This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.
Reported geography
Source-reported location for Project Springbank (Atlas Development Bartow County Campus).
Approximate source coordinates; this is not a parcel claim. Nearby source points are combined into one accessible target that opens this exact map scope. View these exact rows on the interactive map →
Source row snapshot
- Operator as published
- Atlas Development LLC
- Address and locality
- Barnsley Gardens Road · Adairsville · Bartow County · Georgia
- Official metro area
- Atlanta-Sandy Springs-Roswell, GA
- Source-reported status
- cancelled
- Provider facility type
- data center
- Reported capacity
- Planned: 432 MW (source-reported; boundary not independently verified; MW measure not stated by provider)
- Source freshness
- 30 September 2026
- Location precision
- approximate
- Compute Atlas confidence label
- confirmed (provider's classification; not a DataCenterData check)
- Stable directory ID
dcd-dir-000105
Reported details
Source-reported by Compute Atlas; not independently verified by DataCenterData. Provider wording is kept; long provider notes are shortened and marked …; unknown is not zero; none of these values is totaled, ranked or compared.
- Cooling
- Not established
- Reported water use
- 0.015 million gallons per day (source-reported)
- Land area
- 630 acres (source-reported; parcel boundary not established)
- Announced investment
- $4.5 billion
- Community response
- Provider label: opposed
- Announced
- February 2025
Provider notes
Water. DRI #4403 estimates 0.015 MGD (15,000 gallons per day) water demand from Bartow County and zero sewage flow, and describes closed-loop technology.
Community. Residents organized against the rezoning. A change.org petition, "Halt Proposed Land Use Change from Agriculture to Industrial in Bartow County", co-founded by Josh Cauthen, had 1,280 signatures by 2025-03-11 and 1,723 by 2025-03-21, and was reported at over 2,000 by the 2025-04-28 hearing. "The local community is in lockstep against the proposed rezoning," Cauthen said. …
These reviews flag conflicting scope, inconsistent source text or support that has not been established. A withheld value may appear in the explanation, but is not displayed as an established field. The upstream row remains attributed under Sources.
- Cooling: Previously held pending provider-field review. The concern has not been resolved by an independent source review for this captured edition; the field remains withheld.
What the source record says
Six buildings totaling 2,274,000 sq ft (about 379,000 sq ft each), per DRI #4403, which states the project "will utilize closed loop technology to reduce water and sewer demand." The DRI states a build-out value of $4,500,000,000 and completion in December 2031, and leaves the electrical-load and energy-provider fields blank. The 432 MW figure (six buildings of up to 78 MW each) is from press reporting on the site plan, not the DRI. Property owners per the DRI: The Darryl William Edwards Living Revocable Trust, King Curtis LLC and Riverside NVR LLC. Acreage: the county's minutes and the Daily Tribune give 630 acres for the rezoning request (to Business Park District); earlier press gave 588. Coordinates are the point stated in the DRI filing, not a surveyed site centroid. No named end-user operator was attached to the project. Distinct from Atlas Development's later Stiles Road application off Euharlee Road (withdrawn December 2025).
Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.
Status history supplied by the source
- 2025-02-14 · source-reported proposed
Bartow County submitted Development of Regional Impact #4403 ("Project Springbank", developer Atlas Development LLC) to the Georgia DCA; determined to warrant regional review 2025-02-24.
- 2025-05-13 · source-reported cancelled
Atlas Development withdrew rezoning application Z-25-00006 through its attorney on 2025-05-13, the day before the sole commissioner was to rule, after the Bartow County Planning Commission voted 6-1 on 2025-04-28 to recommend denial. Atlas gave no reason. No refiling of this site has been found.
Sources and attribution
These sources are listed for the whole row. Unless a figure links to its own source, the provider does not mark which one gave it, so a figure may not appear in every source.
- New data center proposal in Bartow would require as much power as 324K homes · Rome News-Tribune / Northwest Georgia News
- Data Center Operator Planning $4.5B Bartow County Campus · Connect CRE
- Springbank data center application withdrawn · Daily Tribune News (Cartersville)
- Bartow County planning commission votes to recommend denying data center rezoning request · FOX 5 Atlanta
- Development of Regional Impact #4403, Project Springbank — initial form (location, owner, size) · Georgia Department of Community Affairs
- Development of Regional Impact #4403, Project Springbank — additional information (value, water, sewer) · Georgia Department of Community Affairs
- Petition started, town hall set regarding proposed data center · Daily Tribune News (Cartersville)
- Minutes, Public Meeting, Bartow County Commissioner, May 14, 2025 — Z-25-00006 withdrawn · Bartow County Commissioner's Office
- Town hall held, public hearing postponed for proposed data center · Daily Tribune News (Cartersville)
- Backlash over proposed data center near Adairsville · FOX 5 Atlanta
Adapted from Compute Atlas by Edward Kubiak, edition 1.34.1, under CC BY 4.0. Upstream ID atlas-project-springbank-adairsville-ga. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added. Some locations in this layer are reported by the provider as derived from OpenStreetMap (© OpenStreetMap contributors, ODbL, https://www.openstreetmap.org/copyright) and Epoch AI (CC BY 4.0).
Compute Atlas 1.34.1 with retained prior rows and publication holds. This is a DataCenterData composite, not an unmodified publisher edition. This row uses the captured source from 1.34.1, source as of 2026-10-14T20:40:52.293Z.
That does not mean the row is wrong, and it does not mean no reviewed record exists for the same place. A link is added only when an identifier or source establishes the match.
Recorded information
What this page records, grouped by topic, with the source's units and qualifications. Company-reported values stay labeled as company-reported. Related listings are shown separately.
Licensed directory listing dcd-dir-000105
Licensed directory row.
Provider notes and the source narrative are printed on this page and are not repeated here.
Identity and relationships
- Provider facility type: data center
Provider facility type.
Location and precision
- Barnsley Gardens Road, Adairsville, GA · Bartow (Approximate location)
Roles
- Operator: Atlas Development LLC
Operator label as published by the provider; no parent company is inferred.
Lifecycle
- Source-stated status: source-reported cancelled
Provider status label; not a DataCenterData finding that the facility is operating.
- Announced: February 2025
Provider-reported announcement date.
- Status history: 2025-02-14 · source-reported proposed
Status history supplied by the source.
- Status history: 2025-05-13 · source-reported cancelled
Status history supplied by the source.
Area, acreage and buildings
- Land area: 630 acres (source-reported; parcel boundary not established)
Power capacity
- Reported capacity: Planned: 432 MW (source-reported; boundary not independently verified; MW measure not stated by provider)
Reproduced as the page prints it; not ranked or totaled; unknown is not zero.
Cooling, water, PUE and WUE
- Cooling: Not established
The provider reports water information but no cooling type.
- Reported water use: 0.015 million gallons per day (source-reported)
Whether this is metered use, a permit limit or a request is not established; see the provider water note.
Permits, incentives, jobs and proceedings
- Announced investment: $4.5 billion
Announced figure; whether it covers one building, a campus or a multi-phase program is not established.
- Community response: Provider label: opposed
Compute Atlas characterization, not a DataCenterData assessment.
Sources, dates, limitations and corrections
- Provider update date: 2026-09-30
Provider update date is not a DataCenterData verification date.
Not yet recorded here: Connectivity · Services · Certifications and design ratings · Rack density · Availability · Specification links and contact.