Licensed lead · not independently verified · dcd-dir-000085

Applied Digital Polaris Forge 1

source-reported operational

Applied Digital Corporation

Ellendale · Dickey County · North Dakota

Reported planned 400 MWReported operational 100 MWSource updated 10 October 2026approximate location · provider confidence label: confirmed
How to read this page

This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.

Reported geography

Source-reported location for Applied Digital Polaris Forge 1.

Approximate source coordinates; this is not a parcel claim. Nearby source points are combined into one accessible target that opens this exact map scope. View these exact rows on the interactive map →

Exact source coordinates Approximate or representative coordinates Nearby-point group. This relative plot uses only source-supplied points, makes no parcel claim and loads no map tiles.

Source row snapshot

Operator as published
Applied Digital Corporation
Address and locality
Ellendale · Dickey County · North Dakota
Official metro area
Outside an official metropolitan boundary
Source-reported status
operational
Provider facility type
data center
Reported capacity
Operational: 100 MW; Planned: 400 MW (source-reported; boundary not independently verified; MW measure not stated by provider)
Source freshness
10 October 2026
Location precision
approximate (provider label: exact; the provider's own note describes an approximate location)
Compute Atlas confidence label
confirmed (provider's classification; not a DataCenterData check)
Stable directory ID
dcd-dir-000085

Reported details

Source-reported by Compute Atlas; not independently verified by DataCenterData. Provider wording is kept; long provider notes are shortened and marked …; unknown is not zero; none of these values is totaled, ranked or compared.

Electric utility
Montana-Dakota UtilitiesUtility as named by the provider.
Power source
GridProvider label.
Cooling
Closed-loopProvider label.
Land area
320 acres (source-reported; parcel boundary not established)
Announced investment
$5.3 billionAnnounced figure; whether it covers one building, a campus or a multi-phase program is not established.
Community response
Provider label: supportedCompute Atlas characterization, not a DataCenterData assessment. Open cited source →
AI-use label (provider)
confirmedCompute Atlas classification, not a DataCenterData finding.
Announced
June 2025Provider-reported announcement date.

Provider notes

Energy. Designed for near-zero water consumption; proprietary closed-loop direct-to-chip liquid cooling; projected PUE 1.18; campus engineered to scale to 1 GW

Water. Proprietary waterless direct-to-chip liquid cooling; WUE near zero by design

Community. Ellendale (pop. ~1,000) has welcomed the campus as a transformative economic boost; the state's R-WISH rural-workforce housing program is funding new homes for incoming workers. No documented opposition or litigation. Coverage notes workforce and housing strain as growing pains.

Some source-reported values are held out of this page.

These reviews flag conflicting scope, inconsistent source text or support that has not been established. A withheld value may appear in the explanation, but is not displayed as an established field. The upstream row remains attributed under Sources.

  • Announced permanent jobs: The source note says local jobs are reported only as projections, not confirmed headcounts, so the permanent-jobs value is not established.
  • Announced construction jobs: The source note says local jobs are reported only as projections, not confirmed headcounts, so the construction-jobs value is not established.

What the source record says

Campus is 400 MW fully contracted to CoreWeave under ~15-year lease agreements valued at ~$11B total revenue. Three buildings: Building 1 (100 MW) complete Dec 2025; Building 2 (150 MW) expected mid-2026; Building 3 (150 MW) expected 2027. Coordinates are Ellendale city centroid; exact site is northeast of the city. Local jobs are reported only as projections — 'as many as 85 new jobs' (Dec 2024) and up to ~110 total local workforce at full expansion — not confirmed headcounts. No confirmed total campus capital-expenditure figure is public (the ~$11B CoreWeave figure is 15-year lease revenue, not capex); North Dakota's data-center sales-tax exemption applies but individual award amounts are statutorily confidential. investmentUsd reflects Applied Digital's own infrastructure spend (~$1.3B committed + ~$4B anticipated); the company's '$20B total campus' figure additionally counts ~$15B of customer/tenant capital.

Capacity is not ranked or totaled here.

Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.

