TeraWulf Morgantown Generating Station AI Campus

source-reported proposed

TeraWulf

Charles County · Maryland

Reported planned 1,000 MWSource updated 10 September 2026approximate location · provider confidence label: confirmed
How to read this page

This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.

Reported geography

Source-reported location for TeraWulf Morgantown Generating Station AI Campus.

Approximate source coordinates; this is not a parcel claim. Nearby source points are combined into one accessible target that opens this exact map scope. View these exact rows on the interactive map →

Exact source coordinates Approximate or representative coordinates Nearby-point group. This relative plot uses only source-supplied points, makes no parcel claim and loads no map tiles.

Source row snapshot

Operator as published
TeraWulf
Address and locality
Charles County · Maryland
Official metro area
Outside an official metropolitan boundary
Source-reported status
proposed
Provider facility type
data center
Reported capacity
Planned: 1,000 MW (source-reported; boundary not independently verified; MW measure not stated by provider)
Source freshness
10 September 2026
Location precision
approximate (provider label: exact; the provider's own note describes an approximate location)
Compute Atlas confidence label
confirmed (provider's classification; not a DataCenterData check)
Stable directory ID
dcd-dir-001442

Reported details

Source-reported by Compute Atlas; not independently verified by DataCenterData. Provider wording is kept; long provider notes are shortened and marked …; unknown is not zero; none of these values is totaled, ranked or compared.

Electric utility
Dominion Energy VirginiaUtility as named by the provider.
Power source
MixedProvider label.
On-site generation
500 MW (source-reported)On-site figures often describe backup generators rather than primary supply; read the provider energy note.
Land area
250 acres (source-reported; parcel boundary not established)
Community response
Provider label: contestedCompute Atlas characterization, not a DataCenterData assessment. Open cited source →
AI-use label (provider)
likelyCompute Atlas classification, not a DataCenterData finding.
Announced
February 2026Provider-reported announcement date.

Provider notes

Energy. Former coal-fired plant (closed 2022) on PJM grid near Potomac River. TeraWulf plans 500 MW initial generation expansion; ultimate target 1 GW of on-site power to support 1 GW data center load while remaining net-positive energy supplier.

Community. Charles County Planning Commission voted to recommend denial of ZTA in March 2026 and again in June 2026 public hearing (four hours of resident testimony). Charles County Against Data Centers Coalition active. County has no explicit data center zoning; commissioners voted 3-2 to send proposed ZTA back to planning board.

What the source record says

Morgantown Generating Station is on the Potomac River near the Governor Harry W. Nice Memorial Bridge, Charles County MD. Acquisition funding and TeraWulf financial stability questioned by Maryland Office of People's Counsel (net losses $660M+ in 2025, 90% revenue from Bitcoin mining). Coordinates approximate. TeraWulf sought about $100M in Maryland state funds toward the Morgantown acquisition; the purchase price is withheld from FERC as confidential (FOIA Exemption 4), which Public Citizen is petitioning to disclose. No cooling design, water-withdrawal figure, confirmed subsidy, or job count has been publicly disclosed for the proposed AI campus. Re-checked 2026-09-10: overall record status correctly remains PROPOSED. Material development since lastUpdated (2026-07-23): FERC ruled 2026-07-29 that the ownership transfer of Morgantown Generating Station to TeraWulf is consistent with the public interest, but the order explicitly does not authorize data-center construction, new/repowered generation, or interconnection changes -- so 'proposed' remains the correct enum. Purchase price was kept confidential by FERC order (no investmentUsd figure obtainable). No water/cooling or jobs figures found this run. [Applier note 2026-09-10: the finding proposed only location.city, which the enrichment intent schema deliberately does not accept (enrichment fills street and postalCode only and cannot change a facility's city). Converted to a notes-only finding so the substantive research lands; the proposed city change needs a maintainer hand-edit.]

Capacity is not ranked or totaled here.

Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.

Status history supplied by the source

  1. 2026-02 · source-reported proposed

    TeraWulf announced acquisition of Morgantown Generating Station (250 buildable acres, ~210 MW current operational capacity) from existing owner. Acquisition pending FERC approval and third-party consents (expected Q2 or Q3 2026 closing). Zoning text amendment (ZTA) required. TeraWulf shifting from Bitcoin mining to AI/HPC data centers.

    Open cited source →

Sources and attribution

These sources are listed for the whole row. Unless a figure links to its own source, the provider does not mark which one gave it, so a figure may not appear in every source.

Adapted from Compute Atlas by Edward Kubiak, edition 1.34.1, under CC BY 4.0. Upstream ID terawulf-morgantown-charles-county-md. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added. Some locations in this layer are reported by the provider as derived from OpenStreetMap (© OpenStreetMap contributors, ODbL, https://www.openstreetmap.org/copyright) and Epoch AI (CC BY 4.0).

Compute Atlas 1.34.1 with retained prior rows and publication holds. This is a DataCenterData composite, not an unmodified publisher edition. This row uses the captured source from 1.34.1, source as of 2026-10-14T20:40:52.293Z.

No reviewed record is linked to this row yet.

That does not mean the row is wrong, and it does not mean no reviewed record exists for the same place. A link is added only when an identifier or source establishes the match.

Recorded information

What this page records, grouped by topic, with the source's units and qualifications. Company-reported values stay labeled as company-reported. Related listings are shown separately.

Licensed directory listing dcd-dir-001442

Licensed directory row. Licensed directory label. Source-reported and not independently verified.

Provider notes and the source narrative are printed on this page and are not repeated here.

Identity and relationships

  • Provider facility type: data center

    Provider facility type.

  • AI-use label (provider): likely

    Compute Atlas classification, not a DataCenterData finding.

Location and precision

  • MD · Charles (Approximate location)

Roles

  • Operator: TeraWulf

    Operator label as published by the provider; no parent company is inferred.

Lifecycle

  • Source-stated status: source-reported proposed

    Provider status label; not a DataCenterData finding that the facility is operating.

  • Announced: February 2026

    Provider-reported announcement date.

  • Status history: 2026-02 · source-reported proposed

    Status history supplied by the source.

Area, acreage and buildings

  • Land area: 250 acres (source-reported; parcel boundary not established)

Power capacity

  • Reported capacity: Planned: 1,000 MW (source-reported; boundary not independently verified; MW measure not stated by provider)

    Reproduced as the page prints it; not ranked or totaled; unknown is not zero.

  • Electric utility: Dominion Energy Virginia

    Utility as named by the provider.

  • Power source: Mixed

    Provider label.

  • On-site generation: 500 MW (source-reported)

    On-site figures often describe backup generators rather than primary supply; read the provider energy note.

Permits, incentives, jobs and proceedings

  • Community response: Provider label: contested

    Compute Atlas characterization, not a DataCenterData assessment.

Sources, dates, limitations and corrections

  • Provider update date: 2026-09-10

    Provider update date is not a DataCenterData verification date.

Not yet recorded here: Cooling, water, PUE and WUE · Connectivity · Services · Certifications and design ratings · Rack density · Availability · Specification links and contact.

Licensed values: adapted from Compute Atlas by Edward Kubiak under CC BY 4.0. Source-reported and not independently verified.

Update this profile with a public source. The request includes topics needing more information; this does not mean the facility lacks them. Corrections and additions are reviewed before publication.

Corrections

Report an error in this row →