describes a 1 GW campus and reported a February 2026 groundbreaking. The reviewed sources do not establish current metered load, a completed buildout or a comparable utility-service commitment.

Still unknown

None recorded

Confidence: medium — Company; Institution · 1 sources

Open full claim →

Evidence details

  1. Meta Lebanon groundbreaking announcement → Company

    Exact location https://about.fb.com/news/2026/02/metas-new-data-center-lebanon-indiana-marks-milestone-ai-investment/

    What it supports This source is cited for the record as a whole; no narrower passage was recorded.

    Retrieved 11 September 2026

Counterevidence

None recorded.

Next check

None recorded

Data + actions

This claim as JSON →

Meta — Lebanon · Linked record

DataCenterData Meta Lebanon ledger · Related DataCenterData page

Suggest a correction → Claim ID meta-lebanon-current-gw and the page are prefilled. Accepted material corrections appear publicly on Changes.