Brewer, Maine

Brewer: tiered data center standards; 20 MW and over prohibited

Permanent restriction or prohibition · Brewer only (local rule)

In effect This instrument is recorded as currently in effect as of the dataset date.

Summary

The Brewer City Council enacted Council Order 2026-C010 on 12 May 2026 as part of a unanimous consent-calendar vote. The order adds data center use tiers to the city's land use code, requires off-lot water for every data center tier and major site plan review for Tier 2 and Tier 3, sets noise limits for generators and cooling equipment, and prohibits data centers of 20 megawatts and over. The minutes do not print a separate effective day, so none is stored.

Scope

Brewer Council Order 2026-C010 amends the Brewer land use code to add tiered data center uses, requires off-lot water for all three data center tiers and major site plan review for Tier 2 and Tier 3, sets generator and cooling noise limits, and provides that data centers of 20 megawatts and over are prohibited. It is a City of Brewer land use amendment and does not apply elsewhere in Maine.

Geographic scope
Brewer, Maine
Jurisdiction
Local
Authority type
Local government
Issuing authority
Brewer City Council

Dates

Adopted
12 May 2026
Effective
Effective date not stated in the source
Scheduled expiration
See completion condition
Ended
Not recorded as ended
Completion condition
The order states no expiration. The minutes print no separate effective day, so the adoption day is not stored as the legal effective day.
Source document
12 May 2026
Last checked
22 September 2026
About this date

This record was last checked before the tracker date, 16 November 2026. An earlier check date does not by itself mean the record's status has changed.

What this does not establish

  • The source is the official meeting minutes, which contain the order text and the vote; a separately signed order was not opened.
  • The minutes recite that Brewer orders generally take effect five days after passage; that rule was not used to store an effective day.
  • Maine's statewide proposal L.D. 307 is a separate instrument and did not become law.

Unresolved questions

None recorded.

Relationships

Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.

  • No related action is recorded.

Sources

Primary source: Brewer City Council page on brewermaine.gov

    Back to the policy tracker · Maine policy module