Reported geography
Source-reported location for IREN Woods County Campus.
Approximate source coordinates; this is not a parcel claim. Nearby source points are combined into one accessible target that opens this exact map scope. View these exact rows on the interactive map →
Source row snapshot
- Operator as published
- IREN (Iris Energy)
- Address and locality
- Alva · Woods County · Oklahoma
- Official metro area
- Outside an official metropolitan boundary
- Source-reported status
- proposed
- Provider facility type
- data center
- Reported capacity
- Planned: 1,600 MW (source-reported; boundary not independently verified; MW measure not stated by provider)
- Source freshness
- 10 September 2026
- Location precision
- approximate (provider label: exact; the provider's own note describes an approximate location)
- Compute Atlas confidence label
- reported (provider's classification; not a DataCenterData check)
- Stable directory ID
dcd-dir-000814
Reported details
Source-reported by Compute Atlas; not independently verified by DataCenterData. Provider wording is kept; long provider notes are shortened and marked …; unknown is not zero; none of these values is totaled, ranked or compared.
- Electric utility
- OG&E
- Power source
- Grid
- Land area
- 2,000 acres (source-reported; parcel boundary not established)
- AI-use label (provider)
- likely
Provider notes
Energy. Southwest Power Pool (SPP) grid; 1.6 GW allocation.
What the source record says
~2,000-acre land bank near Alva, Woods County, with a secured 1.6 GW power allocation on the Southwest Power Pool grid; initial power ramp scheduled for 2028. IREN's land-bank expansion beyond its operational Texas campuses (Childress, Sweetwater). Single-tracker source → confidence reported. Coordinates are the Alva area centroid. Capacity re-sourced 2026-08-08: IREN's own Oklahoma page states "1,600 MW", "2,000 Acres" and "2028 Substation Energization", status "IN DEVELOPMENT" — replacing an aggregator listing as the basis for the figure. Public-reception check (2026-09-10): Checked baxtel.com's project profile (2026-09-10) -- it covers only technical/permitting facts (2,000-acre site on the SPP grid) plus one unrelated statewide article (Oklahoma's data-center ratepayer-protection bill, 2026-05-16). No hearing, resident reaction, or local-official statement specific to the Woods County/Alva site was found in this source.
Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.
Status history supplied by the source
- 2026 · source-reported proposed
IREN land bank of ~2,000 acres in Woods County with a secured 1.6 GW power allocation on the SPP grid; power ramp from 2028
Sources and attribution
These sources are listed for the whole row. Unless a figure links to its own source, the provider does not mark which one gave it, so a figure may not appear in every source.
- IREN Woods County Oklahoma · Baxtel
- HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · Oak Ridge National Laboratory (ORNL) / HIFLD
- IREN Oklahoma data center — 1,600 MW, 2,000 acres, 2028 substation energization · IREN
Adapted from Compute Atlas by Edward Kubiak, edition 1.34.1, under CC BY 4.0. Upstream ID iren-woods-county-ok. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added. Some locations in this layer are reported by the provider as derived from OpenStreetMap (© OpenStreetMap contributors, ODbL, https://www.openstreetmap.org/copyright) and Epoch AI (CC BY 4.0).
Compute Atlas 1.34.1 with retained prior rows and publication holds. This is a DataCenterData composite, not an unmodified publisher edition. This row uses the captured source from 1.34.1, source as of 2026-10-14T20:40:52.293Z.
That does not mean the row is wrong, and it does not mean no reviewed record exists for the same place. A link is added only when an identifier or source establishes the match.
Recorded information
What this page records, grouped by topic, with the source's units and qualifications. Company-reported values stay labeled as company-reported. Related listings are shown separately.
Licensed directory listing dcd-dir-000814
Licensed directory row.
Provider notes and the source narrative are printed on this page and are not repeated here.
Identity and relationships
- Provider facility type: data center
Provider facility type.
- AI-use label (provider): likely
Compute Atlas classification, not a DataCenterData finding.
Location and precision
- Alva, OK · Woods (Approximate location)
Roles
- Operator: IREN (Iris Energy)
Operator label as published by the provider; no parent company is inferred.
Lifecycle
- Source-stated status: source-reported proposed
Provider status label; not a DataCenterData finding that the facility is operating.
- Status history: 2026 · source-reported proposed
Status history supplied by the source.
Area, acreage and buildings
- Land area: 2,000 acres (source-reported; parcel boundary not established)
Power capacity
- Reported capacity: Planned: 1,600 MW (source-reported; boundary not independently verified; MW measure not stated by provider)
Reproduced as the page prints it; not ranked or totaled; unknown is not zero.
- Electric utility: OG&E
Utility as named by the provider.
- Power source: Grid
Provider label.
Sources, dates, limitations and corrections
- Provider update date: 2026-09-10
Provider update date is not a DataCenterData verification date.
Not yet recorded here: Cooling, water, PUE and WUE · Connectivity · Services · Certifications and design ratings · Rack density · Availability · Specification links and contact · Permits, incentives, jobs and proceedings.
Licensed values: adapted from Compute Atlas by Edward Kubiak under CC BY 4.0. Source-reported and not independently verified.
Update this profile with a public source. The request includes topics needing more information; this does not mean the facility lacks them. Corrections and additions are reviewed before publication.