The reviewed utility order establishes Google Fort Wayne's cooling design and water use.
Limit: Cooling architecture, source water, and permitted or measured withdrawal, consumption, and discharge.
Claims · by topic
12 checked claims so far on this topic. Withdrawal, consumption, discharge, make-up water and avoided potable use remain separate measures. Not a census of water & cooling claims or of data centers. Cooling and water record set →
12 claims · newest check first
A verdict applies only to the wording shown.
Company claims are shown as stated; they are not findings.
Limit: Cooling architecture, source water, and permitted or measured withdrawal, consumption, and discharge.
Limit: Site-specific cooling design, cooling-water source, and measured data-center withdrawal, consumption, and discharge.
Limit: Cooling architecture, source water, and permitted or measured withdrawal, consumption, and discharge.
Limit: Operating configuration, initial-fill volume, other site water uses, and measured withdrawal, consumption,…
Limit: Actual annual withdrawal and consumption, potable and nonpotable shares…
Limit: Independent utility/meter corroboration;
Limit: Current measured withdrawal, consumption and discharge;
Limit: Independent utility/meter records;
Limit: Individual permits for named data-center outfalls were not inventoried.
Limit: Source water, permitted quantity, current metered withdrawal/consumption, and completion.
Limit: Permit quantity, current metered withdrawal/consumption, source-water mix and completion.
Limit: Operating configuration, total site water and measured consumption.
What this covers. 12 checked claims so far on this topic. They concern data-center projects in Indiana (6), Ohio (3), Oregon (1), Washington (1) and Wisconsin (1). That is because those are the water & cooling claims DataCenterData has checked, not a count of claims or of data centers. Where a state, operator, project or topic shows no checked claim, read it as “not yet checked by DataCenterData”.
What a verdict means. A verdict applies only to the wording shown and the evidence linked on the check date. “Unknown” means the reviewed evidence did not establish the point; it never means zero or false.
All 50 checked claims and what they cover → · Corrections log →