Sentinel Data Centers Androscoggin Mill Campus, Jay

source-reported cancelled

Sentinel Data Centers

Jay · Franklin County · Maine

Reported planned 82 MWSource updated 2026-06exact location (provider label) · provider confidence label: reported
How to read this page

This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.

Reported geography

Source-reported location for Sentinel Data Centers Androscoggin Mill Campus, Jay.

Exact source coordinates (provider label); this is not a parcel claim. Nearby source points are combined into one accessible target that opens this exact map scope. View these exact rows on the interactive map →

Exact source coordinates Approximate or representative coordinates Nearby-point group. This relative plot uses only source-supplied points, makes no parcel claim and loads no map tiles.

Source row snapshot

Operator as published
Sentinel Data Centers
Address and locality
Jay · Franklin County · Maine
Official metro area
Outside an official metropolitan boundary
Source-reported status
cancelled
Provider facility type
data center
Reported capacity
Planned: 82 MW (source-reported; boundary not independently verified; MW measure not stated by provider)
Source freshness
2026-06
Location precision
exact (provider label)
Compute Atlas confidence label
reported (provider's classification; not a DataCenterData check)
Stable directory ID
dcd-dir-001306

Reported details

Source-reported by Compute Atlas; not independently verified by DataCenterData. Provider wording is kept; long provider notes are shortened and marked …; unknown is not zero; none of these values is totaled, ranked or compared.

Electric utility
Central Maine PowerUtility as named by the provider.
Power source
SolarProvider label.
Cooling
Closed-loopProvider label.
Reported water use
0.3 million gallons per day (source-reported)Whether this is metered use, a permit limit or a request is not established; see the provider water note.
Announced investment
$550 millionAnnounced figure; whether it covers one building, a campus or a multi-phase program is not established.
Announced jobs
137 permanent · 900 constructionAnnounced figures; whether they cover one building, a campus or a multi-phase program is not established. Open cited source →
Community response
Provider label: supportedCompute Atlas characterization, not a DataCenterData assessment. Open cited source →
AI-use label (provider)
likelyCompute Atlas classification, not a DataCenterData finding.
Announced
January 2025Provider-reported announcement date.

Provider notes

Energy. On-site solar generates up to 150MW; facility draws no more than 25MW from grid on cloudy days. Maine PUC approved use of on-site hydroelectric power. Cooling system proposed ~300,000 gal/day of Androscoggin River water (less than 1% of former mill usage).

Water. Closed-loop system; ~300,000 gallons/day from Androscoggin River to replace evaporation, compared to 35-40 million gallons/day used by former paper mill.

Community. Jay Select Board voted 4-0 to support project; town and RSU 73 school board support expanded tax base. No public opposition recorded at local approval votes. Legislative battle over moratorium resolved in project's favor after Gov. Mills vetoed LD 307 and veto was sustained June 2026. Sentinel Data Centers notified JGT2 in June 2026 of intent not to move forward; project placed on hold indefinitely pending other operators.

What the source record says

Sentinel Data Centers LLC is headquartered in New York City. JGT2 Redevelopment purchased the former Pixelle Specialty Solutions mill in December 2023. ~425,000 sq ft of obsolete mill buildings demolished; paper machines shipped to Pakistan. In June 2026 Sentinel notified JGT2 of intent not to move forward; no permits were issued and no groundbreaking was held. JGT2 is seeking other operators for the site.

Capacity is not ranked or totaled here.

Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.

Status history supplied by the source

  1. 2025-01 · source-reported proposed

    JGT2 Redevelopment proposes $550M Sentinel Data Centers colocation campus at former Androscoggin Mill (closed 2023 after digester explosion, property purchased December 2023)

    Open cited source →

  2. 2026-04 · source-reported proposed

    Jay Select Board votes 4-0 to support project and prepare letter of support; town meeting warrant approved; Maine Legislature sustains Gov. Mills' veto of moratorium bill LD 307; remediation and demolition underway

    Open cited source →

  3. 2026-06 · source-reported proposed

    Sentinel Data Centers notifies JGT2 Redevelopment of intent not to move forward; planned July 2026 groundbreaking cancelled; project on hold indefinitely; JGT2 pursuing other operators

    Open cited source →

  4. 2026-06 · source-reported cancelled

    Sentinel Data Centers withdrew from the Androscoggin Mill project and halted work in June 2026 (after Gov. Mills vetoed a statewide 20MW+ data-center moratorium that had been intended to protect it). Per the JGT2 mill-redevelopment team, the site itself is 'not dead' — the 82MW (expandable) power infrastructure and rail access remain, and JGT2 is seeking a new data-center operator or industrial tenant.