Status history supplied by the source

  1. 2023 · source-reported under construction

    AI factory construction begins in Ellendale

  2. 2025-10 · source-reported operational

    Building 1 Phase 1 (50 MW) achieves Ready for Service for CoreWeave

    Open cited source →

  3. 2025-12 · source-reported under construction

    Building 1 fully operational at 100 MW; Buildings 2 (150 MW) and 3 (150 MW) under construction for CoreWeave

    Open cited source →

  4. 2026-10-10 · source-reported operational

    Campus has live, operational capacity and is no longer solely under construction: Building 1 (100MW) and Building 2 Phase 1 (75MW) have both reached Ready for Service, bringing total live critical IT load to 175MW against a fully-leased, 400MW CoreWeave build-out.

    Open cited source →

Sources and attribution

These sources are listed for the whole row. Unless a figure links to its own source, the provider does not mark which one gave it, so a figure may not appear in every source.

Adapted from Compute Atlas by Edward Kubiak, edition 1.34.1, under CC BY 4.0. Upstream ID applied-digital-polaris-forge-1-ellendale-nd. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added. Some locations in this layer are reported by the provider as derived from OpenStreetMap (© OpenStreetMap contributors, ODbL, https://www.openstreetmap.org/copyright) and Epoch AI (CC BY 4.0).

Compute Atlas 1.34.1 with retained prior rows and publication holds. This is a DataCenterData composite, not an unmodified publisher edition. This row uses the captured source from 1.34.1, source as of 2026-10-14T20:40:52.293Z.

Independently reviewed match

This exact source identifier is linked to Polaris Forge 1. The licensed row remains a separate discovery record.

Recorded information

What this page records, grouped by topic, with the source's units and qualifications. Company-reported values stay labeled as company-reported. Related listings are shown separately.

Licensed directory listing dcd-dir-000085

Licensed directory row. Licensed directory label. Source-reported and not independently verified.

Provider notes and the source narrative are printed on this page and are not repeated here.

Identity and relationships

  • Provider facility type: data center

    Provider facility type.

  • AI-use label (provider): confirmed

    Compute Atlas classification, not a DataCenterData finding.

Location and precision

  • Ellendale, ND · Dickey (Approximate location)

Roles

  • Operator: Applied Digital Corporation

    Operator label as published by the provider; no parent company is inferred.

Lifecycle

  • Source-stated status: source-reported operational

    Provider status label; not a DataCenterData finding that the facility is operating.

  • Announced: June 2025

    Provider-reported announcement date.

  • Status history: 2023 · source-reported under construction

    Status history supplied by the source.

  • Status history: 2025-10 · source-reported operational

    Status history supplied by the source.

  • Status history: 2025-12 · source-reported under construction

    Status history supplied by the source.

  • Status history: 2026-10-10 · source-reported operational

    Status history supplied by the source.

Area, acreage and buildings

  • Land area: 320 acres (source-reported; parcel boundary not established)

Power capacity

  • Reported capacity: Operational: 100 MW; Planned: 400 MW (source-reported; boundary not independently verified; MW measure not stated by provider)

    Reproduced as the page prints it; not ranked or totaled; unknown is not zero.

  • Electric utility: Montana-Dakota Utilities

    Utility as named by the provider.

  • Power source: Grid

    Provider label.

Cooling, water, PUE and WUE

  • Cooling: Closed-loop

    Provider label.

Permits, incentives, jobs and proceedings

  • Announced investment: $5.3 billion

    Announced figure; whether it covers one building, a campus or a multi-phase program is not established.

  • Community response: Provider label: supported

    Compute Atlas characterization, not a DataCenterData assessment.

Sources, dates, limitations and corrections

  • Provider update date: 2026-10-10

    Provider update date is not a DataCenterData verification date.

Not yet recorded here: Connectivity · Services · Certifications and design ratings · Rack density · Availability · Specification links and contact.

Licensed values: adapted from Compute Atlas by Edward Kubiak under CC BY 4.0. Source-reported and not independently verified.

Update this profile with a public source. The request includes topics needing more information; this does not mean the facility lacks them. Corrections and additions are reviewed before publication.

Corrections

Report an error in this row →