Summary
Washington's Department of Ecology explains how it permits data centers' diesel backup generators: a notice of construction permit is required before a data center is built or expanded, and when required a health impact assessment of diesel exhaust and nitrogen dioxide must be reviewed first. The page notes that most Ecology-regulated data centers are in Quincy and the Wenatchee area, that local clean air agencies regulate data centers elsewhere, and it lists individual approval orders. It is informational; individual approval orders are facility permits.
Scope
The Washington Department of Ecology's "Data centers" air quality page states that Ecology issues air quality permits to data centers to limit pollution from diesel-powered backup generators and tracks the combined diesel exhaust impacts; that, when required, a data center must prepare a health impact assessment of its toxic air pollution (diesel exhaust and nitrogen dioxide), which Ecology must review before issuing the notice of construction permit required before a data center is built or expanded; that most data centers Ecology regulates are in Quincy and the Wenatchee area, with others regulated by local clean air agencies; and it lists Ecology approval orders by city. It is an informational agency page applying general air rules to data centers; it is not a data-center-specific rule.
- Geographic scope
- Washington
- Jurisdiction
- State
- Authority type
- Government agency
- Issuing authority
- Washington State Department of Ecology
Dates
- Adopted
- No adoption day is recorded
- Effective
- Not a binding measure
- Scheduled expiration
- No expiration date recorded
- Ended
- Not recorded as ended
- Completion condition
- None stated
- Source document
- The source page states no document date
- Last checked
- 5 October 2026
About this date
This record was last checked before the tracker date, 16 November 2026. An earlier check date does not by itself mean the record's status has changed.
What this does not establish
- The page is undated; no publication day is stored.
- The permit and health-impact requirements it describes come from generally applicable air rules, not a data-center-specific rule; a draft data-center General Order (2025) was not found on the page and is not part of this record.
- Data centers outside Ecology's jurisdiction are regulated by local clean air agencies, which were not reviewed.
Unresolved questions
None recorded.
Relationships
Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.
- No related action is recorded.
Sources
Primary source: Washington State Department of Ecology page on ecology.wa.gov