Public statement checked
Answer
Verdict on the wording above: Company claim as of TotalEnergies release checked 2026-10-01 The only support is the company or its agents. Shown as stated, not adopted. Not a finding that it is true or false. How verdicts work →
- Who stated it
- Said by TotalEnergies · company statement in TotalEnergies news release · 9 February 2026 →
- What the evidence establishes
- TotalEnergies announced two Texas solar agreements totaling 1 GW of nameplate capacity, 805 MWp and 195 MWp, described as 28 TWh over 15 years, with construction scheduled to begin in the second quarter of 2026. That is contracted nameplate, not data-center IT load or a physical flow of electricity. Shown as the company's statement, not as a finding either way.
- Biggest limitation
- Whether the plants are built or the energy is generated. Which Google facility takes it. Hourly or physical matching. The contract text itself.
- Checked
- 1 October 2026 · Next review: A regulatory filing, generation record, or named receiving facility for these agreements
Evidence
What the evidence supports
The TotalEnergies page datelined Paris/Houston, 9 February 2026, says the company signed two long-term power purchase agreements to deliver 1 GW of solar capacity, equivalent to 28 TWh of renewable electricity over 15 years, for Google's data centers in Texas. It names Wichita at 805 MWp and Mustang Creek at 195 MWp, both under development, with construction scheduled to begin in the second quarter of 2026. Those construction jobs, described as several hundred, are for the solar farms. The page does not name a data-center building, an IT capacity, or hourly matching. A company announcement of an agreement is not a record that the electricity has been generated.
Still unknown
Whether the plants are built or the energy is generated. Which Google facility takes it. Hourly or physical matching. The contract text itself.
Sources
-
TotalEnergies news release, 9 February 2026 → Company
Exact location Lead paragraph: two long-term PPAs, 1 GW of solar capacity, 28 TWh over 15 years, Wichita 805 MWp and Mustang Creek 195 MWp, construction scheduled to begin in Q2 2026.
What it supports States the contracted solar nameplate, the energy-equivalent figure, the two projects, and the construction schedule. Not physical supply or IT capacity.
Review details
Scope
- Unit
- contracted solar nameplate
- Geography
- Wichita 805 MWp and Mustang Creek 195 MWp, Texas; purchaser described as Google data centers in Texas
- Period
- agreements announced 2026-02-09; construction stated to begin in the second quarter of 2026; 15-year term stated
- As of
- TotalEnergies release checked 2026-10-01
- Confidence
- medium — Company news release only. No regulatory contract filing or generation record reviewed.
- Kind
- Public statement checked
Conflicting evidence
None recorded when this claim was checked. That records what we logged, not a finding that no conflicting record exists.
Chronology
- Stated by TotalEnergies
- Published — TotalEnergies news release, 9 February 2026
- Source retrieved
- Checked by DataCenterData
- Date not established Next review: A regulatory filing, generation record, or named receiving facility for these agreements
Corrections and history
No corrections or wording changes recorded for this claim.