This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.
Reported geography
Source-reported location for Applied Digital Delta Forge 1 AI Factory Campus.
Exact source coordinates (provider label); this is not a parcel claim. Nearby source points are combined into one accessible target that opens this exact map scope. View these exact rows on the interactive map →
Source row snapshot
- Operator as published
- Applied Digital Corporation
- Address and locality
- Boyce · Rapides County · Louisiana
- Official metro area
- Alexandria, LA
- Source-reported status
- under construction
- Provider facility type
- data center
- Reported capacity
- Planned: 300 MW (source-reported; boundary not independently verified; MW measure not stated by provider)
- Source freshness
- 15 September 2026
- Location precision
- exact (provider label)
- Compute Atlas confidence label
- confirmed (provider's classification; not a DataCenterData check)
- Stable directory ID
dcd-dir-000083
The underlying provider record is retained. These notes add source-attributed context and flag conflicts; any withheld value is explained separately. They do not certify current operation.
- Source review · reviewed 2026-10-11: Prior source review (2026-10-09): Applied Digital’s April 23, 2026 filing announces approximately a 15-year lease for 300 MW of critical IT capacity at Delta Forge 1. This is contracted capacity for a project described as under construction, not measured or energized load. The 430 MW campus headline is a different measure and is not combined with the leased IT figure. Acreage reconciliation remains unresolved. Historical document addendum reviewed 2026-10-11: The England Economic and Industrial Development District's May 28, 2026 release states that Applied Digital entered into a payment-in-lieu-of-taxes agreement with the district. This adds local incentive context only; the executed agreement, payments received, land-use approval and operating status are not established by this release.
- Applied Digital Corporation (SEC Form 8-K, operator) — 2026-04-23 · source retrieved 2026-10-09
- England Economic and Industrial Development District — 2026-05-28 · source retrieved 2026-10-10
Reported details
Source-reported by Compute Atlas; not independently verified by DataCenterData. Provider wording is kept; long provider notes are shortened and marked …; unknown is not zero; none of these values is totaled, ranked or compared.
- Electric utility
- Cleco
- Power source
- Grid
- Cooling
- Closed-loop
- Land area
- 300 acres (source-reported; parcel boundary not established)
- Announced investment
- $3.6 billion
- Announced jobs
- 200 permanent · 1,000 construction
- AI-use label (provider)
- confirmed
- Announced
- May 2026
Incentives reported by the source
Whether each incentive was approved, awarded or received is not established.
- Louisiana Act 730 Sales and Use Tax Exemption on data center equipment · Louisiana · 2026 Open cited source →
Provider notes
Energy. Cleco pays full cost of power infrastructure needed to serve campus (called 'largest economic development opportunity in Cleco's 90-plus year history'). Campus located on 300 acres of a 672-acre secured site.
Water. Applied Digital proprietary closed-loop cooling technology for high-density AI workloads.
What the source record says
Anchor tenant is an undisclosed investment-grade U.S. hyperscaler under a $7.5B, 15-year lease. Two initial facilities totaling 300 MW across 300 acres (of 672-acre secured site). Initial operations targeted mid-2027. Applied Digital HQ in Dallas, TX.
Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.
Status history supplied by the source
- 2025-10 · source-reported proposed
Applied Digital begins site development in Rapides Parish with location kept confidential; signed $7.5B, 15-year lease with undisclosed investment-grade U.S. hyperscaler for 300 MW.
- 2026-01 · source-reported under construction
Site development begins January 2026. Location publicly revealed as Boyce, Rapides Parish in May 2026.
Sources and attribution
These sources are listed for the whole row. Unless a figure links to its own source, the provider does not mark which one gave it, so a figure may not appear in every source.
- Central Louisiana secures $3.6B Applied Digital AI Factory Campus · Louisiana Economic Development
- Rapides Parish lands massive $3.6B AI data center project · Rapides Parish Journal
- Cleco plans 756-MW gas plant alongside Rapides data center · The Hayride
- Cleco looks to fast-track new generator for data center · KALB
Adapted from Compute Atlas by Edward Kubiak, edition 1.34.1, under CC BY 4.0. Upstream ID applied-digital-delta-forge-1-la. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added. Some locations in this layer are reported by the provider as derived from OpenStreetMap (© OpenStreetMap contributors, ODbL, https://www.openstreetmap.org/copyright) and Epoch AI (CC BY 4.0).
Compute Atlas 1.34.1 with retained prior rows and publication holds. This is a DataCenterData composite, not an unmodified publisher edition. This row uses the captured source from 1.34.1, source as of 2026-10-14T20:40:52.293Z.
That does not mean the row is wrong, and it does not mean no reviewed record exists for the same place. A link is added only when an identifier or source establishes the match.
Recorded information
What this page records, grouped by topic, with the source's units and qualifications. Company-reported values stay labeled as company-reported. Related listings are shown separately.
Licensed directory listing dcd-dir-000083
Licensed directory row.
Provider notes and the source narrative are printed on this page and are not repeated here.
Identity and relationships
- Provider facility type: data center
Provider facility type.
- AI-use label (provider): confirmed
Compute Atlas classification, not a DataCenterData finding.
Location and precision
- Boyce, LA · Rapides (Exact location)
Roles
- Operator: Applied Digital Corporation
Operator label as published by the provider; no parent company is inferred.
Lifecycle
- Source-stated status: source-reported under construction
Provider status label; not a DataCenterData finding that the facility is operating.
- Announced: May 2026
Provider-reported announcement date.
- Status history: 2025-10 · source-reported proposed
Status history supplied by the source.
- Status history: 2026-01 · source-reported under construction
Status history supplied by the source.
Area, acreage and buildings
- Land area: 300 acres (source-reported; parcel boundary not established)
Power capacity
- Reported capacity: Planned: 300 MW (source-reported; boundary not independently verified; MW measure not stated by provider)
Reproduced as the page prints it; not ranked or totaled; unknown is not zero.
- Electric utility: Cleco
Utility as named by the provider.
- Power source: Grid
Provider label.
Cooling, water, PUE and WUE
- Cooling: Closed-loop
Provider label.
Permits, incentives, jobs and proceedings
- Announced investment: $3.6 billion
Announced figure; whether it covers one building, a campus or a multi-phase program is not established.
- Announced jobs: 200 permanent · 1,000 construction
Announced figures; whether they cover one building, a campus or a multi-phase program is not established.
- Incentive reported by the source: Louisiana Act 730 Sales and Use Tax Exemption on data center equipment · Louisiana · 2026
Whether the incentive was approved, awarded or received is not established.
Sources, dates, limitations and corrections
- Provider update date: 2026-09-15
Provider update date is not a DataCenterData verification date.
Not yet recorded here: Connectivity · Services · Certifications and design ratings · Rack density · Availability · Specification links and contact.