    Open cited source →

Sources and attribution

These sources are listed for the whole row. Unless a figure links to its own source, the provider does not mark which one gave it, so a figure may not appear in every source.

Adapted from Compute Atlas by Edward Kubiak, edition 1.34.1, under CC BY 4.0. Upstream ID sentinel-jay-me. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added. Some locations in this layer are reported by the provider as derived from OpenStreetMap (© OpenStreetMap contributors, ODbL, https://www.openstreetmap.org/copyright) and Epoch AI (CC BY 4.0).

Compute Atlas 1.34.1 with retained prior rows and publication holds. This is a DataCenterData composite, not an unmodified publisher edition. This row uses the captured source from 1.34.1, source as of 2026-10-14T20:40:52.293Z.

No reviewed record is linked to this row yet.

That does not mean the row is wrong, and it does not mean no reviewed record exists for the same place. A link is added only when an identifier or source establishes the match.

Recorded information

What this page records, grouped by topic, with the source's units and qualifications. Company-reported values stay labeled as company-reported. Related listings are shown separately.

Licensed directory listing dcd-dir-001306

Licensed directory row. Licensed directory label. Source-reported and not independently verified.

Provider notes and the source narrative are printed on this page and are not repeated here.

Identity and relationships

  • Provider facility type: data center

    Provider facility type.

  • AI-use label (provider): likely

    Compute Atlas classification, not a DataCenterData finding.

Location and precision

  • Jay, ME · Franklin (Exact location)

Roles

  • Operator: Sentinel Data Centers

    Operator label as published by the provider; no parent company is inferred.

Lifecycle

  • Source-stated status: source-reported cancelled

    Provider status label; not a DataCenterData finding that the facility is operating.

  • Announced: January 2025

    Provider-reported announcement date.

  • Status history: 2025-01 · source-reported proposed

    Status history supplied by the source.

  • Status history: 2026-04 · source-reported proposed

    Status history supplied by the source.

  • Status history: 2026-06 · source-reported proposed

    Status history supplied by the source.

  • Status history: 2026-06 · source-reported cancelled

    Status history supplied by the source.

Power capacity

  • Reported capacity: Planned: 82 MW (source-reported; boundary not independently verified; MW measure not stated by provider)

    Reproduced as the page prints it; not ranked or totaled; unknown is not zero.

  • Electric utility: Central Maine Power

    Utility as named by the provider.

  • Power source: Solar

    Provider label.

Cooling, water, PUE and WUE

  • Cooling: Closed-loop

    Provider label.

  • Reported water use: 0.3 million gallons per day (source-reported)

    Whether this is metered use, a permit limit or a request is not established; see the provider water note.

Permits, incentives, jobs and proceedings

  • Announced investment: $550 million

    Announced figure; whether it covers one building, a campus or a multi-phase program is not established.

  • Announced jobs: 137 permanent · 900 construction

    Announced figures; whether they cover one building, a campus or a multi-phase program is not established.

  • Community response: Provider label: supported

    Compute Atlas characterization, not a DataCenterData assessment.

Sources, dates, limitations and corrections

  • Provider update date: 2026-06

    Provider update date is not a DataCenterData verification date.

Not yet recorded here: Area, acreage and buildings · Connectivity · Services · Certifications and design ratings · Rack density · Availability · Specification links and contact.

Licensed values: adapted from Compute Atlas by Edward Kubiak under CC BY 4.0. Source-reported and not independently verified.

Update this profile with a public source. The request includes topics needing more information; this does not mean the facility lacks them. Corrections and additions are reviewed before publication.

Corrections

Report an error in this row →