Consumers Energy electric service territory, Michigan

MPSC Case U-21859: rehearing of Consumers Energy large load terms denied

Enacted legislation or regulation

In effect This instrument is recorded as currently in effect as of the dataset date.

Scope

The Michigan Public Service Commission's order of 19 February 2026 in Case No. U-21859 denies the Michigan Department of Attorney General's petition for rehearing of the Commission's 6 November 2025 order approving large load amendments to Consumers Energy's Rate GPD, a case that began as an application to add a Data Center Provision, and reserves jurisdiction. It applies only in Consumers Energy's electric service territory.

Geographic scope
Consumers Energy electric service territory, Michigan
Jurisdiction
State
Authority type
Regulator or commission
Issuing authority
Michigan Public Service Commission

Dates

Adopted
19 February 2026
Effective
Effective date not stated in the source
Scheduled expiration
None scheduled
Ended
Not recorded as ended
Completion condition
None stated
Source document
19 February 2026
Last checked
23 September 2026 (earlier than tracker date 5 October 2026; not an automatic status change)

Summary

On 19 February 2026 the Michigan Public Service Commission denied the Attorney General's petition for rehearing of its 6 November 2025 order in Case No. U-21859, which approved end-use-neutral large load terms in Consumers Energy's Rate GPD for loads of 100 MW or more. The Commission found the earlier order adequately explained its eligibility threshold and reserved jurisdiction.

What this does not establish

  • This is a rehearing decision; the large load terms themselves are in the 6 November 2025 order, which is a separate record.
  • The approved provisions are end-use neutral rather than limited to data centers.
  • The effective date of the order is not stated in its text; the adoption date is the Commission meeting date.
  • Whether any party appealed to the courts was not checked; courts.michigan.gov disallows automated access in its robots.txt.

Unresolved questions

None recorded.

Relationships

Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.

Sources

Primary source

https://adms.apps.lara.state.mi.us/Mpsc/ViewCommissionOrderDocument/27373

    Back to the policy tracker ยท Michigan policy module