Recorded as in effect on the dataset date. This does not mean every project in a represented state is restricted or approved.
Enacted legislation or regulation
In effect · Maine · State
Effective: 29 July 2026
Issuing authority: Maine Legislature
Maine Public Law 2026, chapter 768, approved by the Governor on 23 April 2026, excludes property in data centers that begin operations on or after 1 August 2026, including later expansions, from the Business Equipment Tax Exemption and removes data center services from the Dirigo Business Incentives Program.
Read the sourced record · Primary source
Permanent restriction or prohibition · Brewer only (local rule)
In effect · Brewer, Maine · Local
Source document: 12 May 2026
Issuing authority: Brewer City Council
The Brewer City Council enacted Council Order 2026-C010 on 12 May 2026 as part of a unanimous consent-calendar vote.
Read the sourced record · Primary source
Enacted legislation or regulation
In effect · Maine · State
Last checked: 23 September 2026
Issuing authority: Governor of Maine
Maine Governor's Executive Order 5 of fiscal year 2025-26 directs the Department of Energy Resources to work with the Public Utilities Commission on strategies to protect ratepayers from data-center-driven energy costs and creates the Maine Data Center Advisory Council to evaluate large-scale data center issues and deliver a strategy report with any proposed legislation.
Read the sourced record · Primary source