Licensed lead · not independently verified · dcd-dir-001443

TeraWulf Muskie Data Campus (EastPark)

source-reported proposed

TeraWulf

Ashland · Greenup County · Kentucky

Reported planned 1,000 MWSource updated 15 September 2026approximate location · provider confidence label: confirmed
How to read this page

This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.

Reported geography

Source-reported location for TeraWulf Muskie Data Campus (EastPark).

Approximate source coordinates; this is not a parcel claim. Nearby source points are combined into one accessible target that opens this exact map scope. View these exact rows on the interactive map →

Exact source coordinates Approximate or representative coordinates Nearby-point group. This relative plot uses only source-supplied points, makes no parcel claim and loads no map tiles.

Source row snapshot

Operator as published
TeraWulf
Address and locality
Ashland · Greenup County · Kentucky
Official metro area
Huntington-Ashland, WV-KY-OH
Source-reported status
proposed
Provider facility type
data center
Reported capacity
Planned: 1,000 MW (source-reported; boundary not independently verified; MW measure not stated by provider)
Source freshness
15 September 2026
Location precision
approximate (provider label: exact; the provider's own note describes an approximate location)
Compute Atlas confidence label
confirmed (provider's classification; not a DataCenterData check)
Stable directory ID
dcd-dir-001443

Reported details

Source-reported by Compute Atlas; not independently verified by DataCenterData. Provider wording is kept; long provider notes are shortened and marked …; unknown is not zero; none of these values is totaled, ranked or compared.

Electric utility
Kentucky Power (AEP)Utility as named by the provider.
Power source
GridProvider label.
Cooling
Not establishedProvider label: unknown.
Land area
285 acres (source-reported; parcel boundary not established)
Community response
Provider label: mixedCompute Atlas characterization, not a DataCenterData assessment.
AI-use label (provider)
confirmedCompute Atlas classification, not a DataCenterData finding.
Announced
26 May 2026Provider-reported announcement date.

Provider notes

Energy. Kentucky Power (an AEP company) is building a 345 kV substation on the existing 765 kV network to serve the campus. TeraWulf confirmed it will pay the full Industrial General Service tariff with no discounts or exemptions. Phased power: 500 MW H2 2028, +500 MW H2 2030.

Community. Boyd County Judge-Executive Eric Chaney and FIVCO-region officials are broadly supportive; the City of Ashland enacted a moratorium on new data-center applications within city limits (site is outside city limits). Tax revenue projected to benefit schools across the five FIVCO counties.

Some source-reported values are held out of this page.

These reviews flag conflicting scope, inconsistent source text or support that has not been established. A withheld value may appear in the explanation, but is not displayed as an established field. The upstream row remains attributed under Sources.

  • Announced permanent jobs: The source note says permanent jobs are official projections, not a reported headcount.

What the source record says

TeraWulf's second Kentucky campus (alongside the Justified/Hawesville campus tracked separately). TeraWulf (Nasdaq: WULF), historically a bitcoin miner, repositioning toward HPC/AI. Muskie is a 285-acre site at EastPark Industrial Park (a 1,000-acre former strip mine). Planned 1+ GW phased: initial 500 MW ramp H2 2028, additional 500 MW targeted H2 2030. County discrepancy: local TV cites Boyd County, but Wikipedia and the Lane Report place EastPark primarily in Greenup County (site straddles Boyd/Greenup/Carter); Greenup used, city Ashland retained as the regional reference. INVESTMENT OMITTED: the $4B figure came from a Boyd County official, not TeraWulf's investor PR or 8-K. ~300 permanent jobs are official projections (in notes, not jobs). TeraWulf stated it will pay the full standard industrial tariff with no subsidies. Coordinates are the EastPark park centroid.

Capacity is not ranked or totaled here.

Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.

Status history supplied by the source

  1. 2026-05-26 · source-reported proposed

    TeraWulf announced the acquisition of the 285-acre Muskie Data Campus from Industrial Equity Partners at EastPark Industrial Park; land purchase closed effective 2026-05-22

    Open cited source →

Sources and attribution

These sources are listed for the whole row. Unless a figure links to its own source, the provider does not mark which one gave it, so a figure may not appear in every source.

Adapted from Compute Atlas by Edward Kubiak, edition 1.34.1, under CC BY 4.0. Upstream ID terawulf-muskie-eastpark-ky. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added. Some locations in this layer are reported by the provider as derived from OpenStreetMap (© OpenStreetMap contributors, ODbL, https://www.openstreetmap.org/copyright) and Epoch AI (CC BY 4.0).

Compute Atlas 1.34.1 with retained prior rows and publication holds. This is a DataCenterData composite, not an unmodified publisher edition. This row uses the captured source from 1.34.1, source as of 2026-10-14T20:40:52.293Z.

No reviewed record is linked to this row yet.

That does not mean the row is wrong, and it does not mean no reviewed record exists for the same place. A link is added only when an identifier or source establishes the match.

Recorded information

What this page records, grouped by topic, with the source's units and qualifications. Company-reported values stay labeled as company-reported. Related listings are shown separately.

Licensed directory listing dcd-dir-001443

Licensed directory row. Licensed directory label. Source-reported and not independently verified.

Provider notes and the source narrative are printed on this page and are not repeated here.

Identity and relationships

  • Provider facility type: data center

    Provider facility type.

  • AI-use label (provider): confirmed

    Compute Atlas classification, not a DataCenterData finding.

Location and precision

  • Ashland, KY · Greenup (Approximate location)

Roles

  • Operator: TeraWulf

    Operator label as published by the provider; no parent company is inferred.

Lifecycle

  • Source-stated status: source-reported proposed

    Provider status label; not a DataCenterData finding that the facility is operating.

  • Announced: 26 May 2026

    Provider-reported announcement date.

  • Status history: 2026-05-26 · source-reported proposed

    Status history supplied by the source.

Area, acreage and buildings

  • Land area: 285 acres (source-reported; parcel boundary not established)

Power capacity

  • Reported capacity: Planned: 1,000 MW (source-reported; boundary not independently verified; MW measure not stated by provider)

    Reproduced as the page prints it; not ranked or totaled; unknown is not zero.

  • Electric utility: Kentucky Power (AEP)

    Utility as named by the provider.

  • Power source: Grid

    Provider label.

Cooling, water, PUE and WUE

  • Cooling: Not established

    Provider label: unknown.

Permits, incentives, jobs and proceedings

  • Community response: Provider label: mixed

    Compute Atlas characterization, not a DataCenterData assessment.

Sources, dates, limitations and corrections

  • Provider update date: 2026-09-15

    Provider update date is not a DataCenterData verification date.

Not yet recorded here: Connectivity · Services · Certifications and design ratings · Rack density · Availability · Specification links and contact.

Licensed values: adapted from Compute Atlas by Edward Kubiak under CC BY 4.0. Source-reported and not independently verified.

Update this profile with a public source. The request includes topics needing more information; this does not mean the facility lacks them. Corrections and additions are reviewed before publication.

Corrections

Report an error in this row →