Documented fact
Answer
Verdict on the wording above: Supported as of Statute text captured 2026-11-06 Independent evidence supports the claim as stated, for the stated period. Not permanent; not proof of related claims. How verdicts work →
- Who stated it
- Said by Kansas Legislature (K.S.A. 66-101j) · government record in K.S.A. 66-101j, Kansas Office of the Revisor of Statutes →
- What the evidence establishes
- Kansas law lets the commission authorize utilities to discount standard electric rates for new or expanded commercial and industrial facilities, but K.S.A. 66-101j(c) says a facility that is a qualified data center is not eligible for that discount. That is one statutory route; the page does not say what rate a data center pays, and contract rates are outside the section.
- Biggest limitation
- The definition of qualified data center in K.S.A. 74-50,331 and its thresholds; whether any Kansas utility serves a data center under a commission-approved contract rate outside this section; what tariff or contract any named Kansas project, including the tracked Beale Data Center record, would take service under; and the 'cooperative' exclusion's effect on data centers served by cooperatives. No reviewed document in the sources checked establishes it.
- Checked
- 6 November 2026 · Next review: A change to K.S.A. 66-101j or 74-50,331, or a Kansas Corporation Commission order on a data-center rate or contract
Evidence
What the evidence supports
The Revisor page for K.S.A. 66-101j says the commission shall authorize an electric public utility to implement economic development rate schedules that provide discounts from standard rates for new or expanded facilities of industrial or commercial customers, subject to eligibility tests including local, regional, state or federal incentives and minimum peak demand. Subsection (c) says a customer is not eligible for the discount for any new or expanded facility that is a qualified data center as defined in K.S.A. 2025 Supp. 74-50,331. Subsection (f) states that revenue foregone through these discounts is not imputed into the utility's revenue requirement for discounts from July 1, 2024. Subsection (g) says the section does not apply to contract rates approved under K.S.A. 66-101i. The statute is cited for eligibility only: it does not state what a qualified data center pays, whether any data center has a contract rate, or any rate level. The 'qualified data center' definition in K.S.A. 74-50,331 was not read.
Still unknown
The definition of qualified data center in K.S.A. 74-50,331 and its thresholds; whether any Kansas utility serves a data center under a commission-approved contract rate outside this section; what tariff or contract any named Kansas project, including the tracked Beale Data Center record, would take service under; and the 'cooperative' exclusion's effect on data centers served by cooperatives. No reviewed document in the sources checked establishes it.
Sources
-
K.S.A. 66-101j, economic development rate schedules → Gov. record
Exact location Subsection (c); subsections (a), (f), (g); History line. Verbatim: "A customer shall not be eligible for the discount authorized by this section for any new or expanded facility that is a qualified data center as defined in K.S.A. 2025 Supp. 74-50,331" / "the commission shall authorize an electric public utility to implement economic development rate schedules that provide discounts from otherwise applicable standard rates" / "The provisions of this section shall not apply to rates for service provided to customers under contract rates approved by the commission pursuant to K.S.A. 2025 Supp. 66-101i"
What it supports The data-center exclusion from the discount, and its limits.
Review details
Scope
- Unit
- statutory eligibility for discounted electric rate schedules
- Geography
- Kansas electric public utilities (not cooperatives) and qualified data centers as defined in K.S.A. 74-50,331
- Period
- statute text as shown 2026-10-05; history shows L. 2025 ch. 124 effective July 1
- As of
- Statute text captured 2026-11-06
- Confidence
- high — Statute text read from the official Kansas Revisor page capture; limited to the text of subsection (c).
- Kind
- Documented fact
Conflicting evidence
None recorded when this claim was checked. That records what we logged, not a finding that no conflicting record exists.
Chronology
- Source retrieved
- Checked by DataCenterData
- Date not established Stated by Kansas Legislature (K.S.A. 66-101j) — statement date not established
- Date not established Next review: A change to K.S.A. 66-101j or 74-50,331, or a Kansas Corporation Commission order on a data-center rate or contract
Corrections and history
No corrections or wording changes recorded for this claim.
Data
Suggest a correction
Suggest a correction → Claim ID ks-data-centers-excluded-from-economic-development-rate-discount and this page are prefilled. Accepted material corrections appear publicly on Changes.