Consumers Energy electric service territory, Michigan

MPSC Case U-21859: Consumers Energy Rate GPD large load terms

Enacted legislation or regulation

In effect This instrument is recorded as currently in effect as of the dataset date.

Scope

The Michigan Public Service Commission's order of 6 November 2025 in Case No. U-21859 approves large load amendments to Consumers Energy's General Primary Demand Rate (Rate GPD), on an application that sought to add a Data Center Provision. The order applies the new large load provisions to loads of 100 MW or greater, makes eligibility end-use neutral rather than limited to data center customers, sets a 15-year contract term after a ramp-up period of no more than five years and an 80% minimum billing demand, adopts a $100,000 upfront application fee reconciled to actual costs, and directs Consumers to file tariff sheets within 30 days. It applies only in Consumers Energy's electric service territory.

Geographic scope
Consumers Energy electric service territory, Michigan
Jurisdiction
State
Authority type
Regulator or commission
Issuing authority
Michigan Public Service Commission

Dates

Adopted
6 November 2025
Effective
Effective date not stated in the source
Scheduled expiration
See completion condition
Ended
Not recorded as ended
Completion condition
The order states no expiration.
Source document
6 November 2025
Last checked
23 September 2026 (earlier than tracker date 5 October 2026; not an automatic status change)

Summary

On 6 November 2025 the Michigan Public Service Commission approved, in Case No. U-21859, large load terms in Consumers Energy's Rate GPD after a contested case that began as a request to add a Data Center Provision. The terms apply to loads of 100 MW or more regardless of end use, with a 15-year contract term after a ramp-up of up to five years, an 80% minimum billing demand and a $100,000 upfront fee. The order notes that data centers are the only customers likely to be assigned to these provisions in the near future.

What this does not establish

  • The approved large load provisions are end-use neutral; the order says eligibility should not be limited to data center customers, while noting that data centers are the only potential customers likely to be assigned to them in the near future.
  • The effective date of the order is not stated in its text; the adoption date is the Commission meeting date.
  • The compliance tariff sheets filed after the order, and their effective date, were not opened; the Commission-hosted rate book is on michigan.gov, which does not permit automated access.
  • Other provisions of the order, including aggregation of commonly owned sites, exit fee, collateral, notice periods, cost allocation studies and reporting, are not restated.
  • Whether any party appealed to the courts was not checked; courts.michigan.gov disallows automated access in its robots.txt.

Unresolved questions

  • The effective date of the Rate GPD compliance tariff sheets.

Relationships

Supersession means a later instrument replaces the earlier legal effect. Repeal links identify the repeal instrument and the measure it ends. A later implementation or related letter is not treated as a replacement unless the record says so.