Documented fact
Answer
Verdict on the wording above: Not yet due as of City of Gilroy Data Center General Q&A page and fact sheet captured 2026-11-03 A commitment or projection whose trigger or deadline has not arrived. It cannot be graded yet and is not a failure. How verdicts work →
- Who stated it
- Said by the City of Gilroy · government record in Data Center General Q&A, Water Q&A · 12 August 2026 →
- What the evidence establishes
- The City of Gilroy estimates about 23 acre-feet a year of potable water in Phase 1, falling to about 2 after the required switch to recycled water. That is an estimate for a building not yet operating, and its trigger (Phase 1 completion and the recycled-water connection, expected by 2030) has not arrived. An undated City fact sheet gives 23 as the total at full buildout, and the City does not reconcile the two.
- Biggest limitation
- Whether the 23 acre-feet is a Phase 1 figure, as the Q&A says, or a full-buildout figure, as the fact sheet says; measured potable or recycled water use after opening; the recycled-water volume; the recycled-water agreements' terms and whether they were completed; the Water Supply Assessment (the page lists it as Appendix O of the environmental review, not read); and the conditions-of-approval text.
- Checked
- 3 November 2026 · Next review: Completed recycled-water agreements or connection, first-building occupancy, or metered potable and recycled water records
Evidence
What the evidence supports
The city's Water Q&A says the data center is expected to use approximately 23 acre-feet of potable water per year in Phase 1, compared with about 8,065 acre-feet used by the Gilroy community, and that within two years of completing Phase 1, or before Phase 2's first occupancy if sooner, it must transition industrial and irrigation water use to recycled water under the conditions of approval, after which potable use is estimated at 2 acre-feet per year. The same page says the project will use evaporative cooling for the current project, that cooling water is discharged to the sewer, that recycled-water agreements were expected to be completed in the fall of 2026 and that the connection is anticipated by 2030, and that the figures were updated to match the Environmental Review. These are the City's estimates and a condition of approval, for a building the city lists as expected online in 2028. They are potable water only: total water, recycled-water volume, wastewater and metered consumption are not stated. The City's undated fact sheet, linked from the project page, frames the figure differently: it says that at full buildout (phase I and II) the project's total potable water demand is up to 23 acre-feet per year, made up of 18 for cooling, 3 for landscaping and 2 for domestic purposes, and that recycled water comes at Phase II. The City does not reconcile the two statements.
Still unknown
Whether the 23 acre-feet is a Phase 1 figure, as the Q&A says, or a full-buildout figure, as the fact sheet says; measured potable or recycled water use after opening; the recycled-water volume; the recycled-water agreements' terms and whether they were completed; the Water Supply Assessment (the page lists it as Appendix O of the environmental review, not read); and the conditions-of-approval text.
Sources
-
Data Center General Q&A → Gov. record
Exact location Water Q&A: 'How much potable water will the data center use?'; 'When will the site begin using recycled water?'; 'Can the data center use a closed loop system?'. Verbatim: "Initially, in Phase 1, the data center is expected to use approximately 23 acre-feet of potable water per year" / "Within two years of completion of Phase 1, or before the first occupancy of Phase 2, whichever comes first, the data center is required to transition its industrial and irrigation water use to recycled water as part of the conditions of approval." / "its potable water use will decrease to an estimated 2 acre-feet per year" / "The AWS project will use evaporative cooling for the current project." / "The connection is anticipated to be completed by 2030."
What it supports City estimate of potable water, the recycled-water transition condition and the evaporative cooling design.
-
Gilroy Data Center Fact Sheet → Gov. record
Exact location Water Usage: 'Is 5 million gallons of water going to be used per day?'; 'Is recycled water going to be used?'. Verbatim: "No, at full buildout (phase I and II), the project’s total potable water demand is up to 23 acre-feet per year" / "Yes, at Phase II of the project."
What it supports City fact sheet's full-buildout framing of the 23 acre-feet and its cooling, landscaping and domestic breakdown.
Review details
Scope
- Unit
- estimated potable water (acre-feet per year)
- Geography
- Gilroy Data Center Phase 1 (Building 1), 8050 Camino Arroyo; potable water only
- Period
- Phase 1 estimate and post-recycled-water estimate; city Q&A updated 2026-08-12; first building expected online 2028
- As of
- City of Gilroy Data Center General Q&A page and fact sheet captured 2026-11-03
- Confidence
- medium — City-published estimate and condition of approval; the facility is not operating and the recycled-water switch has not occurred.
- Kind
- Documented fact
Conflicting evidence
None recorded when this claim was checked. That records what we logged, not a finding that no conflicting record exists.
Not yet due: the trigger is Completed recycled-water agreements or connection, first-building occupancy, or metered potable and recycled water records. It cannot be graded yet and is not a failure.
Chronology
- Stated by City of Gilroy
- Published — Data Center General Q&A
- 2 sources retrieved
- Checked by DataCenterData
- Date not established Next review: Completed recycled-water agreements or connection, first-building occupancy, or metered potable and recycled water records
Corrections and history
No corrections or wording changes recorded for this claim.